You are on page 1of 9

Ref. Title Page No.

10.1 Piling: General 10-1


10.1.1 Description 10-1
10.1.2 Materials 10-1
10.1.3 Construction Requirements 10-1
10.1.3.1 General 10-1
10.1.3.2 Cast in Place Piles 10-3
10.1.3.3 Placing Concrete 10-4
10.1.3.4 Preliminary Drilled Piles 10-4
10.1.3.5 Precast Concrete Piles 10-4
10.1.3.6 Steel piles 10-5
10.1.3.7 Tolerances 10-5
10.1.4 Method of Measurement 10-5
10.1.5 Basis of Payment 10-5
10.1.6 Items in the Bill of Quantities 10-5

10.2 Pile Testing 10-5


10.2.1 Description 10-5
10.2.2 Submittals 10-5
10.2.3 Execution 10-6
10.2.3.1 Preparation 10-6
10.2.3.2 Static-Load Testing 10-6
10.2.3.3 Non-Destructive, Low-Strain Integrity
Testing 10-6
10.2.3.4 Test Records 10-7
10.2.4 Method of Measurement 10-7
10.2.5 Basis of Payment 10-7
10.2.6 Items in the Bill of Quantities 10-7

♦ 10-0 ♦
♦ 10-0 ♦
10.1 Piling: General adequate notice of any intention to work outside normal
site hours.
10.1.1 Description 3 The Contractor shall engage an experienced installer
who has specialized in installing drilled or driven piles
1 This Section describes requirements for supplying similar to those required for the Project.
and installing precast concrete, cast in-situ concrete and
4 The Contractor shall protect structures, utilities,
steel piles by boring and/or driving.
sidewalks, pavements and other facilities, on or adjacent
to the Site, from damage caused by settlement, lateral
10.1.2 Materials
movement, vibration, and other hazards created by drilled
1 Concrete and steel reinforcement shall be as or driven pile operations.
specified in the relevant Clauses of Section 5. 5 The Contractor shall carry out the piling work in such
2 Concrete mixes, mixing and curing procedures shall a manner and at such times to minimize noise and
be as specified in the relevant Clauses of Section 5. disturbance to the general public. If, during execution of
Concrete mixes for use in piles shall be capable of the work, damage is likely to be caused to utilities or
maintaining a slump of 200 mm for 2 hours after adjacent structures, the Contractor shall submit to the
placement. Concrete mixes shall be designed to resist Engineer proposals for the repair or avoidance of such
aggressive soils and ground water if encountered in damage.
compliance with the requirements of the Construction 6 Piles shall be installed to the tolerances given in
Industry Research and Information Association – CIRIA Table 10.1.3.1.
‘Guide to the Construction of Reinforced Concrete in the
Arabian Peninsula’. Characteristic Allowable Limit
3 Steel pipe casings shall comply with the 75mm in any direction at the
Position
requirements of ASTM A 283M, Grade C; or ASTM A 36M pile head
carbon-steel plate, with vertical joints full-penetration
welded according to AWS D1.1. Verticality 1 in 75 deviation

4 Welds for fabricating steel piles and connecting steel Rake


1 in 25 deviation
pile lengths shall be as specified in the relevant Clauses of (for raked piles only)
Section 6. Table 10.1.3-1: Pile Installation Tolerances.
5 Sand-cement grout shall consist of Portland cement
manufactured according to ASTM C 150, Type I; and clean 7 The Contractor shall submit daily records to the
natural sand complying with ASTM C 404. Unless Engineer within 24 hours giving the information listed in
otherwise indicated, mix at ratio of 1 part cement to 2-1/2 Table 10.1.3.2.
parts sand, by volume, with sufficient water to permit flow 8 On completion of piling, the Contractor shall deliver a
during placement. final schedule of installed piles giving the information
6 Slurry shall consist of pulverized sodium bentonite, required by Table 10.1.3.2.
pulverized attapulgite, or polymers, mixed with potable
water to form a stable colloidal suspension; complying
with ACI 336.1, and the values indicated for density,
apparent viscosity (in centipoise), gel strength (in N/sq.m.),
sand content, and pH.

