FORMULA
Assume:
A = Architect’s rate / hour
C = Consultant’s rate / hour
T = Rate per hour of Technical Staff,
Researchers and others involved in the
Project
AN, CN, TN = No. of hours spent by
Architect, Consultants and Technical Staff
M = Multiplier to account for overhead and
reasonable profit. The value may range from
1.5 to 2.5 depending on the set-up of the
Architect’s office and the complexity of the
Project.
R = Reimbursable expenses such as
transportation, housing and living allowance
of Consultant, transportation, per diem,
housing and living allowance of local
consultants and technical staff if assigned
to places over 100 km. from the area of
operation of the Architect.
Cost of printing of extra set of drawings,
reports, maps, contract documents, etc.
over the five (5) copies submitted to the
Client, overseas and long distance calls,
technical and laboratory tests, licenses,
fees, taxes and similar cost items needed by
the Project.
Direct cost = AN + CN + TN
Fee = Direct Cost x M
Total Cost of Service charged to Client =
Fee + R
4.2 Professional Fee Plus Expenses
This method of compensation is frequently
used where there is continuing relationship
involving a series of Projects. It
establishes a fixed sum over and above the
reimbursement for the Architect’s technical
time and overhead. An agreement on the
general scope of the work is necessary in
order to set an equitable fee.
4.3 Lump Sum or Fixed Fee
This method may be applied to government
projects since they entail more paper work
and time-consuming efforts.
4.4 Per Diem, Honorarium Plus Reimbursable
Expenses
In some cases a Client may request an
Architect to do work which will require his
personal time such as:
4.4.1 attending project-related meetings,
conferences or trips;
4.4.2 conducting ocular inspection of
possible project sites; and
4.4.3 conferring with others regarding
prospective investments or ventures and the
like.
For these particular activities, the
Architect as agent of the Owner may be paid
on a per diem and honorarium basis plus out-
of-pocket expenses such as but not limited
to travel, accommodations and subsistence.
4.5 Mixed Methods of Compensation
The SPP provides for more than one method of
compensation on a project.
Each project should be examined to determine
the most appropriate and equitable method of
compensation.
SPP 202 METHOD OF COMPENSATION METHOD OF COMPENSATION
The Architect’s compensation is based on The Architect's compensation is based on the
the Architect’s / architectural firm’s Architect's / architectural firm's talents,
talents, skill, experience, imagination, and skill, experience, and on the type and level of
on the type and level of professional professional services provided. Compensation
services provided. Compensation for Regular for Regular Design Services may be based on one
Design Services may be based on one or more or more of the following:
of the following:
5.1 Percentage (%) of Project Construction 6.2.1 Percentage (%) of Project Construction
Cost (PCC) Cost (PCC)
The Architect’s Fee based on the PPC shall 6.2.2 Unit Cost Method based on Project
be detailed in the Architect’s Guidelines. Construction Cost
6.2.3 Professional Fee plus Expenses
5.2 Multiple of Direct Personnel Expenses 6.2.4 Lump Sum or Fixed Fee
This cost-based method of compensation is 6.2.5 Per Diem. Honorarium Plus Reimbursable
applicable only to non-creative work such as Expenses
accounting, secretarial, research, data 6.2.6 Multiple of Direct Personnel Expenses
gathering, preparation of reports and the 6.2.7 Mixed Methods of Compensation
like. This method of compensation is based
on technical hours spent and does not 6.3 Recommended Professional Fee (RPF)
account for creative work since the value of Professional architectural work is classified
creative design cannot be measured by the in accordance with the degree of complexity and
length of time the designer has spent on his the creative skill required to meet the
work. The computation is made by adding all requirements of the Client within technical,
costs of technical services (man hour/s x functional, economic and aesthetic constraints.
rate) and then multiplying it by a A grouping of buildings is provided to
multiplier to cover overhead and profit. determine the fair remuneration for the
Architect.
