Professional Documents
Culture Documents
Final MBA-Project MD Dawood Alam
Final MBA-Project MD Dawood Alam
Report submitted to
By
Md Dawood Alam
April 2019
1
DECLARATION
I, Md Dawood Alam, hereby declare that The thesis entitled “To study the Reason of Failure of
Amrapali Group Projects in Noida” in fulfilment of the requirements for the award of the degree of
Master of Business Administration (Executive) which is submitted by me to the Centre for Management
Studies, Jamia Millia Islamia University, New Delhi has been done by me and that, to the best of my
knowledge and belief, it contains no material previously published or written by another person nor
material which has been accepted for the award of any other degree or diploma ,Associateship,
Fellowship or other similar title or recognition. This is the original work and is the result of my own
efforts.
Dated: 18-04-2019
2
CERTIFICATE
On the basis of the declaration submitted by Md Dawood Alam, a student of MBA-Executive, I hereby
certify that that the project report titled “To study the Reason of Failure of Amrapali Group Projects in
Noida” which is submitted to the Centre for Management Studies, Jamia Millia Islamia University, New
Delhi in partial fulfilment of the requirements for the award of the degree of Master of Business
Administration, is an original contribution with existing knowledge and faithful record of research
carried out by him under my guidance and supervision. Certified further, that to the best of my
knowledge the work reported herein does not form part of any other project report or dissertation on the
basis of which a degree or award was conferred on an earlier occasion on this or any other candidate.
3
ACKNOWLEDGEMENT
Words are indeed inadequate to convey my deep sense of gratitude to all those who have helped me in
completing this summer project to the best of my ability. Being a part of this project has certainly been a
I am grateful to Mr. Syed Zakir Hussain, Jamia Millia Islamia for making all kinds of arrangements to
carry the project successfully and for guiding and helping me to solve all kinds of queries regarding the
project work. His incomparable guidance has inspired the pace of the project largely. I am also grateful
to Ex-employee of Amrapali Group, Vendors’ staff and other seniors/colleagues whose time to time
In the end, I would like to express my utmost gratitude towards my Parents, Wife and Friends whose
4
CONTENTS
Cover page 1
Declaration 2
Certificate 3
Acknowledgement 4
Contents 5
Abstract 6
Introduction 7–9
Literature review 10 – 34
Motivation of study 35
Research Methodology 36 – 51
Conclusion 52
References 53 - 55
5
ABSTRACT
Failure to projects is one of the foremost concerns of any industry especially for Amrapali Group
which creates Problems for 42000 Homebuyers. The Failure to the projects is affecting the economies
throughout the world. Failure to projects mean the slowdown of development in all other related fields.
The main aim and objective of this report is to evaluate the reasons for those Failure that were
To know where exactly Amrapali group was lagged in race of leading developer in Noida, study focus
on best practices in the industry by top project management organizations and reason of construction
failure of similar projects and Amrapali group Practices towards completion of Project.
To find the main reason of Amapali’s Project failure a set of questionnaires has been circulated among
employee & associates of Amrapali group and based on their responses main reason is found.
The main reasons for Failure was ignorance of Top management with some reason like Planning
Suggestion given to avoid such failure in future based on the Finding of this study.
INTRODUCTION
6
The reasons for the Failure of Amrapali projects are identified so that the effect on similar construction
projects can be reduced. What are the major factors that should be consider avoiding this type of failure
Projects are envisaged and visualized with the foresight of achieving the primary objective of timely
completion. Some projects are planned and executed successfully whereas others get failure due to
reasons, Amrapali failed Projects will analysed and evaluated in this report.
Failure to projects is one of the common problems in the construction industry. Failure have a negative
effect on the project in terms of performance, time and cost. Thus, it is essential to identify the reason
This project report will ensure the reason of failure that can help to home buyer to evaluate the
progress, process of construction activities at site and how project management implementation is
essential towards successful completion of projects. So that before taking final decision of purchasing
home, shops, offices etc. they can evaluate it and decide accordingly.