10.1.3 Construction Requirements


10.1.3.1 General

1 The Contractor shall submit for prior approval a


detailed method statement that describes all means,
methods and techniques to be adopted for construction
and installation of the drilled or driven piles. The method
statement shall include details of equipment to be used,
method of excavation, slurries to be used method of
concrete placement to ensure removal of slurry from sides
of boring, quality control, testing and report procedures,
work program, and any other information required by the
Engineer.
2 The Contractor shall inform the Engineer each day of
the work program for the following day and shall give

♦ 10-1 ♦
Driven Hollow Cast-
Driven Precast Concrete & Steel Bored Cast-in-Place Concrete
All piles in-Place Concrete
Piles Piles
Piles

1. Date 1. Cross-sectional dimensions. 1. Cross section 1. Diameter of completed


2. Contract 2. Total length of preformed dimensions of pile.
identification, pile. driving tube 2. Diameter of any enlarged
3. Pile identification. 3. Driven length of preformed (temporary base.
4. Pile type. pile. casing). 3. Length of temporary
5. Working load. 4. Sequence of driving in 2. Cross-sectional casing.
6. Ground level at groups. dimensions of 4. Length of permanent
commencement of 5. Final set. completed pile. casing.
operations. 6. Sections and joints used. 3. Length of 5. Length of finished pile
7. Working platform permanent including any enlarged
level. casing. base.
8. Pile toe level. 4. Length of 6. Type of boring.
9. Details of any finished pile 7. Time of commencement
obstructions. excluding any of boring.
10. Delays or other enlarged base. 8. Details of soil strata
interruptions to penetrated.
the sequence of 9. Details of soils samples
work including 1. Time of commencement and completion of driving
taken and in-situ tests
times. or re-driving.
carried out.
11. Cut-off level. 2. Type, weight, drop and mechanical condition of
10. Details of any
12. Head level of hammer used.
interruption in boring.
completed pile. 3. Number, type and condition of the packing on the
11. Standing ground water
13. Ground heave. pile head.
level and water strikes
4. Type and condition of the dolly in the helmet.
during boring.
5. For a single acting hammer, the final drop.
6. For a double acting hammer, the final frequency of
blows.
7. The sets taken at intervals during the last 3 m of
driving, if required.
8. Details of any interruption in driving.
9. Details of re-driving.

1. Method of placing concrete.


2. Concrete mix details:
3. Grade of concrete
4. Nominal maximum aggregate size
5. Cement content
6. Type and quantity of admixtures
7. Water/Cement ratio.
8. Measured slumps.
9. Batch times.
10. Time of commencement of concrete pour.
11. Time of completion of concrete pour.
12. Volume of concrete placed in enlarged base.
13. Volume of concrete placed in pile shaft.
14. Reinforcement details:
15. Number, type and size of main reinforcing bars.
16. Type, size and pitch or spacing of helical binding
or link bars.
17. Length of individual reinforcement cages.
18. Total reinforced length of pile

Table 10.1.3-2: Piling Records.

Notes:

1. The 24 hour clock shall be used. 3. For driving operations not using a piling hammer,
2. For any pile not completed in the working day equivalent information to that required on type,
the date shall be entered in the records together weight, drop etc of hammer, packing and dolly
with the times of commencement and shall be provided.
completion.

