Professional Documents
Culture Documents
The key role of the project sponsor is to protect the project team from
unnecessary changes and loss of resources.
Net Present Value (NPV): Present value of the total benefits (income or revenue) less the
costs over time period.
Q: You have two projects to choose from. Project X will take 2 years to complete and has
an NPV of $35,000. Project Y will take 5 years to complete and has an NPV of $95,000.
Which one will you take up?
A: The answer is project Y, because it has a higher NPV. Don’t get confused with the
longer duration of the project. What is important is that the NPV should be greater.
Internal Rate of Return (IRR): IRR is the rate of discounting (used to reduce
future cash flows to their present value) at which the present value of costs
match the present value of benefits. In other words, it is the rate of return
internal to the project.
Example: If you have to choose between project A with an IRR of 25% or project
B with an IRR of 15%, the answer is project A. The IRR for project A is greater
than the one for project B.
Example: You have two projects to choose from. Project A with a payback period
of 5 months or project B with a payback period of 12 months. Which one would
you go for?
The answer is project A.
Benefit Cost Ratio: The benefit cost ratio (BCR) compares the present value of
benefits to the present value of costs. A benefit cost ratio of more than 1 means that
the benefits are greater than the costs.
Example: If the benefit cost ratio of project A is 2.5 and benefit cost ratio of
project B is 1.5, which project would you select?
The answer is project A – as the benefit cost ratio is higher for project A.
Return on Investment (RoI): RoI is the rate of return on the project normalized by
the initial investment.
Example: if a project involves an initial investment of $100,000 and on average it results
in benefits of $20,000 per year, the RoI is 20,000/100,000 or 20%.
Opportunity Cost: Opportunity cost is the cost related to the next best choice
available to someone who has picked among several mutually exclusive choices. It is
therefore the opportunity given up by selecting one project over another.
Example: You have two projects to choose from. Project A with an NPV of $55,000 and
project B with an NPV of $85,000. What is the opportunity cost of selecting project B?
The answer is $55,000. This is the NPV of project A, which we selected over project B.
Outputs
Project charter
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth
edition, Project Management Institute, Inc., 2013, Page 66
Outputs
Project management plan
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth
edition, Project Management Institute, Inc., 2013, Page 72
Corrective Action
• *“An intentional activity that realigns the performance of the project work with the project
management plan.”
Preventive Action
• *“An intentional activity that ensures the future performance of the project work is aligned with
the project management plan.”
*Definitions taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body
of Knowledge, (PMBOK® Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
Direct and manage project work is the process of leading and performing the
work defined in the project management plan to achieve the project
objectives. It belongs to the executing process group.
Outputs
Deliverables
Work performance data
Change requests
Project management plan updates
Project documents updates
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth
edition, Project Management Institute, Inc., 2013, Page 79
Project Integration Management 13 © Simplilearn Solutions
Monitor and Control Project Work
Monitor and control project work is the process of tracking, reviewing, and
regulating the progress to meet the performance objective(s) defined in the
project management plan. It belongs to the monitoring and controlling
process group
Determine that
Evaluate the
a change is Come up with
impact of
“necessary” or alternatives
change
has occurred
Discuss Discuss
externally internally
Close project or phase is the process of finalizing all activities across all the
project management process groups to formally complete the project or
phase. It belongs to the closing process groups
Outputs
Final product, service, or result
transition
Organizational process assets updates
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth
edition, Project Management Institute, Inc., 2013, Page 100
2. In the middle of a project, you are informed that resources promised at the
beginning of the project are no longer available. As a project manager what
would you do?
A. Raise a concern that you can no longer execute this project
B. Evaluate the impact of not having the promised resources
C. Move forward without the promised resources
D. Identify other resources that can be provided to you in lieu of the
earlier promised resources
2. In the middle of a project, you are informed that resources promised at the
beginning of the project are no longer available. As a project manager what
would you do?
A. Raise a concern that you can no longer execute this project
B. Evaluate the impact of not having the promised resources
C. Move forward without the promised resources
D. Identify other resources that can be provided to you in lieu of the
earlier promised resources
Answer 2: Now this is a tricky question. You might consider doing all of the
mentioned options, but the first thing to do in such cases is to evaluate the
impact. The correct answer is B.
Answer 3: This one is another tricky question. In real life you might consider
doing all the options listed, but the best way to handle such a scenario is to
involve the customer as early in the project as possible. The right answer
therefore is B.
5. As a project manager you received a change request that does not impact
the project schedule. What would you do?
A. Go ahead and do the change
B. Evaluate the impact on the other project constraints
C. Get in touch with the change control board
D. Ask your boss’s permission
5. As a project manager you received a change request that does not impact
the project schedule. What would you do?
A. Go ahead and do the change
B. Evaluate the impact on the other project constraints
C. Get in touch with the change control board
D. Ask your boss’s permission
6. You have been assigned as the project manager of a project that is half way
through execution. You meet the customer and inform him that project is
within the baselines, but the customer informs you that he is not happy
with the performance of the project. What should you do first?
A. Meet with the project team to understand the customer’s concerns
B. Meet with the project sponsor and discuss the customer’s concerns
C. Inform the customer that there is nothing wrong from the project
team’s side
D. Show the customer the performance of similar other projects
6. You have been assigned as the project manager of a project that is half way
through execution. You meet the customer and inform him that project is
within the baselines, but the customer informs you that he is not happy
with the performance of the project. What should you do first?
A. Meet with the project team to understand the customer’s concerns
B. Meet with the project sponsor and discuss the customer’s concerns
C. Inform the customer that there is nothing wrong from the project
team’s side
D. Show the customer the performance of similar other projects
Answer 6: The answer depends upon the scenario. If you heard that a customer
was unhappy from someone else, the best thing would be to meet the
customer. In this case, customer is directly informing you that he is not happy.
So the best option is to meet the project team and discuss the customer’s
concerns, before doing any thing else. The right answer therefore is A.