Amrapali Group has failed to hand over possession of flats to around 42,000 homebuyers. This is big
concern of the study so that after getting main reason of failure proper preventive steps should be taken
7
Amrapali group of builders is based at Noida and currently developing several residential and
commercial projects at Noida, greater Noida and Ghaziabad. At Amrapali the focus is on big
residential projects with huge open spaces filled with all games. Projects of Amrapali are unmatched
in its strategic location and construction speed. Different kind of residential properties like villas, flats,
duplexes, row houses, studio apartments and theme based residential flats are under development at
current projects. Most of the projects have reached in final stages of construction and remaining are
also at very fast pace as Amrapali group have hired best contractors like L&T for structure work of
some of its projects. Factors like tower placement, loading area, firefighting measures, landscaping,
eco friendliness and good outer façade have been specially taken care in all our projects.
Why Amrapali?
If you are looking to buy good residential and commercial property at most prime locations of Noida,
greater Noida and Ghaziabad, you should buy property of Amrapali group. With Amrapali your hard-
earned money is not only safe but would also reap financial benefits for you. (Claimed by
AMRAPALI Group.)
We take great pride in the fact that we have completed and handed over all of our housing
developments well before the scheduled time. Move into an apartment of Amrapali in Noida and you
8
Amrapali Group Projects in Noida
9
LITERATURE REVIEW
10
Supreme Court asked the realty firm to reveal by Dec 3, 2018 the details of all its properties in the
name of directors, their family members, relatives, Chief Financial Officers and statutory auditors in
11
Delayed possession and false promises land Amrapali Group in serious trouble, as homebuyers cry foul,
After taking the homebuyers for a ride long enough, the Amrapali Group seems to have ran out of luck
with the homebuyers taking to social media to mobilise support, the brand ambassador Mahender Singh
Dhoni exiting as face saver and the political support to the builder deserting.
Amrapali Group, after much-publicised “Mission Possession” has only been diverting the attention of
the buyers till the residents of Amrapali’s Saphhire project in Noida lost their patience and went viral on
Twitter. They also tagged the brand ambassador Mahender Singh Dhoni in their tweets asking the
Residents are complaining about the pending civil and electrical works in the project. The company said
12
Amrapali Group CMD Dr Anil Sharma said, “Sometimes there are so many unforeseen reasons. There
are so many force majeure, which are beyond the control of a developer. So, during those periods’
construction is stopped for two years, three years, four years, and five years. Those periods can’t be
contracted. There are two losses, one is time loss, and another is finance loss. We are not burdening that
finance loss to our esteemed customers, but time loss we can’t make up. Ultimately, time loss has to be
extended.”
As the homebuyers were welcoming the Dhoni’s rebuttal to Amrapali, another cricketer Harbhajan
Singh tweeted: “Well done @msdhoni for dropping #Amarpali builders’ brand ambassadorship. They
didn’t gave us VILLAS they announce after 2011 worldcup win”. (Track2reality Apr 17, 2016).
News 3: Amrapali Group Case Supreme Court Orders Sale of Directors' Assets
13
(NBCC will conduct valuation of the properties belonging to the directors of the Amrapali group).
Amrapali Group has failed to hand over possession of flats to around 42,000 homebuyers.
14
The Supreme Court on Thursday identified 16 estates belonging to beleaguered property developer
Amrapali Group to raise funds for stalled projects. The court directed sale of assets owned by all of the
company's directors, their family members and related companies. The case relates to the
embattled Amrapali Group which has failed to hand over possession of flats to around 42,000
homebuyers. The property developer has been facing the wrath of Supreme Court after homebuyers
moved the court for not getting their flats delivered on time. Setting September 12 as the next date of
hearing in the case, the Supreme Court asked for a list of unencumbered assets of the company's
directors.
1. National Buildings Construction Corporation (NBCC) will conduct valuation of the properties
belonging to the directors of the Amrapali group, the court ruled on Thursday. State-run
construction company NBCC had earlier this week told the Supreme Court that it was ready to
2. On Thursday, the Supreme Court ordered a forensic audit of bank accounts from 2008. In August
this year, it had directed the group companies to produce before it details of all the bank accounts
since 2008 and ordered freezing of bank accounts of the directors of its 40 firms, slamming the
group for playing "fraud" and "dirty games" with the court.
3. Assuring NBCC of funds to complete 46,575 flats of crisis-hit Amrapali Group at an estimated
cost of Rs. 8,500 crore, the court had on Tuesday asked the Amrapali Group to cooperate with
15
the auditors or face sealing of its premises and forensic audit of accounts of all entities including
directors, their wives and daughters, according to news agency Press Trust of India.