♦ 10-2 ♦
10.1.3.2 Cast in Place Piles Test Method
and Apparatus
1 Temporary casings or linings shall be used when complying
needed to maintain the stability of the pile borehole with the
during excavation. Casings shall be free from distortion American Samples
Petroleum from
and projections, and shall be uniform section throughout
Institute (API) Sample as excavation
their length. recommended supplied to
Property prior to
2 In case where permanent steel casings is required, practice for excavation placing
steel pipe casings of minimum wall thickness indicated Field Testing concrete
with inside clear diameter not less than diameter of pile of Water-
Based Drilling
shall be installed as follows:
Fluids – API RP
i. Install casings as excavation proceeds, to 13B-1
maintain sidewall stability.
Less than Less than
ii. Fabricate bottom edge of lowest casing section Density Mud balance
1.10 g/ml 1.15 g/ml
with a cutting shoe capable of penetrating rock
Fluid
and achieving a water seal. Low Less than Less than
loss
iii. Connect casing sections by continuous temperature 30 mil 40 mil
(30 min.
test fluid loss (0.762mm) (1.016mm)
penetration welds to form a watertight, test)
continuous casing. 30 to 40 Less than
Viscosity Marsh Cone
iv. Remove and replace, or repair, casings that seconds 60 seconds
have been damaged during installation and Fann
viscometer
that could impair strength or efficiency of Plastic Less than Less than
(material
drilled pile. viscosity 10 cP 20 cP
passing sieve
v. Fill annular void between casing and shaft wall No. 200)
with sand-cement grout. Shear
vi. Corrugated casings formed from zinc-coated strength
Fann 4 to 25 4 to 25
steel sheet may be delivered in sections or (10 min.
viscometer N/m2 N/m2
panels of convenient length, and field gel
strength)
connected according to manufacturer's written
Sand Sand screen Less than Less than
instructions.
content set 1% 3%
3 The drilling fluid shall be maintained at an adequate Electrical pH
viscosity and density. Action shall be taken to prevent the PH meter range 9.5 to 10.8 9.5 to 11.7
spillage of bentonite slurry onto the site. Disposal of used pH 7 to 14
slurry shall be made to a tip approved by the Engineer. Table 10.1.3-3: Tests and Compliance of Slurry.
4 When drilled shafts are to be stabilized with slurry,
the slurry shall be maintained a minimum of 1500 mm iv. Drilled pile shaft shall be excavated and
above ground-water level and above unstable soil strata to completely concreted on same day or the shaft
prevent caving or sloughing of shaft. Excess slurry head is shall be re-drilled, cleaned, re-circulated, de-
to be related to performance of on-going dewatering and sanded, or slurry replaced.
to allow for fluctuations in depressed water levels. v. Bottom of each shaft shall be cleaned before
i. Each batch of freshly prepared or reconstituted concreting.
slurry shall be sampled and tested. Test results 5 Pumping of ground water from boreholes will only
of samples and from excavation shall reflect be permitted where there is no risk of removal of fines
the amount of contamination with saline from the subsoil. Water which cannot be sealed off shall
ground water. be maintained in the borehole at a level above the
ii. At least one sample from the base and one standing ground water.
sample from the top of each shaft shall be
6 On completion of boring, loose soil and debris shall
tested immediately prior to placing steel and
be removed from the base of the pile and the Contractor
concrete. The Engineer may subsequently vary
shall provide facilities required by the Engineer to facilitate
frequency of sampling and testing when a
inspection of the pile base. The method of descent and the
working pattern has been established.
equipment used shall comply with BS 5573.
iii. Tests and Compliance: Values measured at 20
7 If reinforcement cages are used they shall be rigid
deg C shall be as Table 10.1.3.3
and installed and maintained in the correct position during
concreting.

