You are on page 1of 20

Issue 28 - April 2020

International Quarterly provides informative


and practical information regarding legal and
commercial developments in construction
and energy sectors around the world.

Inside this issue:

• Actions for Covid-19 on your


construction project

• Covid-19, FIDIC and


Construction Contracts

• Coronavirus and Construction


Contracts

• Getting termination right: PBS


Energo A.S. v Bester Generacion
UK Limited & Anor [2020] EWHC
223 (TCC) and the FIDIC Silver
Book

• Unforeseeable ground
conditions and the FIDIC Silver
Book

• Prejudice without Prejudice

www.fenwickelliott.com
01 International Quarterly

Welcome to Issue 28

Jeremy Glover
Partner
jglover@fenwickelliott.com

When we started planning the current That article is followed by one by Jon The second half of IQ takes a more
edition of IQ, the world was a very Miller again about the coronavirus traditional look at recent
different place. It is interesting to see and its possible impact on developments in the construction
on the one hand how quickly things construction contracts. Although the legal world. In February 2020, a rare
change, yet on the other from a article was originally written with the event occurred, the release of a TCC
personal point of view, looking out of domestic UK market in mind the judgment relating to a project
my window in Greenwich, London, time practical points it makes are relevant (concerning a biomass energy plant in
is moving slowly and events of a week and worthy of thought in any North Wales that was never built)
ago seem more like a month. jurisdiction. Jon has also been busy on using the FIDIC Form, here an
the webinar front. On 26 March 2020, amended 1999 Silver Book. I have
in association with Building he gave a written a short note about
With the pace of change in mind, we webinar entitled: “Covid-19 and its “unforeseeable ground conditions”
have given first place in this edition IQ impact on construction: the legal whilst Jesse Way has written about
rightly and obviously to how we can view.” The webinar is available termination. Finally Catherine
help you and in our lead article on-demand here: https://www. Simpson has written about what
Nicholas Gould addresses some of the workcast.com/ happens when without prejudice
key points that should be taken into register?cpak=6463352161686209. documents appear in an adjudication,
consideration with regards to the looking at the legal position in
uncertainty about the impact that Scotland and the UAE.
Covid-19 is having and will have on We will be producing more webinars
current projects and businesses. That and podcasts over the next few
short article is followed by an article by weeks, so please keep an eye open for Stay safe
me about force majeure with an eye details.
on the FIDIC Form and MENA region.
Jeremy

CORONAVIRUS (COVID-19) STATEMENT


Fenwick Elliott is closely monitoring the These measures include a working Many thanks, in advance, for your
outbreak of Coronavirus (COVID-19) from home policy for all partners and understanding during these most
and taking relevant guidance to ensure staff. Our London and Dubai offices difficult of times.
we respond as efficiently and are both currently closed. Meetings
effectively as possible. are taking place via video
conferencing.
Where possible, we intend to operate
on the basis of ‘business as usual’, We are committed to delivering
whilst ensuring the health and welfare prompt, reliable and pragmatic legal
of our staff, stakeholders, clients and advice to our clients throughout these
their families remains our utmost difficult times, and such measures will
priority in these unprecedented times. help to ensure this.
We are adopting government
guidelines for staying at home,
We will continue to keep you updated
heightened hygiene and we will be
with the company’s plans and
adopting a number of measures to
response to the spread of COVID-19,
ensure our staff, clients and suppliers
as it develops.
are kept safe.
02 International Quarterly

Actions for Covid-19 on your


construction project

Nicholas Gould
Partner
ngould@fenwickelliott.com

There is of course some uncertainty 4. Notices – look at the contract 8. Insurance – is there any existing
about the impact that Covid-19 to see what the notice needs cover for disruption to your
is having and will have on current to contain and the deadline for business?
projects and businesses. From the issuing it. Are multiple notices
frequent questions arising this week, required, perhaps for the initial 9. Frustration – it is unlikely to work
consideration should be given to: warning, then for details of the in practice, but might be worth
claim and evidence as well as considering over the coming
regular updates? weeks.

1. Site lockdown – what is the 5. Evidence – gather evidence 10. Business as usual – it might seem
impact on your contracts, the as it becomes available and a long way off, but consider with
workforce and the supply chain? document the problems faced in your contracting parties how you
What rights do you have for relief correspondence and notices to will plan for resuming work once
under the contracts, and who the other party. the effects have subsided.
might be bringing claims against
you? 6. Extension of time and money 11. Much depends on the contract
– check the contract for your terms and the actual impact
2. Force majeure – is Covid-19 a right to an extension of time and on your projects and business. If
force majeure event under your possible financial claims. Are more help is needed let me know.
contract? Check the contract separate notices required and,
to see what needs to be proved. again, how long after the event
Gather evidence and notify do you have to serve the notice?
within the contract timescales.
7. Health and safety – the health
3. The impact of notifying – consider and safety of the workforce is
your contractual rights before paramount. Are there enough
notifying a force majeure event. senior people on the site
There might be an initial right to to manage the works, and
suspend followed by limited relief adequate handwashing facilities?
(time but no money).
03 International Quarterly

Covid-19, FIDIC and Construction


Contracts

Jeremy Glover
Partner
jglover@fenwickelliott.com

One of the potential difficulties with majeure event has occurred, and the Force Majeure in the MENA Region
international projects is that the event must be beyond the control of Force majeure is treated in a broadly
contracts entered into are governed the party relying on the clause. Force similar way across MENA, although
by laws which may be unfamiliar majeure excuses what would probably it is always important to check the
to one or other of the contracting otherwise be a breach and effectively provisions of the Civil Code for the
parties. For example, there is a suspends temporarily an obligation jurisdictions where your contract is
difference in the way that force to perform the Works, but it may based.
majeure is treated in common and not give rise to any compensation/
civil law jurisdictions. Whilst most loss and expense unless provided for Force majeure under UAE law
civil codes make provisions for force under the contract. The usual position is that parties
majeure events, at common law, are free to agree the terms of
force majeure is not a term of art and There is no established meaning their contract provided they do
its meaning is far from clear. No force under the common law of force not conflict with the mandatory
majeure provision will be implied in majeure, so every force majeure provisions of the UAE Civil Code. With
the absence of specific contractual clause turns on the words used. This construction contracts, it is only if
provisions, and the extent to which also means that for force majeure to your contract makes no provision for
the parties deal with unforeseen apply there must be a specific clause force majeure or exceptional events,
events will be defined in the contract in your contract, whether it is called then you must look to the civil code.
between them. Thus without force majeure or something else. Whilst, there is no specific definition
a specific clause, there will not In civil jurisdictions force majeure of force majeure under UAE law, as
necessarily be relief for force majeure is a recognised legal concept and noted above, Article 273(1) lays stress
events. The current pandemic caused most civil codes make provision for on performance being impossible:
by Covid-19 has generated much it, for example Article 273 of the
discussion about force majeure and UAE Civil Code. Generally, in the “In contracts binding on both
this article looks at the position under UAE force majeure is given a narrow parties, if force majeure supervenes
the FIDIC form of contract and in the definition with stress on the need for which makes the performance
UAE and Qatar. the event to make performance of of the contract impossible, the
the obligation impossible. Elsewhere corresponding obligation shall
Force Majeure under civil and in the Middle East, in the case of cease, and the contract shall be
common laws National Oil Corp v Libyan Sun Oil Co, automatically cancelled”.
a Tribunal held that US sanctions,
Whatever your jurisdiction, the in terms of the use of American If the force majeure event renders
contract wording is, as always, personnel and technology, did not only part of an obligation impossible
crucial. In broad terms the intention render performance impossible, to perform, then only that only
of a force majeure clause is to provide since other companies were able to that part of the contract will be
for what happens where there is perform, through reliance on citizens cancelled. The Abu Dhabi Court of
non-performance which is caused from other countries and using non- Cassation case No. 13/2010 laid stress
by events beyond the control of the US technology. The fact that the US on it being “absolutely impossible”
party/parties. Most force majeure sanctions made performance more to perform the obligations of the
clauses usually suspend the obligation difficult was not enough. contract by reason of the force
to perform the contract when a force majeure event. Impossible means
04 International Quarterly