4. In May, the apex court had spotted diversion of funds to the tune of over Rs. 2,700 crore by the
Amrapali Group and sought details of financial transactions made by the company and its
statement of accounts.
5. The company had earlier told the top court in an affidavit that it was not in a position to complete
the projects and hand over the possession of flats to over 42,000 homebuyers in a time-bound
For commercial contractors, both GCs and subs, a successful project is one completed on time and
within budget. The client is happy with the finished product and the contractor walks away with a tidy
profit. Everybody wins. When a project fails, it’s typically due to conflicts and issues that cause cost
If not properly managed, it will eventually lead to going over budget and blowing past the scheduled
date for substantial completion. Going over budget eats into the contractor’s profit in addition to being
hit with liquidated damages for every day past the agreed upon completion date. It can also impact
upcoming projects if a contractor’s workers and equipment are tied up trying to finish up a failing
project.
“Failure is not an option.” – Ed Harris as NASA Flight Director Gene Kranz in Apollo 13.
So what causes construction projects to fail? Any number of factors can lead to project failure, but most
of the time it boils down to how well the project manager or project management team performs
16
overseeing the project. Even the most difficult, issue-laden projects can be successful if properly
managed.
Here are five reasons construction projects fail and how to prevent it from happening on your next
project:
1. Inadequate Planning
Poor planning leads to poor execution. The more time and effort put into planning out the project, the
better off you’ll be when work gets underway. This starts by carefully reviewing and fully understanding
the plans, specifications, scope of work and client expectations. Good planning involves working with
working with the client, architect, subcontractors and suppliers to establish construction schedules and
project milestones.
Planning goes beyond just creating a construction schedule. Additional items include conducting a risk
assessment and management strategy, developing site-specific safety plans, establishing contingency
plans, site logistics and lining up the delivery of materials and equipment. Keep in mind that the plan
and schedule are living documents that will have to be updated and adjusted as work on the project
progresses.
2. Failure to Communicate
among stakeholders breaks down or is mishandled, it can lead to delays, accidents, costly rework, and
unhappy clients. Keeping everyone up to date on changes to the work or schedule goes a long way in
17
Develop a communication plan and establish document control procedures. Designate a main point of
contact that all communication will flow through. All communication should be documented and shared
with the appropriate stakeholders. These include meeting notes, submittals, and requests for information,
invoices, daily reports, change orders and submittals. All correspondence, whether it’s emails, phone
calls or in-person conversations should be documented and saved. This goes a long way in settling any
disputes or disagreements that might arise throughout the course of the project.
The flow of communication affects the flow of a construction project. Problems and delays occur when
people stop communicating or responding to inquiries. Projects run smoother and get completed on time
Scope creep is the continuous expansion or changes to the project’s initial scope beyond what was
initially intended. Factors that lead to scope creep include poorly defined scope, incomplete plans and
specifications, poor communication, mismanagement of change orders and clients changing their minds
Change orders are similar in that they involve changes to plans outside of the original scope. Change
orders differ from scope creep because they can involve both additions and deletions from the original
scope. They can also be initiated by the owner, but GCs and subs can also request change orders and
Obviously, you shouldn’t take on a project with a poorly defined scope or incomplete plans and specs.
All construction methods finishes and materials should be determined long before you sign a contract
18
The construction contract should clearly state how any work outside of the original scope should be
requested and documented. No additional work should commence until a written change order has been
executed and authorized by the client. Additional costs and timeline extensions should be determined
and agreed upon. Don’t forget to work with your subs to determine how change orders might impact
We’ll ignore delays caused by events, such as natural disasters, that can’t be controlled by any of the
parties involved. These excused delays are handled under force majeure clauses in construction contracts
and protect the contractor from having to paying damages due to not performing or completing the
project on schedule.
Project schedules are based on productivity expectations. Each task or job requires a certain number of
man-hours to complete and are used to determine how many workers you will need to complete each
When workers don’t show up, get injured or goof off on the job, it can lower your productivity levels,
cause delays and throw your schedule out of whack. This could force you to bring in additional workers
or sub out more work which in turn lowers your profit margins.