♦ 10-3 ♦
head of the pile. Each pile shall be marked at intervals of
10.1.3.3 Placing Concrete 250mm along the top 3m of its length before being driven.
1 The concrete shall be placed without interruption. 2 Only the designed lifting and support points shall be
Records shall be kept of the workability of the approved used during transport and piles shall be stored on
mix. Under water concrete shall be placed only by tremie. adequate supports located under these lifting points of the
The tremie pipe shall be clean and watertight throughout piles. Piles within a stack shall be in groups of the same
and not less than 200 mm internal diameter. Concreting length. Packing of uniform thickness shall be provided
shall start only after the tremie reaches the bottom of the between piles at the lifting points.
pile shaft and concreting shall then proceed with the end 3 During driving, piles shall be adequately supported
of tremie pipe kept immersed in the concrete for a and restrained by means of leaders, trestles, or other
minimum depth of 1 m. Spacer blocks shall be installed as guide arrangements to maintain position and alignment
appropriate to maintain the minimum concrete cover to and to prevent buckling. The Contractor shall satisfy the
the reinforcement steel as specified and/or shown on Engineer regarding the suitability, efficiency and energy of
Drawings. the driving equipment. Piles shall be driven continuously
2 Permanent casing shall be checked for damage. If until the prescribed set or depth has been reached.
necessary the casing shall be withdrawn, repaired, re- 4 The final set of the pile shall be recorded either as the
driven, or other action taken to allow the construction of penetration in millimeters per 10 blows or as the number
the pile. of blows required to produce a penetration of 25mm.
3 Temporary casings shall be extracted while the 5 When a final set is being measured, the following
concrete remains sufficiently workable. While the casing is requirements shall be met:
being extracted a sufficient head of concrete shall be i. The exposed part of the pile shall be in good
maintained within it to avoid necking in the pile. No condition without damage or distortion.
concreting shall be done once the casing has been lifted ii. The dolly and packing, if any, shall be in sound
above the top of the concrete. Withdrawal of temporary condition.
casing shall be coordinated with concrete placement iii. The hammer blow shall be in line with the pile
operations to maintain a head of concrete no less than axis and the impact surfaces shall be flat and at
1500 mm above casing bottom. right angles to the pile and hammer axis.
4 Casings for driven cast-in-place piles shall be iv. The hammer shall be in good condition and
installed to the approved set or specified depth and in the operating correctly.
sequence approved by the Engineer. Each length shall be v. The temporary compression of the pile shall be
driven continuously. Levels shall be taken immediately recorded if required.
when the final depth is approved, before concreting has
6 Piles shall be driven in an approved sequence to
begun. The casings shall be watertight.
minimize the detrimental effects of heave and lateral
10.1.3.4 Preliminary Drilled Piles displacement of the ground. When a pile has risen as a
result of adjacent piles being driven, the contractor shall
1 Construct preliminary drilled piles of diameter and submit to the Engineer proposals for correcting this and
depth and at location indicated or if not indicated, as its avoidance in subsequent work.
directed by the Engineer, of same diameter and depth as
7 If repairs are needed during driving to the head of a
permanent drilled piles, located at least 3 diameters clear
pile, it shall be cut off square at sound concrete, and loose
of permanent drilled piles, to demonstrate Installer's
material removed by wire brushing, followed by washing
construction methods, equipment, standards of
with water. If the pile is to be subjected to further driving,
workmanship, and tolerances.
the head shall be replaced by concrete of an approved
i. Install casing or use bentonite slurry, excavate
class.
bell if applicable, excavate rock socket, all as
required for permanent drilled piles. 8 Piles shall be lengthened, if required, by stripping off
ii. Install reinforcement, fill with concrete, remove concrete from the reinforcement and lapping, coupling or
temporary casings, if applicable, and terminate welding additional steel in place. Laps shall be at least 40
preliminary drilled pile as instructed by the x bar diameter. Couplers shall be approved by the
Engineer. Engineer. Steel to be welded shall be free of concrete for
iii. If Engineer determines that a preliminary drilled at least 300 mm below the weld. Welded joints shall be
pile does not meet requirements, excavate for made in accordance with the relevant Clauses of Section 6.
and cast another until preliminary drilled pile is 9 Repaired or lengthened piles shall not be driven until
accepted. the added concrete has reached the specified
characteristic strength of the concrete of the pile.
10.1.3.5 Precast Concrete Piles