something different to that codified in the KSA, for public sector 19 of the earlier edition which was
which makes performance merely contracts, Article 51 of the 2006 headed ‘‘Force Majeure’’.
“burdensome.” Procurement Law provides for the
extension of a contract period (and Definition
The Civil Code provisions relating to the waiver of any penalty for delay)
Muqawala contracts (which include “if the delay is due to unforeseen However, the scheme of both forms
construction contracts), make similar circumstances or for reasons remains the same, with the party
provision. Article 893 provides that beyond the contractor’s control, affected, usually the contractor,
“when an excuse arises that prevents provided that the period of delay entitled to an extension of time and
the execution of the contract, or is proportionate to these reasons”. (with exceptions) additional cost
the completion of its execution, any More generally, whilst the court do where an “exceptional event” occurs.
of the contracting parties may ask recognise force majeure provisions, To constitute an exceptional event,
for its rescission or termination”. the emphasis is on exceptional events the following needs to have occurred:
Article 894 deals with compensation, which are impossible not merely more
noting that where a contractor has burdensome or expensive. Therefore (i) There must be an event or
started the execution of the work potentially a contract can be voided circumstance;
and then became unable to carry it provided a specific event took (ii) The event/circumstance must
out “for a reason beyond his control, place which was unforeseeable and be beyond the control of the party
he shall be entitled to value of the unavoidable as well as making the affected;
completed work, in addition to the contract impossible to perform. (iii) The party affected could not
expenses disbursed for its execution have foreseen or provided against the
to the extent of the benefit that the Force majeure under Qatari Law event/circumstance before entering
masters derives from such work”. If your contract makes no provision into the contract nor avoided it once
for force majeure or exceptional it had arisen;
Whilst the Civil Code makes no events, then you must look to the civil (iv) The event/circumstance was not
mention of giving notice, the code. Again, as with the UAE, there the fault of the other party; about
underlying requirement to act in is no definition under Qatari law for which,
good faith (Article 246) would require force majeure. Article 204 of the Civil (v) Proper notice in accordance with
that timely and clear notice is given Code provides that if a person can the relevant sub-clause has been
explaining what has happened and demonstrate that a loss has arisen given.
also that steps are taken to reduce due to an external cause not of their
the impact of the event and reduce making, that party will not be liable Although both FIDIC editions list
and losses. for that unless there is agreement some exceptional events, these
to the contrary. Article 258 permits do not include specific reference
Force majeure in the KSA agreement to the contrary allowing to events such as “epidemic” or
parties to allocate the risk for force “pandemic”, but the list is specifically
The Kingdom of Saudi Arabia’s majeure how they choose, usually to stated to be examples only. The key
(KSA’s”) legal system is based the contractor. is that the above conditions are
on the principles of Sharia Law satisfied.
which, following the Hanabali And again as throughout the MENA
school of Islamic interpretation, region, there is an emphasis on the Common Law/Civil Law
adopts a fundamentalist and literal event being impossible (and not
interpretation of the teachings of merely more difficult) with Article As noted above, in civil jurisdictions
the Qur’an. This means that the 188 of the Qatari Civil Code stating force majeure is a recognised legal
way in which Saudi courts regulate that “if fulfillment of the obligation concept and most civil codes make
contractual relationships is therefore becomes impossible due to some provisions for it. Therefore, the
strikingly different from the common external cause” then the contract change to ‘‘exceptional event’’ should
and civil law systems. Whilst Parties may be rescinded. be treated with some care as it
are free to contract with each other, might cause confusion as to whether
the degree of freedom with which Force Majeure and the FIDIC Form the term should be interpreted
they can do so is governed by certain of Contract differently to force majeure or not. It
prohibitions in the Qur’an. If the is important to consider the wording
provisions of your contract violate the The 1999 and 2017 editions of the of the clause carefully against the
fundamental principles of Sharia law FIDIC Form treat force majeure in definition to be found in the relevant
then it is likely that they will not be slightly different ways. Clause 18 code. Does it simply duplicate what is
enforced by the Saudi courts. of the 2017 edition is now headed usually provided for or does it enlarge
Whilst in general the laws are not “Exceptional Events”, replacing Clause the scope of the meaning and
05 International Quarterly

application of force majeure? days, the affected Party is excused Form, the contractor is entitled
At common law, as described above, performance only from the date on to an extension of time for “[u]
the confusion appears less likely to which the Notice is received. nforeseeable shortages in the
arise since ‘‘force majeure’’ is not availability of personnel or Goods
a term of art. No force majeure Extension of Time (or Employer-Supplied Materials,
provision is implied in the absence of if any) caused by epidemic...” As
specific contractual provisions and If the force majeure event has has already been demonstrated
the extent to which the parties deal caused delay, then subject to a globally, most governments have
with unforeseen events will be defined contractor using “all reasonable extensive powers to deal with health
in the contract between them. If endeavors to minimize any delay in emergencies which may lead to the
there is no provision, there will be no the performance of the Contract shutdown of a project or factory
relief. as a result of Force Majeure”, the supplying materials. That is provided
contractor should be entitled to the contractor has complied with
Optional Termination an extension of time. However, the the strict 28-day notice provisions.
contractor may not be entitled to Any shortage of personnel or goods
Both editions of the FIDIC Form claim costs as a result of covid-19. would have to be shortage of a
provide for optional termination if Under the 1999 FIDIC Form, sub- nature unforeseen by the experienced
the execution of “substantially all the clause 19.4 states that a contractor contractor and that contractor must
Works” is prevented for a continuous is only entitled Cost if the event is of also be able to demonstrate both
period of 84 days (or multiple periods the kind described in sub-paragraphs shortages in availability of personnel
which total 140 days). (i) to (iv) of sub-clause 19.1. These or goods and how this caused delay.
only include war and hostilities Sub-clause 8.5 of the 1999 Red Book
Notice (whether war be declared or not), (or 8.6 of the 2017 edition) also
rebellion and terrorism, riot or strike refers to delays caused by authorities,
Inevitably with FIDIC, proper notice and “munitions of war”, not natural noting that if the contractor has
must be given. Under the 1999 disaster or epidemics. A similar clause “diligently followed” the procedures
edition notice must be given within 14 can be found at sub-clause 18.4 of laid down by the relevant legally
days after the date a party became the 2017 edition. constituted public authorities in the
aware of the circumstances. The country where the project is being
same 14-day period can be found There is a potential alternative. carried out, and those authorities
in the 2017 edition but if the Notice Under sub-clause 8.5(d) of the delay or disrupt the contractor’s
is received after the period of 14 2017 Form and 8.4(d) of the 1999 work, and the delay or disruption
06 International Quarterly