Labour shortages and fewer skilled workers have only made the problem of productivity worse over the
past several years. Newer workers don’t have the skills and confidence to complete tasks at the same
speed as experienced veterans on your crew. Understanding the capabilities of your workers is vital
Conduct background checks and provide training to your employees to ensure they have the skills to
perform their job. Assign specific roles and responsibilities so that everyone knows what they should be
19
doing each day. Equip your workers with the proper tools and equipment needed to complete tasks
efficiently. Work with your subcontractors to determine whether they have the workforce available to
When projects are running smoothly, it’s easy to ignore early warning signs that trouble may be
brewing. Little issues can quickly snowball into major problems if left unchecked, causing projects to
fail. This can be caused by workers failing to report issues or not monitoring projects closely.
These minor issues are often put on the back burner while dealing with other aspects of the project. All
problems should be prioritized and handled accordingly when they arise. Project managers should be
able to analyse and troubleshoot issues as early as possible to avoid delays. Quick thinking and good
decision making are what sets great project managers apart from good ones.
Most organizations have experienced projects that did not end on time, were over budget, or changed in
scope over time. There are many pitfalls that can sink projects. Here we will focus on some basic
20
Senior management must prioritize requirements and make decisions. If any person is not actively
Most organizations have more opportunities and project initiatives than they can ever hope to fulfil.
Many companies embark upon more initiatives than they probably should, causing over worked and
Scope creep
Scope creep is a serious issue in many projects. Scope creep means an increase in what you have to
Gaps in communication
Once a project is in full swing, a common issue is communication. Most project teams use email to
communicate about their projects and tasks. The biggest complaint here is that project communication
resides in everyone’s email box. So, if a new resource joins the project, there is no centralized view of
21
Lack of visibility of all projects
A common reason why projects fail is related to visibility. All three tiers of the project team, executive
management, project managers, and team members, need access to the right level of information at the
right time.
Managing a project can be daunting. Whether planning your wedding, developing a new website or
building your dream house by the sea, you need to employ project management techniques to help you
succeed. I'll summarise the top seven best practices at the heart of good project management which can
Firstly, understand the project objectives. Suppose your boss asks you to organise a blood donor
campaign, is the objective to get as much blood donated as possible? Or, is it to raise the local company
profile? Deciding the real objectives will help you plan the project.
22
Scope defines the boundary of the project. Is the organisation of transport to take staff to the blood bank
within scope? Or, should staff make their own way there? Deciding what's in or out of scope will
Understand who the stakeholders are, what they expect to be delivered and enlist their support. Once
you've defined the scope and objectives, get the stakeholders to review and agree to them.
You must define what will be delivered by the project. If your project is an advertising campaign for a
new chocolate bar, then one deliverable might be the artwork for an advertisement. So, decide what
tangible things will be delivered and document them in enough detail to enable someone else to produce
Key stakeholders must review the definition of deliverables and must agree they accurately reflect what
must be delivered.
3. Project Planning
Planning requires that the project manager decides which people, resources and budget are required to
You must define what activities are required to produce the deliverables using techniques such as Work
Breakdown Structures. You must estimate the time and effort required for each activity, dependencies
between activities and decide a realistic schedule to complete them. Involve the project team in
estimating how long activities will take. Set milestones which indicate critical dates during the project.
Write this into the project plan. Get the key stakeholders to review and agree to the plan.
23
4. Communication
Project plans are useless unless they've been communicated effectively to the project team. Every team
member needs to know their responsibilities. I once worked on a project where the project manager sat
in his office surrounded by huge paper schedules. The problem was, nobody on his team knew what the
tasks and milestones were because he hadn't shared the plan with them. The project hit all kinds of
problems with people doing activities which they deemed important rather than doing the activities
Once your project is underway you must monitor and compare the actual progress with the planned
progress. You will need progress reports from project team members. You should record variations
between the actual and planned cost, schedule and scope. You should report variations to your manager
and key stakeholders and take corrective actions if variations get too large.