1 After a pile has been cast, the date of casting and


reference number shall be permanently inscribed on the

♦ 10-4 ♦
10.1.3.6 Steel piles length shown in the approved Drawings or as per the
modifications approved by the Engineer. Any
1 Piles shall be clearly marked in white paint with their unauthorized extra length cast by the Contractor shall not
number and overall length. In addition, each pile shall be be measured for payment.
marked at intervals of 250mm along the top of 3m of its
3 Expendable piles (non-working piles) that are
length before being driven.
constructed for the purpose of carrying out preliminary
2 If steel piles are to be pre-coated, the preparation of load tests shall be measured in linear meters of actual
surfaces and the application of the coating shall be carried length, ordered and tested.
out by experienced specialist labor.
3 Surface preparation, priming and protective coats 10.1.5 Basis of Payment
shall conform to the requirements of Section 7 “Paint for
Steelwork”. 1 The amount of completed and accepted work
measured as provided for above will be paid for at
4 Rolled steel sections shall be within the tolerances
the unit rates for the various types of piles in the Bill
specified in BS 4. For steel piles and proprietary rolled
of Quantities, which rate shall be full compensation
sections, the deviation from straightness shall not exceed
for supplying and installing piles and for materials,
1/1000 of the length of the section.
labor, equipment, tools, records and other items
5 Cylindrical steel piles shall not deviate from
necessary for the proper completion of the work.
straightness by more than 1/600 for the length up to 10m
and 1/1000 for lengths greater than 10m. The actual mass
of each section shall be within +5% and -2.5% of the
10.1.6 Items in the Bill of Quantities
theoretical mass computed in accordance with Section 6. i. Setting up at each pile location nr.
6 Sheet piles shall be pitched and supported as a panel
ii. Piling (type)(length)(size) lin.m.
before driving and securely interlocked. Piles shall not
overlap each other and no pile in a panel shall be more iii. Expendable piles (type)(length)(size) lin.m.
than 1 m in advance of another.
7 Sheet piles previously driven shall not be used in the 10.2 Pile Testing
Permanent Works unless approved.
8 Steel piles shall be driven to a prescribed set or 10.2.1 Description
depth in a sequence approved by the Engineer. Driving
1 This Sub-section describes requirements for testing
shall be continuous.
of concrete piles as follows:
9 If approved, piles shall be lengthened by full i. Static-load testing: ASTM D1143 and ASTM
penetration butt welding. Lengthening sections shall be of D3689.
the same rolling. Longitudinal and spiral seam welding of ii. Non-destructive, sonic or low-strain integrity
cylindrical piles shall be staggered. testing: ASTM D5882.
10.1.3.7 Tolerances
10.2.2 Submittals
Vertical piles shall be constructed to remain within the
1 The Contractor shall submit a method statement for
following tolerances:
each type of testing specified and provide details of
i. Maximum variation from location: Not more specific techniques and processes proposed to be adopted
than 75 mm from design center location. for testing. The method statement shall include details of
ii. Out-of-plumb: 1 in 75 deviation or not more than equipment and instrumentation, quality control and report
1.5 percent of pile length, whichever is less. procedures, work program, and any other information or
iii. Concrete cutoff level: Plus 25 mm or minus 75 special data required by the Engineer.
mm from level indicated. i. The method statement shall include details of
iv. Bottom area of pile: Not less than 96 percent of loading and arrangement of reaction frame,
pile area required. reaction piles or anchors. Due consideration
v. Shaft diameter for drilled pile: Not less than 98 shall be given to the effect of diameters of piles,
percent or more than 110 percent of shaft socket length, type of bedrock, strain
diameter indicated. measurement in steel reinforcement and effect
of dewatering. The structural analysis data shall
10.1.4 Method of Measurement be supervised, signed and sealed by the
qualified professional independent engineer
1 Setting up at each pile shall be measured by number.
responsible for their preparation.
2 Piles shall be measured in linear meters of actual
length placed in the Permanent Works. The measured 2 The Contractor shall submit daily work progress
length shall be from the tip to the underside of the reports, identifying individual piles and type of testing
foundation, plus the penetration into the foundation carried out.
specified on the Drawings. The payment shall be made for

♦ 10-5 ♦
3 For non-destructive integrity testing, the Contractor times working load. The Contractor shall perform
shall qualify and engage an experienced independent at least two preliminary pile tension load tests
testing agency, acceptable to the Engineer, who has and two preliminary pile compression load tests
specialized in non-destructive testing of drilled piles to cover the different rock configurations or as
similar to that required for the Project. specified on the Drawings or in the Special
Specification.
10.2.3 Execution ii. Working piles in tension or compression load
tests: Apply test loads up to 1.5 times working
10.2.3.1 Preparation load, as specified on the Drawings or in the
1 The Contractor shall protect structures, utilities, Special Specifications.
sidewalks, pavements, and other facilities from damage 6 In the event of a pile continuing to displace under
caused by settlement, lateral movement, vibration, and constant load before the maximum test load has been
shall verify the feasibility of testing the loads reached, take readings at 15 minute intervals for a period
corresponding to each pile diameter. The pile load tests of one hour while the load is being maintained. Unload
shall not be carried out until all shrinkage of the concrete the pile in approximately 4 to 6 equal decrements at 15
is complete. The reinforcement in the rock socket shall be minute intervals and allow recovering for 3 hours. Take
strain-gauged to provide confirmation of the tensile force one set of displacement readings after each decrement of
reaching the socket. load and a further set of readings at the end of the
i. Dynamic formulas will not be permitted in place recovery period.
of load tests to determine bearing values of the
piles. 10.2.3.2 Non-Destructive, Low-Strain Integrity Testing
ii. Perform and complete testing, and obtain
1 Non-destructive, integrity testing by sonic logging
approval of preliminary pile test before
shall be performed on all piles, or as specified on the
proceeding with installation of permanent
Drawings and \special Specification, recorded, interpreted
working piles in the Works.
and reported by an approved experienced independent
iii. Select the pile to be tested based on the results
testing agency that has specialized in non-destructive
of pile integrity tests and pile construction
testing of piles similar to that required for the Project.
records subject to the approval of the Engineer.
Submit proposed test result and report formats to the
iv. The same piles that will be tested in working
Engineer for approval before starting integrity testing.
compression loading shall be among the
i. Provide all available details of the ground
selected piles for the working load test in
conditions, pile dimensions and construction
tension.
method to the testing agency before the
2 Pile Tests: Arrange and perform the following static- commencement of integrity testing, in order to
load tests on piles as and when directed in the field: facilitate interpretation of test results.
i. Axial Tension Static-Load Test: ASTM D 3689. ii. Allow a minimum of seven days to elapse after
ii. Axial Compression Static-Load Test: ASTM D casting before performing integrity testing on a
1143. pile.