was unforeseeable, then “this delay a certain period of time has • If you are entering into a new
or disruption will be considered as a elapsed. contract, how does that contract
cause of delay under sub-paragraph allocate risk arising from the
(b) of Sub-Clause 8.4 [Extension of • What alternative means of pandemic?
Time for Completion]”. performance are there? How
can you reduce any delay? • Everyone is talking about
Change to the Contract Price Performance might still be force majeure, but what other
Contractors may also want to check possible, even if engaging remedies may be available in the
sub-clause 13.7. Has there been a alternative suppliers and means contract?
change in the laws of the country of delivery are more costly.
which directly affected performance Ps It’s not just about Force Majeure
of the contract works and has led to • Follow the notice provisions Whilst everyone has been talking
an increase in the Contract Price? of the contract, to the letter. about force majeure, there are
Frustration under the FIDIC form What are the timescales? Who a number of other issues parties
Sub-clause 19.7 of the FIDIC form should the notice be sent to? At should be thinking about. Health
is also of interest. Here, the parties what address? Can you deliver & safety? Should sites close? The
will be released from performance the notice bearing in mind any answer to this will depend on the
(and the Contractor entitled to government restrictions that relevant Government guidance but
specific payment) if (i) any irresistible might be in place? may also depend on the criticality
event (not limited to force majeure) of the projects in question as well as
makes it impossible or unlawful for • You cannot sit back and do whether social distancing measures
the parties to fulfil their contractual nothing after serving the notice. can be implemented at the same
obligations, or (ii) the governing Think about how you can time as ensuring that working under
law so provides. It acts as a fall- mitigate the impact of the force the new methods and restrictions can
back provision for extreme events majeure event. be carried out safely.
(i.e., events rendering contractual
performance illegal or impossible) • It will be important to be able to You must keep your health and
which do not fit within the strict prove the steps that have been safely policies and procedures under
definition of force majeure laid out taken to mitigate the impact, so regular review and also ensure that
under sub-clause 19.1. It also grants both from the employer’s and they are understood by everyone on
the party seeking exoneration the the contractor’s perspective, site. You should also keep a careful
right to rely on any alternative relief- keep clear records which will help eye on risk assessments. In particular,
mechanism contained in the law resolve any potential areas of what is happening with the supply
governing the contract. dispute. chain? Where are goods supposed be
coming from?
Practical steps and checks: • Keep proper records so you
can show why performance Also, make use of technology, think
What does your contract say? And was impossible, what steps did about what can be carried out
it might not use the words “force you take to find an alternative remotely. Think too about how you
majeure” approach and what were the can keep in contact with people.
costs and delays incurred? Take Keeping lines of communication open
• If there is a force majeure photographs and make videos. and maintaining relationships is more
clause, what does it say? In Put a paper trail in place to important now than ever. And not
what circumstances might record that it was unsafe or just email, talking to people is key,
performance be excused and impossible to continue. keep in touch with your team, your
with what result? Just because contacts, with those working on your
something costs more or is more • Think about how you will judge project. The key to collaboration is
difficult, that will not of itself when the event is over? communication. We really are all in
be sufficient to rely on a force this together, and that won’t change
majeure, or similar clause. • Whilst always taking care to when the restrictions wherever you
follow the contract requirements may be, are lifted.
• What is the governing law of the about notices, look to see if there
contract and what does that law are other routes available to
say about force majeure? deal with the issue. Talk to the
other parties who are involved.
• Check what the consequences Everyone has been affected to
of triggering the force majeure C-19. A negotiated way forward is
provision are. Is performance always the preferable route. Far
simply suspended? Some Civil better to agree a way forward,
Codes provide for termination. if need be in a binding contract
Often contracts include the right addendum.
to terminate the contract after
07 International Quarterly

Coronavirus and Construction


Contracts

Jon Miller
Partner
jmiller@fenwickelliott.com

Introduction the Government has not ordered consistent with the HASAWA
building sites to shut down. which contains the well-known
Whether a force majeure event provision, “It shall be the duty
1. The impact of COVID 19 is
has occurred will always turn of every employer to ensure, so
changing daily and last week
upon the wording of the force far as is reasonably practicable,
in England at least many sites
majeure clause in the Contract, the health, safety and welfare at
closed whilst others continued
and how COVID 19 has impacted work of his Employees”2.
working. This note seeks to
the site in question. There is
set out the practical steps
no guaranteed answer to this 4. Further the Management of
to be taken in light of recent
question but, bearing in mind:- Health and Safety Act Work
developments, such as:-
Regulations provides for risk
2.1 we are facing a global assessments to be reviewed if
1.1 is force majeure likely to apply
pandemic which has had “…there has been a significant
to the current situation?
a significant effect on the change in a matter to which it
economy, transport, etc; relates; and where as a result of
1.2 with some sites now forced
to close, what needs to be done any such review changes to an
2.2 guidance whereby, when assessment are required, the…
now?
leaving their own household, person concerned shall make
people should remain 2 metres them” 3.
1.3 other sites remain open
apart even on a building site.
and some Contractors/Sub-
This would require changes to
Contractors believe that they 5. In the light of Government
not only different methods of
are being forced to continue Guidance and HASAWA etc
working at the work place, but
working – what can be done? virtually every site will have to
also amendments to canteen
review and probably change
arrangements, welfare and
1.4 steps to be taken now to try the way it is working. Some
changing facilities. Also at least
to protect your position if claims sites have closed temporarily to
some over the counter trade
are to be made for additional review working practices.
merchants are closing;
time/money in the future?
What if my site has not closed
in my view under most force
(Please bear in mind the (and it should)?
majeure clauses COVID-19 would
principles underlying the
probably now be seen as a force
interpretation of force majeure 6. Some Contractors/Sub-
majeure event.
and other Contract terms as set Contractors have complained of
out in my first note - https:// being forced to continue to work
Site Closures and the Health
www.fenwickelliott.com/ without any change in working
& Safety at Work Act 1974
research-insight/articles-papers/ practices to reflect Government
(“HASAWA”)
other/coronavirus-construction- Guidance. My suggestion would
contracts ) be:-
3. There has also been a spate of
Has a Force Majeure Event site closures during the past
6.1 write immediately pointing
occurred? week. Some Employers and
out the dangers and risks on
Contractors have expressed
site and asking the person
an overriding concern to
2. At the moment (i.e. the morning responsible for Health & Safety
protect their workers which is
of 30 March 2020) in England what they intend to do to
08 International Quarterly

change working practices; in refusing to return to a site What can be recovered?