You can adjust the plan in many ways to get the project back on track but you will always end up
juggling cost, scope and schedule. If the project manager changes one of these, then one or both of the
other elements will inevitably need changing. It is juggling these three elements - known as the project
6. Change Management
Stakeholders often change their mind about what must be delivered. Sometimes the business
environment changes after the project starts, so assumptions made at the beginning of the project may no
longer be valid. This often means the scope or deliverables of the project need changing. If a project
24
manager accepted all changes into the project, the project would inevitably go over budget, be late and
By managing changes, the project manager can make decisions about whether or not to incorporate the
changes immediately or in the future, or to reject them. This increases the chances of project success
because the project manager controls how the changes are incorporated, can allocate resources
accordingly and can plan when and how the changes are made. Not managing changes effectively is
7. Risk Management
Risks are events which can adversely affect the successful outcome of the project. I've worked on
projects where risks have included: staff lacking the technical skills to perform the work, hardware not
being delivered on time, the control room at risk of flooding and many others. Risks will vary for each
project but the main risks to a project must be identified as soon as possible. Plans must be made to
avoid the risk, or, if the risk cannot be avoided, to mitigate the risk to lessen its impact if it occurs. This
You don't manage all risks because there could be too many and not all risks have the same impact. So,
identify all risks, estimate the likelihood of each risk occurring (1 = not likely, 2 = maybe likely, 3 =
very likely). Estimate its impact on the project (1 - low, 2 - medium, 3 - high), then multiply the two
numbers together to give the risk factor. High risk factors indicate the severest risks. Manage the ten
with the highest risk factors. Constantly review risks and lookout for new ones since they have a habit of
25
“Following these best practices cannot guarantee a successful project but they will provide a better
chance of success. Disregarding these best practices will almost certainly lead to project failure”
Is the project a success or a failure? Is there any way to determine or measure the success or failure of a
project? Success is perceived in different ways by all stakeholders involved. Atkinson8 notes that,
whilst there may exist differences in the project success definition, authors agree on the inclusion of the
triple constraint, to define the achievement or attainment of project objectives. The project success
definition has been studied and developed from the simple attainment of cost, time and quality criteria,
also known as the “iron triangle”, or “triple constraint”. But these criteria are part of a multi-
dimensional variable, which includes factors involving not only the project results, but also the
customer’s satisfaction and, ultimately, the organization6. The definition of success is so broad that it’s
As project success depends more on the perceptions of the stakeholders, probably there is no
“absolute success” in project management, but simply a “perceived success”. Projects that failed to
meet the original goals of the “iron triangle” criteria were not necessarily perceived as failed project.
In the literature we found many examples of projects that successfully fulfil the “iron triangle”
criteria but turned to be an unsuccessful business experience. On the other hand, there are projects
that haven’t meet the time, cost and quality constraints, but later became successful.
26
Pinto & Slevin, after analyzing a sample of more than 650 project managers’ opinions, concluded
that achieving project success is undoubtedly more difficult and far more complex than simply meet
the “iron triangle” criteria. Extending the project performance perspective, several authors state that
even a project incorrectly managed can achieve success and, conversely, cannot achieve the
expected results, despite being well managed. Project management objectives differ from project
objectives, the “iron triangle” is directly tied to a project management and for this reason is easy to
measure, and therefore there is a tendency to evaluate project success by project management
success.
Project success is evaluated against the overall objectives of the project, whilst project management
success is mostly evaluated against the “iron triangle. As project management evolved, however,
there was an increased focus on the behavioural aspects of project management and on the
management skills of project managers. In the last decades, a growing consensus has been reached
where upon that project success requires a wider definition than project management success.
Some researchers suggested that PCS should be specific to each project and that they should
therefore be determined by stakeholders at the start of each project. The CSF are those components
that are necessary to deliver the PCS and can be described as the set of situations, factors or actions
The PSC are used to measure project success whilst CSF facilitate the achievement of success.
Projects are developed in different contexts and environments and naturally have different critical
27
factors for consideration. Accordingly, “iron triangle” criteria are the classic answer to the problem
of how to measure project success. It is easily applied and normally gathers consensus within
stakeholders. The definition of project success became broader, with the addition of dimensions like
client satisfaction, realization of customer objectives, end-users satisfaction, and the satisfaction of
“The purpose of Benefits Management (BM) process is to improve the identification of the
achievable benefits and to ensure that decisions and actions taken over de lifetime of the investment
lead to realizing all the feasible benefits”. BM allows the sponsor to have the correct information for
the investment viability studies and clearly shows the way for the delivery of the expected benefits.