3 Provide pile reaction frame, equipment and 2 Perform low-strain integrity testing according to
instrumentation with sufficient reaction capacity to ASTM D5882 by the stress wave method, seismic method
perform tension tests and compression tests. On or other method approved by the Engineer, based on the
completion of testing, remove testing structure, measurement of the axial shaft point mobility at the pile
equipment and instrumentation. head.
i. Notify Engineer at least 48 hours in advance of i. Where the method of testing requires the
performing tests. positioning of sensing equipment on the pile
ii. Provide facilities to enable Engineer to observe head, break down the pile head to expose sound
and check testing. clean concrete, free from water, laitance, loose,
overspill or blinding concrete, and readily
4 Apply test loads by jacking against beams or accessible for the purpose of testing.
equivalent reaction system.
i. Center to center spacing of vertical reaction piles 10.2.3.3 Test Records
from a test pile shall be not less than 3 times the
1 General: Maintain accurate test records for each pile,
diameter of the test pile or the reaction piles or 2
compiled and attested to by a qualified professional
m whichever is the greater.
engineer, and submit to the Engineer at the conclusion of
5 Test Loads: Maximum loads to be applied in each pile test. Include the following data:
maintained load test shall be as follows: i. Project name and number.
i. Expendable preliminary piles in tension or ii. Pile number and date of testing.
compression load test: Apply test loads up to 2.5 iii. Pile dimensions.
iv. Type and method of pile testing.

♦ 10-6 ♦
v. Test results. 10.2.6 Items in the Bill of Quantities
2 Prepare static load test results in the form of i. Static load testing of expendable piles
tabulated field observations, including the following data: (type) (length) (size). nr.
i. Time vs. displacement curves. ii. Static load testing of working piles (type)
ii. Time vs. load curves. (length) (size). nr.
iii. Load vs. displacement curves. iii. Non-destructive integrity test (type) nr.
iv. Displacement vs. log time for each stage.

The Engineer will review test results and determine if a


pile is acceptable, taking into account the acceptable total
and differential displacements of the superstructure, the
foundation geometry, the pile type and the soil conditions,
etc.

10.2.3.4 Static-Load Testing

1 General: Static-load tests will be used to verify and


confirm design load capacity of piles. Each pile diameter
shall be tested as shown on the Drawings. The Contractor
displacement characteristics compared to preliminary test
piles will not be accepted.
2 Non-Destructive Integrity Testing:
i. All piles shall be subjected to integrity testing.
ii. Submit preliminary test results to the Engineer
within 24 hours of carrying out the tests.
iii. Submit test reports to the Engineer within 10
days of the completion of each phase of testing.
iv. Test reports shall contain test results and
conclusions, together with a summary of the
method of interpretation including all
assumptions, calibrations, corrections,
algorithms and derivations used in the analyses.
Where results are presented in a graphical form,
the same scales are to be used consistently
throughout the report and the units on all scales
clearly marked.
v. If any anomaly in acoustic signal test results
indicates a possible defect in a pile, report such
anomalies to the Engineer immediately.
Demonstrate to the Engineer that the pile is
satisfactory for its intended use or carry out
remedial works to the Engineer’s satisfaction.
vi. Grout sonic logging tubes only after piles have
been demonstrated to the Engineer’s
satisfaction, to be satisfactory.

10.2.4 Method of Measurement


1 Pile loading tests shall be measured per number.
2 Pile integrity tests shall be measured per number.

10.2.5 Basis of Payment


1 The amount of completed work of “Pile testing” will
be paid for at the unit rate in the Bill of Quantities which
rate shall be full compensation for setting up, carrying out,
reporting and for labor, transport, equipment, tools,
materials and other item necessary for the proper
completion of the work.

♦ 10-7 ♦

You might also like