6.2 the welfare of employees, where there was no social
Sub Contractors etc should be distancing, not only at the Other Routes of Recovery
the prime consideration. If a workface but with welfare
Contractor/Sub-Contractor facilities etc, it is imperative that 10. The reality which many
is being asked to work in a the Contractor/Sub-Contractor’s Contractors, Sub-Contractor etc
dangerous situation and refuses not only writes to the person are facing is that even if a force
to do so, this could amount to responsible for Health& Safety majeure clause applies, under
an “impediment, prevention on site highlighting the unsafe most but not all standard forms
or default, whether by act or working practices and asks of Construction Contract only
omission”4 or “[a] breach of how they are going to change, an extension of time is granted
contract…”5. Again this would but gathers evidence of what – there is little/no prospect
turn upon who is responsible the situation on site was really of recovering the loss and
for Health & Safety matters, like. In months to come there expense incurred as a result of a
the terms of the Construction may be arguments as to what shutdown6.
Contract and what is (or is was happening on site – the
not) happening on site. An Contractor/Sub Contractor
11. However many Construction
“impediment, prevention or concerned will have to establish
Contracts contain other clauses
default, whether by act or why it was unsafe to return.
in addition to a force majeure
omission” typically gives rise to
clause which may not only give
additional time and money. 9. Proof can be gathered from rise to an extension of time, but
sources such as:- loss and expense/compensation
7. Bear in mind that refusing to as well:-
work when instructed to do so is 9.1 employees;
very risky commercially speaking 11.1 compliance with an
– it can amount to a repudiation 9.2 other tradesmen and the instruction/direction shutting
of the Construction Contract professional team on site – make down the site can potentially
giving rise to claims for damages a note of who they are as they give rise to a claim for an
for breach. may prove useful in the future; extension of time and loss and
expense7. Indeed an instruction
Evidence 9.3 photographs showing what to stop work will probably also
the true situation was. count as an act of prevention –
8. If a Contractor/Sub-Contractor this too could give rise to claims
is to argue they were justified for time and money8;
09 International Quarterly

11.2 often forgotten is that itself and nothing else - any are aware of a site where
some standard forms contain other points that need to be working practices have been
a provision allowing the raised should be in a separate changed whereby there is no
Employer/Project Manager etc communication13; more than one operative in
to postpone all or part of the each room, operatives start at
works9 - exercising this power 13.4 separate notices are different times and ensure they
will also normally give rise to an often required in respect of an maintain a distance of 2 metres
extension of time and loss and extension of time and claims throughout.
expense10; for money, each of which may
have different requirements as But even then this will give
11.3 not providing safe working to what they should contain14; rise to delays to the progress
practices on site can amount to some forms of Contract require of the Works – i.e. changing
prevention, hindrance or even one notice15. working arrangements which
a breach of Contract – see the slow progress may still give rise
point made above. 14. Failure to give a notice in the to an extension of time if they
form required by the Contract, delay the Completion Date (and
using the correct method of additional recoverable costs
Notices delivery, or given after the if the Construction Contract
deadline may result in not only allows it).
12. The protection offered by a any compensations/loss and
Construction Contract means expense not being payable, but 19. How many people were
little unless invoked, almost amount to a justifiable reason supposed to be on site? Who
always by the issue of a notice. to refuse to grant an extension was self-isolating/ill/had a
According to most JCT forms a of time. This in turn can result pre-existing condition? What
notice requiring an extension of in liquidated and ascertained trade(s) were they and where
time is to be issued when “… the damages being payable. were they supposed to work?
progress of the Works… is being
or is likely to be delayed”11, whilst Confrontational Notices? 20. Was there a lack of supplies/
most NEC forms require notice materials? If so when were they
to be given within 8 weeks of 15. Aggressive and confrontational to be delivered (and eventually
becoming aware of an event attitudes in construction are when did delivery take place)?
which could change the Prices, not that rare16. A notice need
the Completion Date or a Key not be given in aggressive terms 21. Nearly all Construction
Date12. - it only needs to comply with Contracts impose a need to
the underlying Construction mitigate/use best endeavours
Under these standard forms, Contract. to reduce delays17. Record
the time for giving notice has
all attempts to try and find
almost certainly already started
16. It is acceptable for a notice alternative labour and get new
to run.
to explain, “We are making delivery dates – i.e. keep emails.
our work safe and acting in
13. Giving a notice raises a number accordance with your instruction Costs
of issues including:- whereby we expect to leave the
site at 5pm today. Under the 22. Record separately all costs
13.1 all Contracts have different terms of our Contract we are related with stopping on site or
deadlines for when a notice obliged to give you notice of…”. any slowdown e.g.:-
is to be given. Frequently the
time limits for giving notices Proving your Claim and what 22.1 demobilisation and
are amended in standard needs to be done now remobilisation costs;
form Contracts to make them
shorter; Delays 22.2 the costs of making the site
safe;
13.2 the Contract may require
17. Only delays to the Completion
the notice to be given in a
Date can give rise to an 22.3 materials - what was
particular manner and to a
extension of time. Programming originally allowed for in the
particular person – an email
information is crucial. The Contract Price, and what did it
to the Employer may not be
burden is on the party making increase to?
enough;
the claim to show why the
COVID-19 shutdown delayed the 22.4 retaining labour/non-
13.3 Contracts normally set out
Completion Date. productive payments are often
what the notice is to contain.
difficult to recover. Ask the
For example under the NEC4 a
18. Some sites may be able to Employer/Contractor what they
notice is to contain the notice
continue working safely. We want to do?
10 International Quarterly

Costs – the big mistake 24.1 works should be made safe; 8. e.g. JCT D&B 2016 Clause 2.26.6 &
4.21.5 and NEC4 Clause 60.1(2).
23. A common mistake people 24.2 if you are insuring the 9. e.g. NEC4 Clause 60.1(4) and JCT D&B
make is that the additional Works, your insurer should be 2016 Clause 3.10.
costs incurred are not clearly told.
10. e.g. JCT D&B 2016 Clause 2.26.2.2 &
attribute to the relevant
delay/shutdown due to Finally I stress again please read 4.21.2.1 and NEC4 Clause 60.1(4).
matters such as COVID-19. For your Contract. The rights and 11. e.g. JCT D&B 2016 Clause 2.24.1.
example demobilisation and re obligations you have will largely
12. e.g. NEC4 Clause 61.3.
mobilisation costs should be depend on its terms.
recorded separately. Suppliers 13. Clause 13.7.
invoices should not simply cover 14. e.g. JCT D&B 2016 Clause 2.24 & 4.20.1.
all the materials delivered to site Footnotes
15. e.g. NEC4 Clause 61.3.
before and after a shutdown
– get clear what materials 16. To put it politely.
1. There is obviously a difference
increased as a result of the 17. e.g. JCT 2016 D&B Clause 2.25.6.1.
shutdown and why. between the two, both terms are used
here in the colloquial sense.
Particularly infuriating are 2. Section 2(1).
timesheets with 7 (or more)
3. Regulation 3(3)(b).
hours for every day without any
explanation of what was being 4. JCT 2016 D&B Clause 2.26.6 and 4.21.5.
done, or where the operatives 5. NEC4 Clause 60.1(18).
were working.
6. The NEC is probably a notable
exception as it will probably allow
Further Action
compensation to be paid in these
circumstances.
24. No doubt there are other actions
which need to be taken which 7. e.g. JCT D&B 2016 Clause 2.26.2 &
will depend on the site etc but:- 4.21.1 and NEC4 Clause 60.1(4).
11 International Quarterly