The Benefits Dependency Network (BDN) is the core technique of this methodology. First
introduced by Ward and Elvin was developed to promote the relationship between the investment
objectives and its promised benefits linked strategically and structured for business.
Based in the theoretical model of Soh and Markus (1995) this framework explains the steps involved
in creating value from IS/IT, and highlights the importance of business change in this process. BDN
provides explicitly the linkage between investment objectives and the related benefits (the ends),
business transformation necessary to deliver the expected benefits and IS/IT capabilities (the ways),
28
The BDN construction starts with understanding of the internal and external driver’s context and the
general agreement on the business benefits identification that will result if the investment objectives
are achieved. Is also needed to identify the changes to the ways individuals and groups works that
are a fundamental part of realizing the potential benefits identified. Each benefit should be
considered in turn and the changes that would be necessary to realize those benefits should then be
To reach a consensus on the benefits and changes in business, it is advisable to organize workshops
with all the relevant stakeholders to facilitate the alignment of the IS/IT investments and business
strategy. A wide range of different types of organizational changes could be performed, namely:
redefined measures and metrics and new practices and politics for managing and disseminating the
information.
There is also a set of changes that may be necessary in order to produce the expected changes in the
business, leveraging the attainment of the identified benefits. These enabling changes are only
required to be carried out once, and may be necessary for triggering business changes, mainly
through training, design new processes, defining new roles, redefinition of responsibilities, changing
organizational structures, establishing rules and practices or defining new governance structures.
The organization that hosted the case study was founded in 1973. It is a small-medium company,
leader in the field of geographic engineering, specialized in providing digital geographical products
and geo-referenced databases. Following on from the growing boom of road construction,
29
authorities soon realized that the large network of highways that had been created would require
The maintenance and upkeep of this infrastructure is a continuous process, which consumes a
significant amount of time and financial resources. The main difficulty found by managers was the
absence of digital information, much of it still in the paper form. This unorganized knowledge
prevented the timely decision-making process based on an adequate technical support. The situation
was further aggravated by several EU directives which imposed the standardization of conservation
In contrast to the considerable time and money that was spent in collecting and cataloguing all their
road assets, the proposed solution consisted of recording all road infrastructure components in just
one single trip. This approach was immediately adopted and had a considerable impact on the road
sector. The solution consisted in designing vehicles that combine a set of different sensors, video,
laser and image for geo-referenced information collection supported in global positioning system
The authors examined the effect of applying BM at CSF level to maximize the final results of the
project. Initially the study identified what PSC were relevant and what CSF increased the chances of
project success. Based on the BM approach, two workshops have been performed to gather
These workshops brought together all the most important stakeholders from the client and
organization in order to design a plan to achieve objectives and related benefits and get an
30
agreement on which business changes were needed to be implemented. Within these two sessions, a
A ranking was constructed based on the number of times each criterion was cited by the participants.
This list cannot be considered to be a measure of importance of each factor, but rather a means of
Support
2. Cost 3. Team Engagement 4. Resource
Availability
3. Technical Requirements 5. Risk Management 6. Business
Opportunity
4. Customer Satisfaction 7. Market Impact
31
Benefits management and the benefits dependency network
Driven by the internal and external challenges (Figure 1) the organization chose which IS/IT
investments were needed, identifying the business objectives (short-term) and business benefits
(medium and long-term) that will be achieved through organizational changes. The linkage of
strategic objectives was supported by a business case. The business case included a benefits
The value proposition for the customer is the focus of the business strategy. That included a unique
set of products, the service attributes, the customer relationship strategy and the corporate image.
The value proposition identifies how the organization stands out from competitors and helps connect
32
its internal and external processes to achieve better results. The internal and external drivers remind
us that organizational activity is driven by objectives and targets that intends to ensure full
satisfaction of customer/stakeholder’s needs, and pursuing financial goals. Once the organization
understands its customer and financial perspectives, it can then determine the means by which it will
achieve the differentiation and the necessary productivity improvements and the required business
changes. In order to enhance, control and evaluate the CSF achievement we apply the BM
investment lifecycle. Setting up the strategic objectives and benefits, then we proceed to build the
BDN. In Table 2 we list all the elements needed to the organizational changes and IS/IT enablers
agreed by the stakeholders. Each CSF was running as a particular project with a responsible
allocated to deliver the final goal. The application of the BM lifecycle to the CSF leads to a better
33
Objectives Business benefits Enablers IS/IT Enabling Business Changes
Changes
O1 – Market B1 – Better T1 – CRM E1 – PM C1 – Project planning
market communication E7 –
satisfaction E8 – Training
The network of cause and effect depicted in Figure 2 illustrates a framework that explicitly links the
investment objectives with expected benefits, identifying the processes and business activities that
are needed to realize the benefits required with the help of technological enablers.