The multiplier ranges from 1.5 to 2.5
depending on the office set-up, overhead and 6.3.1 Group I
experience of the Architect and the Buildings of the simplest utilization and
complexity of the Project. character, which are without complication of
plan/design or detail and which require only a
Other items such as cost of transportation, minimum of architectural finishes, engineering
living and housing allowances of foreign and allied architectural elements:
consultants, out-of-town and housing
allowances of the local consultants and the Armories, Packaging and Processing Plants,
like, are all to be charged to the Client. Bakeries, Parking Structures, Habitable
At the start of the commission, the Agricultural Buildings, Printing Plants, Public
Architect shall make known to the Client the Markets, Service Garages, Hangars, industrial
rate of professionals and personnel who will Buildings, Manufacturing /industrial Plants,
be assigned to the Project and the Simple Loft Type Buildings, Warehouses, Other
multiplier that has to be applied before similar utilization type buildings
agreeing on this method of compensation.
Project Construction Recommended
FORMULA Cost(PCC) Professional Fee (RPF)
Assume: for Detailed
A = Architect’s rate / hour Architectural and
C = Consultant’s rate / hour Engineering Design
T = Rate per hour of Technical Staff, Services (DAEDS)
Researchers and others involved in the P50.0 million and 5%
Project less
AN, CN, TN = No. of hours spent by Over P50.0 million to P2,500,000 plus 4% of
Architect, Consultants and Technical Staff P100.0 million excess of P50.0
M = Multiplier to account for overhead and million
reasonable profit. The value may range from Over P100.0 million to P4,500,000 plus 3% of
1.5 to 2.5 depending on the set-up of the P200.0 million excess of P100.0
Architect’s office and the complexity of the million
Project. Over P200.0 million to P7,500,000 plus 2% of
R = Reimbursable expenses such as P500.0 million excess of P200.0
transportation, housing and living allowance million
of Consultant, transportation, per diem, Over 500.0 million to P13,500,000 plus 1%
housing and living allowance of local P1.0 billion of excess of P500
consultants and technical staff if assigned million
to places over 100km. from area of operation Over P'1.0 billion P18,500,000 plus
of the Architect. 1l2o/o of excess of
P1 .0 billion
Cost of printing of extra set of drawings,
reports, maps, contract documents, etc.
over the seven (7) copies submitted to the
Client, overseas and long distance calls,
technical and laboratory tests, licenses,
fees, taxes and similar cost items needed by
Project the Project.Recommended
Construction
Cost(PCC) Professional Fee (RPF) 6.3.2 Group 2
Direct cost = forAN + CN + TN Detailed Buildings of moderate complexity of plan/design
Fee = DirectArchitectural
Cost x M Design requiring a moderate amount of research and of
Total Cost of Service
Services(DADS) charged to Client = engineering and allied architectural design.
P50.0 Fee
million + R and 3.0% Art Gallery, Office Buildings/Office
less Condominium, Banks, Exchange and Other
5.3 Professional
Over P50.0 million to Fee Plus
P1,500,000 plusExpenses
2.4o/o Buildings, Park, Playground and Open-Air
This
P100.0 million method of compensation
of excess of P50.0 is frequently Recreational Facilities, Financial
used where there
million is continuing relationship institutions, Residential Condominiums,
involving a series
Over P100.0 million to P2,700,000 plus 1.8%of Projects. It Bowlodromes, Police Stations, Call Centers,
establishes
P200.0 million a fixed sum over
of excess of P100.0 and above the Postal Facilities, Churches and Religious
reimbursement for the Architect’s technical
million Facilities, Private Clubs, City/Town Halls &
time and overhead. An agreement on the Civic Centers, Publishing Plants, College
Over P200.0 million to P4,500,000 plus 1 .
general scope of the work is necessary in Buildings, Convents, Monasteries & Seminaries,
P500.0 million 2o/o of excess of
order to set an equitable fee. Correctional & Detention Facilities, Court
P200.0 million
Houses/Halls of Justice, Dormitories,
Over 500.0 million to P8,100,000 plus 0.6%
5.4 Lump Sum or Fixed Fee Exhibition Halls & Display Structures, Fire
P1.0 billion of excess of P500.0
This method may be applied to government Stations, Laundries & Cleaning Facilities,
million
projects since they entail more paper work Libraries, Malls/Mall Complexes, Motels &
Over P1.0 billion P11,100,000 plus 0.6%
and time-consuming efforts. Apartels, Multi-storey Apartments, Nursing
of excess of P1.0
Homes, Race Tracks, Restaurants/Fast food
billion
5.5 Per Diem, Honorarium Plus Reimbursable Stores, Retail/Wholesale Stores, Schools,
Expenses Serviced Apartments, Shopping Centers,
In some cases a Client may request an Showrooms/Service Centers, Specialty Shops,
Architect to do work which will require his Supermarkets/Hyper-marts, Welfare Buildings,
personal time such as: Mixed Use Buildings, Other buildings of
5.5.1 Attending project-related meetings, similar nature or use
conferences or trips;
5.5.2 Conducting ocular inspection of Project Construction Recommended
possible project sites; and Cost (PCC) Professional Fee(RPF)
5.5.3 Conferring with others regarding for Detailed
prospective investments or ventures and the Architectural and
like. Engineering Design
For these particular activities, the Services (DAEDS)
Architect as agent of the Owner may be paid P50.0 million and 60/.