Getting termination right: PBS


Energo A.S. v Bester Generacion UK
Limited & Anor [2020] EWHC 223
(TCC) and the FIDIC Silver Book

Jesse Way
Associate
jway@fenwickelliott.com

Introduction contract because PBS had failed to The project commenced in May 2016
comply with a Notice to Correct and but the key programme dates were
PBS Energo A.S. v Bester Generacion PBS had abandoned the works or not met. Disputes arose and, by April
UK Limited is a case with a raft of evinced an intention not to perform 2017, contractors performing civil
issues which commonly arise on the contract. works had stopped work.
construction projects. However, the
parties’ entitlement to terminate In the end, the Court determined On 24 May 2017, PBS gave notice
was the central issue before the that PBS’s basis for terminating the of its intention to terminate the
Court and will be the focus of this contract was without foundation. Contract on the basis that Bester
article. Terminating a contract is a The Court held that Bester was failed to make payment for Milestone
risky business and, if it is not done entitled to terminate the contract 5 by the Final Date for Payment
correctly, it can have disastrous and its reasons for reaching that and for substantial failures to fulfil
financial implications. This article will finding are explained in more detail its contractual obligations. The
consider the PBS decision and discuss below. substantial failures alleged by PBS
the 2017 FIDIC Silver Book (“Silver were essentially a failure to determine
Book”) provisions for termination by Facts PBS’s extension of time (“EOT”)
a Contractor for a failure to receive claims. PBS’s EOT claims related to:
payment. On 29 April 2016, Bester contracted
with Equitix ESI CHP (Wrexham) • unforeseeable detection of
The project concerned was a biomass Limited (“Equitix”) to design, underground sewage/drainage
energy plant to be built in the north construct, install and commission system;
of Wales. Ultimately, the plant was a biomass-fired energy generating
never constructed and the case was plant and associated works, and later • detection of asbestos at the site;
concerned with the circumstances (by a separate contract) to operate
in which that happened. PBS, a the plant (“the Equitix Contract”). • delay in provision of ROC and
company incorporated in the Czech permits;
Republic, specialises in the design On 10 May 2016, PBS and Bester
and manufacture of power plant entered into a subcontract (“the • additional payment for a
equipment. Bester, a UK subsidiary Contract”) for the engineering, variation in respect of an
of a Spanish company, specialises procurement, construction and electrical connection; and
in the provision of renewable energy commissioning of a biomass-
projects. Unsurprisingly, the parties fired energy generating plant and • BT cable lines.
fell out and ended up in Court. associated works at Wrexham
PBS, the Contractor, claimed it (“the Works”). The Contract price On 14 June 2017, PBS sent a further
was entitled to terminate because was approximately £14 million and letter to terminate the Contract on
Bester, the Employer, failed to pay the Contract was based on an and from the date of the letter.
the fifth Milestone payment by the amended form of the FIDIC Silver
date required and substantially failed Book Conditions of Contract for EPC/ Bester then sent a series of letters
to fulfil its contractual obligations. Turnkey Projects. in which Bester sought to affirm the
Bester claimed it could terminate the Contract and requested PBS retract
12 International Quarterly

the termination but PBS did not do On 7 August 2017, Bester confirmed valid so as to trigger an entitlement
so. its termination of the Contract. to payment.
Whilst the above was happening, The Court held that Milestones
On 12 July 2017, Bester served a notice Equitix issued a notice of intention 3 and 4 were never achieved,
of termination on the basis that: to terminate the Equitix Contract on albeit they were paid on a without
3 July 2017 and did terminate that prejudice or commercial basis. As
• PBS failed to comply with Bester’s contract on 17 July 2017. Milestones 3 and 4 had not been
Notice to Correct of 7 November achieved, it followed that payment
2016 (relating to delays in PBS’s PBS’s termination for Milestone 5 could never have
submissions of civil work designs, become due for payment. This was
procurement of documents, The Court considered PBS’s EOT because completion of the preceding
failure to progress the works, claims and determined they were Milestones was a prerequisite to
and failure to provide collateral without basis or not pursued by PBS payment (i.e. Milestones 1–4 had
warranties and subcontracts at trial. An examination of each to be achieved before payment for
from PBS’s subcontractors); of the EOT claims and the Court’s Milestone 5 could be achieved).
reasoning in respect of each is Accordingly, PBS’s termination failed.
• ongoing delay by PBS, failure to beyond the scope of this article. The
proceed diligently, and unlawful second basis upon which PBS sought Bester’s termination
suspensions; to terminate the Contract was that
Bester failed to make payment of The Court held that Bester was
• PBS failed to provide permits and Milestone 5 by the date for payment. entitled to terminate. This was on the
assistance to Bester; and The Contract contained a number of basis that PBS had abandoned the
Milestones but the issue was whether works and failed to comply with the
• PBS abandoned the works and/ Milestones 3–5 were achieved. In Notice to Correct. PBS had argued
or intended not to perform its relation to Milestone 5, if it was that it was unable to comply with
obligations under the Contract. achieved, the issue was whether the the Notice to Correct because Equitix
notice served in relation to it was had terminated Bester’s contract
13 International Quarterly