34
PREVENTION OF FAILURE
35
Failure can be prevented by applying methods which can be implemented from the project
commencement itself like planning and analysing the requirements in detail which will allow the
mapping of resources. The risk can be identified to allow the estimation and allocation of works which
is required to be modularized. Escalation of issues at the appropriate times also ensures that the Failure
can be prevented.
The prevention of Failure is possible when all the project stakeholders work as a team to ensure the
success of the project. It is also important for the client to employ a proactive consultant, freeze the
design and details before the commencement of the project and employ good reputed contractors for the
project.
MOTIVATION OF STUDY
36
The motivation of this study is to evaluate the reason of Failure that occur in the Amrapali Group &
the reasons why Failure occur and to compare this with best practice of project management in the
industry.
To achieve the aim extensive study was made to understand the process & steps of Project
management and where Amrapali group was failed to analyse its future?
OBJECTIVES OF STUDY
To study the best practice of Project management in the construction industry and suggest
To prevent failure of similar projects in future which creates problems for home buyers.
To identify how Project management tools and technique is essential for successful completion
of project on time.
To help home buyers to evaluate the basic progress, Process of construction activities and
RESEARCH METHODOLOGY
Research Technique
37
Research methods adopted to take Primary data from Amrapali Employee and secondary data through
various past projects failed in the industry and news related to Amrapali group. After data collection it
is analysed to find out root cause of failure of Amrapali Projects. A questionnaire has been circulated to
Research Problem
What are the main Reason of the Amrapali Group projects failure? And to suggest the best method
Data Collection
To solve the Research problems primary data has been collected from Amrapali Employee & associates
Secondary data has been collected from past failed projects and compare the gap with the best practices
in the industry.
This data analysis will help us to understand the actual failure reason of Amrapali projects based on the
data collected. We will analyse the responses and discuss the findings here.
Data Analysis
After extensive analysis in the questionnaire & responses I find main 5 failure reasons are as below:
Execution Failure
After analysis on these failure reasons and their response in % which help us to understand root cause
Findings
Based on the Analysis Top five failure reasons find with the average percentage of response on the
Thus, it is found that it is complete failure due to Top Management ignorance whereas Planning,
Monitoring & Control Failure are also among the top reasons of Failure.
39
Following Questionnaire has been circulated among the Amrapali employee or its associates and their
responses collected.
Following suggestion can be given based on the finding in Amrapali group for the betterment of the
Top Management should focus on Overall Performance of team otherwise their ignorance will
Separate planning team for each project or at least for 4-5 projects which regularly review their
Time analysis (Proposed & actual) should be consider very seriously, Past project experience
should be considered.
Proper Monitoring Control should be implemented on Projects and for that review meetings
should be planned.
their ideas; Appraisals should be there which will further help to remove bottleneck from the
process.
Well experienced Professionals can be used in Project Execution to have thorough knowledge of
40
Proper Project management practices increases chance of project success and for that PMI
Nowadays Project management consultant (PMC) is there who is ready to help technically and
Received 32 response in which 30 from the employee of Amrapali group and its associates which
needs to be analysed.
41
Projects at which respondent were worked.
We can see that project was going on without planning team as more than half of the respondent
42
Almost 65% agreed that they were not serious towards Planning & Scheduling activities which is
We can analyse that 75% respondent accepted that Planning failure is the main reason of Amapali’s
project failure.
43
Here
we can also say that almost 60% respondent agreed that projects was not managed professionally.
Corru
ption was involved in execution (56.3%) which leads to hamper project completion and even false
44
Mean
s they neither achieved nor trying to achieve the Execution Schedule as 75% response says if we
combine both.