and locked up the site. However, the Unless the Employer remedies the to note the distinction because the
Court found that on the evidence matter described in a Notice given Silver Book sets out when Notices are
it was in fact PBS who had locked under Sub-Clause 16.2.1 [Notice] deemed to be received.
up the site and abandoned it long within 14 days of receiving the
before termination of the Equitix Notice, the Contractor may by giving Once the Notice to terminate is
Contract. The Court found that a second Notice to the Employer given, it takes effect immediately and
Bester’s contract was terminated immediately terminate the Contract. there are further steps required to
because of PBS’s failure to perform. The date of termination shall then be be taken by the Contract under the
PBS tried to rely on the prevention the date the Employer receives the later clauses regarding termination.
principle; however, the Court was not second Notice.”There are a number However, it is clear from the above
persuaded the prevention principle of elements to the above clauses that there are a number of steps to
applied here. As an aside, the Court which are commonly overlooked be followed to correctly terminate
noted Coulson LJ in Cyden v North or misinterpreted by Contractors a contract subject to the Silver
Midland [2018] EWCA Civ 1744 where (not only in FIDIC contracts but in Book conditions and they must be
he reiterated the warning that the standard forms as well). complied with.
prevention principle is not a broad
and overarching principle or general One of the most common pitfalls is Of course, in the example above, it is
backstop to an EOT regime, but the issue of a Notice of termination all predicated on the basis that the
a principle of narrow application. (the Notice contemplated in Sub- Contractor has in fact not received
Accordingly, as Bester was entitled Clause 16.2.2) before, and without, a payment under Sub-Clause 14.7
to terminate, the Court held that issuing the initial Notice (the Notice and that the payment application
Bester’s counterclaim succeeded, contemplated in Sub-Clause 16.2.1). process has been complied with
which was approximately £16 million However, as is clear from the clauses, by the Contractor. A common
(and the consequence of PBS’s failed the first step is to issue Notice of the way for an Employer to impeach
termination). Contractor’s intention to terminate a termination by a Contractor on
the Contract. This is an important the basis of a failure to receive
2017 FIDIC Silver Book – termination point. The reason for such a Notice payment is that the Contractor was
by a Contractor is because the consequences of never entitled to payment because
termination, as can be seen from the the Contractor failed to follow the
Sub-Clause 16.2 of the Silver Book PBS decision, are significant and also payment application process. This
sets out how a Contractor can to allow the Employer an opportunity is similar to what occurred in PBS
terminate the contract. In this to remedy the default. because the Court held that PBS
article, only termination for a had no entitlement to payment for
failure to receive payment will be A Notice is a defined term in the Milestone 5 because completion of
considered. Silver Book and the requirements for Milestones 3 and 4 was a prerequisite
it must be followed, including how for an entitlement to payment for
Sub-Clause 16.2.1 and 16.2.2 and to whom it is to be issued (see Milestone 5. As PBS did not complete
relevantly state: Sub-Clauses 1.1.48 and 1.3). The Milestones 3 and 4, entitlement to
Notice must also state that it is given payment for Milestone 5 could not
“16.2.1 Notice under Sub-Clause 16.2.1. Whilst this arise.
may seem insignificant, the purpose
The Contractor shall be entitled to is to draw the Employer’s attention Conclusion
give a Notice (which shall state that to the fact that it is a Notice of
it is given under this Sub-Clause intention to terminate. Termination is a common issue that
16.2.1) to the Employer of the arises on construction projects.
Contractor’s intention to terminate The Contractor can only proceed The PBS case serves as a good
the Contract … if: to terminate if the Employer does example of the importance of
not remedy the matter described in getting termination right as there is
… the Notice under Sub-Clause 16.2.1 often a competing termination and
within 14 days of receiving the Notice. the consequences of an incorrect
(b) the Contractor does not receive Once again, the Contractor must termination are significant. To
a payment under Sub-Clause 14.7 comply with the requirements for a terminate a contract effectively it
[Payment] within 42 days after Notice as described above. However, is imperative that the terms of the
the expiry of the relevant period for termination can only occur if the contract are followed and it is clear
payment stated in Sub-Clause 14.7; Employer has not remedied the from the Silver Book conditions that
matter in the initial Notice “within there are many requirements which
… 14 days of receiving the Notice”. It is can easily be overlooked. The bottom
not within 14 days of the Contractor line? Check twice before terminating
16.2.2 Termination sending the Notice. It is important (and then again!).
14 International Quarterly

Unforeseeable ground conditions


and the FIDIC Silver Book

Jeremy Glover
Partner
jglover@fenwickelliott.com

My colleague Jesse Way has written such data which come into the (b) by signing the Contract,
separately about the termination Employer’s possession after the the Contractor accepts total
issues that arose in the case of PBS date of execution of this Contract. responsibility for having foreseen all
Energo AS v Bester Generacion UK The Contractor shall be responsible difficulties and costs of successfully
Ltd & Anr;1 the case also considered for interpreting all such data. The completing the Works; and
the meaning of “unforeseeable Employer shall have no responsibility
ground conditions” and the for the accuracy, sufficiency or
(c) and subject to Clause 13
judgment includes a useful summary completeness of such data.
(Variations and Adjustments), the
of the position making reference
Contract Price shall not be adjusted
to previous caselaw such as the
The condition of the Site (including to take account of any unforeseen
Obrascon decision.
Sub-Surface Conditions) shall difficulties or costs.”
be the sole responsibility of the
In short, the overall dispute Contractor and the Contractor is
There was a disagreement
concerned a biomass energy plant deemed to have obtained for itself
between the parties about how
in North Wales that was never built. all necessary information as to
the contract operated to transfer
The contract was an amended risks, contingencies and all other
the risks associated with obtaining
version of the FIDIC Silver Book 1999 circumstances which may affect
planning permission, but this article
for EPC or turnkey projects and one the Works, the remedying of Defects
concentrates on the risk of the
of the many disagreements related and the selection of technology and
ground conditions and the discovery
to who was responsible for the risk of (save where otherwise set out in this
of asbestos, strictly, the second
the asbestos which was found under Contract) the Contractor accepts
discovery of asbestos. The first
the surface and which had to be entire responsibility for investigating
discovery of asbestos by PBS was not
removed to get planning permission and ascertaining the conditions
due to any error or incompleteness
finalised. of the Site including, without
in the reports and had not in fact
limitation, ground, load-bearing and
caused critical delay.
other structural parts, suitability of
Sub-clause 4.10 of the contract As Mrs Justice Cockerill noted, the
the utilities and incoming services,
provided that: difficulty for PBS was that it had
hydrological climatic, access,
environmental, weather and other quite a lot of information prior to
“4.10 Site data general conditions and the form and the contract as to the presence of
nature of the Site including both asbestos. For example, it knew that
natural and man-made conditions.” there was asbestos disclosed by
Subject to Clauses 4.18 (Protection testing in just a few limited areas;
of the Environment) and 4.25 Whilst sub-clause 4.12 provided that:
and it knew from the trial pit results
(Lease), the Parties acknowledge “Except for Unforeseeable that this asbestos included bits
and agree that the Employer has Difficulties and except as otherwise which were deeper than 0.1 metres.
made available to the Contractor stated in the Contract: PBS would need to say that the
for his information, prior to the extent of the deeper asbestos was
date of execution of this Contract, unforeseeable, even though the
(a) the Contractor shall be
all relevant data in the Employer’s presence of some deeper asbestos
deemed to have obtained all
possession on subsurface and was known about.
necessary information as to
hydrological conditions at the Site,
risks, contingencies and other
including environmental aspects.
circumstances which may influence Helpfully, the Judge referred to
The Employer shall similarly make
or affect the Works; previous decisions, in particular
available to the Contractor all
15 International Quarterly