45
Most of the respondent agreed that top Management & Finance Department were accountable for
46
Finan
ce Department was failed to handle cash flow perfectly and professionally as 65% response with
47
Top
management was failed in financial management and ignoring finishing cost of already ongoing
47% response was not clear about Contesting election was creates financial problem by CMD of
Amrapali group.
48
85% answer says that they were not monitor the projects and no review meetings. It means no
49
Al
most 56% agreed they were not serious as project goes out of control.
50
R
espondent feel that if the project monitor & Control professionally then they may not failed.
(78%)
51
A
udit was conducted (53% agreed) but just for formalities as result shows because in audit they
52
No material reconciliation happens as 66% accepted.
53
Tr
ansparent audit was missing that’s why almost all problems & corruption was hidden (78%).
54
72% answer says that Top management was failed to identify accountability and responsibility
of project successful.
55
56
Here also 84% agreed that Top management was responsible.
FAILURE.
57
22. Can you describe in brief the actual reason of Failure in Amrapali Projects?
1. Corruption
2. Senior management
relatives who was taking care of top activities of the projects who done the complete corruption
8. Poor management
9. NA
11. The reason of failure is competition of loot money of investor or create personal assets by cmd
13. Main reason was there was no planning and lack of coordination between employee
14. No
15. Corruption
18. yes
58
19. Yes project management
20. None
24. Yes,
30. Miscommunication
31. Politics
In the above response mostly feels that Top management was mainly responsible for failure of
Amrapali group.
CONCLUSIONS
59
It is conclude that based on data analysis and findings main reason of Amrapali projects failure is
ignorance of Top Management and to avoid failure like Amrapali group every organization needs to
adopt best practices of Project management as per PMI standard, use PMP certified staff, manage
Homebuyers should also check the given advice while going to purchase home so that they cannot be
It is summarising that after having 42 projects in Noida and one of the leading developers at that time
was not able to survive due to top management failure, planning failure, monitoring & Control failure.
The major gap found between well managed organization that practices project management perfectly
(as per PMI) and whereas Amrapali group was not managed professionally. This ignorance and
cheating behaviour created problems of 42000 house buyer in Noida who still fight for getting homes.
This was mainly because of ignorance of top management who failed to analyse properly to adopt best
REFERENCES
60
Abbasi, N., Wajid, I., Iqbal, Z., & Zafar, F. (2014). Project failure case studies and
Bezak, S., & Nahod, M. M. (2011). Project manager's role analysis as a project management
Bryde, D. J. (2005). Methods for managing different perspectives of project success. British Journal of
Management, 16(2), 119-131.
Davis, K. (2014). Different stakeholder groups and their perceptions of project success. International
Gomes, J., & Romão, M. (2016). Improving project success: A case study using benefits and project
Gudienė, N., Banaitis, A., Banaitienė, N., & Lopes, J. (2013). Development of a conceptual critical
success factors model for construction projects: a case of Lithuania. Procedia Engineering, 57, 392-
397.
Han, W. S., Yusof, A. M., Ismail, S., & Aun, N. C. (2012). Reviewing the notions of construction
Howsawi, E., Eager, D., Bagia, R., & Niebecker, K. (2014). The four-level project success framework:
Ilieş, L., Crişan, E., & Mureşan, I. N. (2010). Best practices in project management. Review of
61
Kendall, G. I., & Rollins, S. C. (2003). Advanced project portfolio management and the PMO:
Masurkar, Y. S., & Attar, A. C. (2014). Investigating the causes for failures in construction by taking a
McLeod, L., Doolin, B., & MacDonell, S. G. (2012). A perspective‐based understanding of project
Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project
202-217.
Pinto, J. K., & Mantel, S. J. (1990). The causes of project failure. IEEE transactions on engineering
management, 37(4), 269-276.
engineering, 196, 607-615.
engineering, 196, 607-615.
Ribeiro, P., Paiva, A., Varajão, J., & Dominguez, C. (2013). Success evaluation factors in construction
project management—some evidence from medium and large Portuguese companies. KSCE Journal of
Serrador, P., & Turner, J. R. (2014). The relationship between project success and project
Shahhossein, V., Afshar, M. R., & Amiri, O. (2018). The root causes of construction project
Shenhar, A. J., & Dvir, D. (2007). Reinventing project management: the diamond approach to
Söderlund, J. (2004). Building theories of project management: past research, questions for the
63