the decision of Mr Justice Coulson in more granular detail than


in Van Oord UK Ltd v Allseas UK previous reports had suggested. “not reasonably foreseeable by an
Ltd2 and the Court of Appeal It had to show that the asbestos experienced contractor by the Base
decision in Obrascon Huarte Laine discovered was unforeseeable. This Date”.
SA v Her Majesty’s Attorney General was something it could not do, even
for Gibraltar3 where Mr Justice though a Geotechnics Report which
Akenhead had refused a claim based referred to the discovery of asbestos There are a number of references
on allegedly unforeseen ground was only disclosed after the contract to the “experienced” contractor
conditions, saying that: was concluded. That report did in the 2017 Form, but there is
not “come out of the blue”. Pre- no contractual definition of this
contract, PBS were informed about phrase. It is therefore a question
“I am wholly satisfied that an of fact. What would or should an
trial pit results. The Judge noted that
experienced contractor at tender experienced contractor have done in
the trial pit results were important,
stage would not simply limit itself the particular circumstances. When
even though they represented a
to an analysis of the geotechnical it comes to tender documentation,
detailed investigation of ground
information contained in the pre- the experienced contractor cannot
conditions at various places across
contract site investigation report simply rely on the information
the site. This led to a clear analogy
and sampling exercise. In so doing provided by others. In the Obrascon
to Obrascon: “this was not a case of
not only do I accept the approach case, the English Court of Appeal,
asbestos being a possibility – it was
adumbrated by Mr Hall [the when considering the 1999 Yellow
clear that asbestos contamination
defendant’s geotechnical expert] Book, noted that when assessing
was a reality, and potentially at
in evidence but also I adopt what tender data:
some depth in some places, though
seems to me to be simple common
the extent of the problem was not
sense by any contractor in this field.”
clearly delineated.” “an experienced contractor
would make its own
The Court of Appeal agreed: assessment of all available
Since ground conditions were at
PBS’s risk, it was for PBS to satisfy data … Clauses 1.1 and 4.12 of
“Every experienced contractor itself as to the state of play as the FIDIC conditions require
knows that ground investigations regards asbestos. If there were public the contractor at tender stage
can only be 100% accurate in the documents available these should to make its own independent
precise locations in which they are have been taken account of. PBS assessment of the available
carried out. It is for an experienced had a good picture of the situation information. The contractor
contractor to fill in the gaps and as regards the presence of asbestos must draw upon its own
take an informed decision as to on the site. expertise and its experience
what the likely conditions would be of previous civil engineering
overall.” projects. The contractor
PBS further either chose not to, or must make a reasonable
were unable to, call evidence which, assessment of the physical
This was exactly what had happened in the words of the Judge, “grappled conditions which it may
here. A contractor cannot rely on with the detail of what was found”. encounter. The contractor
an argument claiming that the For example, there was no evidence cannot simply accept
ground investigations were 100% as to what would, in accordance someone else’s interpretation
accurate. In Obrascon there was with “Good Industry Practice”, have of the data and say that is all
fuller documentation than here been foreseeable from the baseline that was foreseeable.”
indicating that contaminants had of knowledge which PBS had. The
been identified which raised “a large asbestos discovered was not a new
flag” to an incoming contractor. discovery, or different from what Words any contractor in any
However, Mrs Justice Cockerill said had been indicated by the previous jurisdiction should take on board.
that in Van Oord, Mr Justice Coulson findings, but simply a more detailed
made a more general point that manifestation of what was shown Footnotes
what matters is the information by the earlier materials. It followed,
itself. Is the information such as to therefore, that PBS had either actual
put a contractor on inquiry: “such or constructive knowledge of the 1. [2020] EWHC 223 (TCC) (07 February
that he can then only complain if asbestos prior to the Contract. It 2020).
what emerges is unforeseeable – in was not unforeseeable.
2. [2015] EWHC 3071 (TCC).
the light of what he does have”.
3. [2015] EWHC 3071 (TCC).
Under sub-cause 1.1.77 of the 2017
Therefore it was not enough for PBS FIDIC Silver Book, unforeseeable is
to point to the discovery of asbestos defined as meaning:
16 International Quarterly

Prejudice without prejudice?

Catherine Simpson
Trainee Solicitor
csimpson@fenwickelliott.com

Different jurisdictions apply different the prescriptive period had been proceedings, that only in the
meanings to the words “without extended. Transform subsequently plainest of cases would a challenge
prejudice”. A recent Scottish raised an action for enforcement on the basis of breach of natural
case, Transform Schools (North of the adjudicator’s decision, after justice be successful, and even if the
Lanarkshire) Limited v Balfour Balfour Beatty refused to pay the adjudicator had erred on law, there
Beatty Construction Limited1 and award of approximately £4,000,000. was no breach of natural justice
Balfour Beatty Kilpatrick Limited, in this case (as both parties had
provides a useful reminder of some been given the opportunity to make
What were the parties’ arguments?
key issues that often arise in the representations in relation to the
course of construction disputes, without prejudice material).
in particular in the context of Balfour Beatty opposed enforcement
enforcement of adjudicator’s on the basis that the adjudicator
What was decided?
decisions arising from breach of had referred to certain letters
natural justice. In this case, the focus which had been marked “without
was the admissibility or otherwise of prejudice”. Their argument was, The court emphasised that it was
without prejudice documents. broadly, that: (1) without prejudice only concerned with whether the
correspondence was protected adjudicator’s decision should be
against use in the adjudication; (2) enforced. The question of whether
What was the case about?
the adjudicator had relied upon the without prejudice letters were
the protected correspondence to actually admissible was a matter
Transform Schools (North a material extent in determining for the court to decide on final
Lanarkshire) Limited (“Transform”) prescription; (3) the adjudicator’s determination of the dispute.
had engaged Balfour Beatty approach “offended against the
Construction Limited and Balfour public policy” underpinning without
The fact that the admissibility
Beatty Kilpatrick Limited (“Balfour prejudice privilege (they argued
of the correspondence had been
Beatty”) to perform construction that if parties could not enter
a central issue, and the way in
work at various schools in North into without prejudice settlement
which the adjudicator had dealt
Lanarkshire, Scotland. discussions without the risk of these
with it, led Lord Ericht to conclude
being relied on in an adjudication,
that there had been no breach of
the process of adjudication would
A dispute arose between the parties natural justice by the adjudicator
be “damaged”); (4) the adjudicator
in relation to latent defects at in considering and relying on the
was guilty of a material error in
one of the schools. The dispute correspondence. The court enforced
admitting, considering and relying
was submitted for adjudication the adjudicator’s decision.
on the correspondence; and (5)
and found in favour of Transform. The reasoning behind this was
the adjudicator’s error amounted
In the adjudication, Balfour that the adjudicator had to decide
to a material breach of natural
Beatty’s argument that the claim whether or not Transform’s claim
justice and/or the adjudicator’s
had prescribed (or that it was had prescribed and, in order to do
reliance on the without prejudice
time barred under the principle that, he had to decide whether
correspondence gave rise to
equivalent to limitation, for those or not the without prejudice
apparent bias.
unfamiliar with the Scottish jargon) letters were admissible. Only as a
was rejected. The adjudicator consequence of his decision that
concluded, with reference to a chain Transform submitted, with reference they were admissible, did he take
of letters between Balfour Beatty to the accepted principles that are them into account in deciding
and Transform’s solicitors, that applied in adjudication enforcement that the prescriptive period had
17 International Quarterly

been extended. The adjudicator’s improper or involved any breach of principles to be applied
approach had been to look at the natural justice or apparent bias.” in considering whether to
correspondence as a whole, and enforce an adjudicator’s
greater weight had been given decision;
What can we learn from this case?
to letters which were not marked
“without prejudice”. Accordingly, the
• Rush and Tompkins Limited
court confirmed that the adjudicator Well this will vary according to the
v GLC 3 on the without
had been entitled to decide on the jurisdiction. Scottish judgements are
prejudice rule governing the
admissibility of the without prejudice referred to in the English courts, so
admissibility of evidence;
correspondence. they have a persuasive authority:

• Costain Limited v
Although the court did not consider • An adjudicator can rule on
Strathclyde Builders
whether the adjudicator had admissibility where the material
Limited4 on the application
been right to conclude that the is alleged to be without
of the principles of natural
correspondence was admissible, it prejudice.
justice in the context of an
did confirm that if the adjudicator
adjudication;
had been wrong, that would have
• The court will consider
been an error of law, and an error of
factors such as whether
law on the part of the adjudicator • Ellis Building Contractors
the admissibility of without
would not be grounds to refuse Limited v Goldstein5 on
prejudice documents was a
to enforce the decision. The court the relationship between
central issue in the adjudication
would be justified in refusing to without prejudice
and the manner in which the
enforce the decision if there had documents and the rules of
adjudicator handled the issue
been a serious breach of natural natural justice.
when determining whether or
justice. However, this was not the
not there has been a breach of
case. The question of admissibility
natural justice or bias. England: what does the English
was one which had to be decided as
case law say?
a central issue in the adjudication.
The adjudicator had given both • The case also helpfully
parties an opportunity to make summarises the following There have been various cases in the
submissions, on which he had made established case law – courts of England and Wales where
a reasoned decision. Lord Ericht it has similarly been argued that an
concluded: “It cannot be said that adjudicator was biased because they
the submission of the letters to the • Carillion Construction
were provided with without prejudice
adjudicator, or the way in which he Limited v Devonport Royal
material and/or that their decision
dealt with them, was in any way Dockyard Limited2 on the
should not be enforced due to
18 International Quarterly

breach of natural justice (requiring decision being biased. The test is that the agreement be governed by
that every party has the right as set out in Ellis – there will be an the law of whichever jurisdiction is
to a fair hearing by an impartial objective appraisal of the material selected. In the UK, this would mean
tribunal). However, an adjudicator’s facts to assess whether there is that the dispute board would be
decision will not necessarily be a legitimate fear of adjudicator bound to follow the rules of natural
biased or in breach of natural justice bias. It is also highly probable that justice, and the concept of without
just because they saw or were made the other party will simply ask the prejudice would apply. In the UAE,
aware of without prejudice material. adjudicator to ignore the material however, the without prejudice
if inadvertently submitted. The fact rule would not apply, which poses
that adjudicators are commercially difficulties if one or more party does
In Specialist Ceiling Services
minded should mean that they are not want the content of settlement
Northern Ltd v ZVI Construction
able to remain impartial. Transform negotiations to be disclosed. They
(UK) Ltd6 the judge noted that the
Schools is persuasive authority (like would not be able to argue that the
adjudicator was “unfazed by the
many before it) that courts will look adjudicator’s decision was tainted by
knowledge that there had been
to see how the adjudicator handled bias as a result of them having seen
without prejudice negotiations,
the matter in determining whether the statements made in an attempt
because he not only expected
there has been a breach of natural to settle.
them to occur, but in his experience
justice or bias.
offers were often made on a
purely commercial basis in an This begs the question: what can
effort to obviate the need for The UAE: what if the without parties operating under UAE law do
an adjudication”. It follows that prejudice rule does not exist? to ensure that any without prejudice
adjudicators will generally know material is not relied upon in an
that offers may be made for adjudication? First, it would be wise
The concept of without prejudice
sound commercial reasons and do not to document any settlement
is not recognised in certain
not necessarily indicate liability. negotiations in writing. It may
jurisdictions, meaning material
Provided the adjudicator can remain also be preferable for the parties
marked “without prejudice” which
uninfluenced and in effect put the to enter into a formal agreement
has been exchanged in an effort to
without prejudice material out of his before the project starts, which
settle could be used as evidence of
mind when reaching a decision, he provides that they cannot later refer
admissions against the interest of
should be able to proceed with the to without prejudice material (or
the party that made them. The UAE
adjudication unbiased. material marked as “confidential”
is one such jurisdiction.
as confidentiality is an accepted
principle in the UAE) in the event of
All the same, it is clear from Ellis
Adjudication has not been a dispute, without the consent of
Building Contractors Ltd v Goldstein7
introduced by local legislation in the other side.
that the improper submission of
the UAE, the main barrier to its
without prejudice material might
acceptance as a method of dispute
give rise to apparent bias and/ Footnotes
resolution being the lack of a
or could render the adjudicator’s
statutory framework and recognised
decision unenforceable on the
enforcement mechanism. However, 1. [2020] CSOH 19.
grounds of breach of natural justice.
dispute adjudication boards or
In this case, the TCC said bias must 2. [2006] BLR 15.
DABs (tribunals of one or three
be assessed objectively and the
qualified persons established under 3. [1988] UKHL 7.
test was whether “the material
a contract to resolve disputes) 4. 2004 SLT 102.
facts give rise to a legitimate fear
are sometimes used in the region
that the adjudicator may not have 5. [2011] EWHC 269 (TCC).
through the use of the FIDIC suite of
been impartial”. The court also
contracts. These contain provision 6. [2004] BLR 403.
sought to discourage parties from
for disputes to be resolved by DAB
using without prejudice material 7. [2011] EWHC 269 (TCC).
prior to commencing arbitration
in adjudications – it was clear on
proceedings.
the facts that it was improper for
without prejudice evidence to be put
before the adjudicator, and, in the The agreement between the parties
words of Akenhead J, “it is a practice and the adjudicator(s) will usually
that should be discouraged”. incorporate the General Conditions
of the Dispute Adjudication
Agreement contained in the
So whilst parties should not
Appendix to the FIDIC General
disclose without prejudice
Conditions, with such amendments
material to an adjudicator, they
as are agreed between the parties.
need not assume that doing so
The form in the Appendix provides
will automatically result in the
International Quarterly is produced quarterly
by Fenwick Elliott LLP, the leading specialist
construction law firm in the UK, working with
clients in the building, engineering and energy
sectors throughout the world. International
Quarterly is a newsletter and does not provide
legal advice.

Edited by
Jeremy Glover
Partner
jglover@fenwickelliott.com
Tel: + 44 (0) 207 421 1986

Fenwick Elliott LLP


Aldwych House
71 - 91 Aldwych
London WC2B 4HN

Fenwick Elliott LLP


Office 1A, Silver Tower
Cluster i, Jumeirah Lakes
Towers
PO Box 283149
Dubai
www.fenwickelliott.com

You might also like