on a per diem and honorarium basis plus out- less
of-pocket expenses such as but not limited Over P50.0 million to P3,000,000 plus 5%
to travel, accommodations and subsistence. P100.0 million of excess of P 50.0
million
5.6 Mixed Methods of Compensation Over P100.0 million to P5,500,000 plus 4% of
The SPP provides for more than one method of P200.0 million excess of P100.0
compensation on a project. Each project million
should be examined to determine the most Over P200.0 million to P9,500,000 plus 3% of
appropriate method of compensation. P500.0 million excess of P200.0
million
7.4 Per Diem and Traveling Expenses Over 500.0 million to P18,500,000 plus 2%
A per diem plus traveling and living P1.0 billion of excess of P500
expenses shall be chargeable to the Owner million
whenever the Architect or his duly Over P1.0 billion P28,500,000 plus 1olo
authorized representative is required to of excess of P1.0
perform services at a locality beyond 50.0 billion
kilometers (air, straight line or radial
distance) from his established office as it Project Construction Recommended
appears in the Architect’s letterhead. Cost(PCC) Professional Fee (RPF)
for Detailed
7.6 Change/s Ordered by the Owner Architectural Design
If the Architect renders additional Services(DADs)
professional services due to changes ordered P50.0 million and 3.6%
by the Owner after approval of the less
Architect’s outputs, the Owner shall pay the Over P50.0 million to P1,800,000 plus 3.0%
Architect for extra time, resources/ P100.0 million of excess of P50.0
drafting, or other office expenses. million
Over P100.0 million to P3,300,000 plus 2.4%
7.7 Work Suspended or Abandoned
P200.0 million of excess of P100.0
If the work of the Architect is abandoned or
million
suspended in whole or in part, the Owner
Over P200.0 million to P 5, 700,000 plus 1.8%
shall pay the Architect for the services
P500.0 million of excess of P200.0
rendered corresponding to the amount due at
million
the stage of suspension or abandonment of
the work. Over 500.0 million to P11,100,000 plus 1 .
The primary service of the Architect is the P1.0 billion 2% of excess of
preparation of architectural plans/designs, P500.0 million
specifications and other building Over P1.0 billion P17,100,000 plus 0.6%
construction documents. of excess of P'l.0
These are sets of detailed instructions that billion
shall serve as the basis for the General
Contractor to implement the project. Once 6.3.3 Group 3
the Architect has prepared all these Buildings of exceptional character and
documents, the Architect has completed the complexity of plan/design or requiring
Detailed Design and Contract Documents Phase comparatively large amounts of research and of
of his services, which is equivalent to engineering and allied architectural design:
Ninety percent (90%) of his work. When the Airport/ wet & dry ports & Terminal, Mental
Owner therefore fails to implement the plans institutions, Aquariums, Mortuaries,
and documents for construction as prepared Auditoriums, Nuclear Facilities, Breweries
by the Architect, the Architect is entitled Observatories, Cold Storage Facilities, Public
to receive as compensation the sum Health Centers, Convention Facilities, Research
corresponding to ninety percent (90%) of the Facilities, Gymnasiums, Stadia, Hospitals &
Architect’s fee. Medical Buildings, Telecommunication Buildings,
Hotels, Theaters & Similar Facilities,
7.8 Different Periods of Construction Laboratories/Testing Facilities, Transportation
If portions of the building/s are erected at Facilities & Systems, Marinas and Resort
different periods of time, thus increasing Complexes, Veterinary Hospitals, Medical Arts
the construction period and Architect’s Offices & Clinics, Other buildings of similar
burden of services, charges pertaining to nature or use
services rendered during the Construction
Phase shall be adjusted proportionately. Project Construction Recommended
When the suspension of construction exceeds Cost(PCC) Professional Fee (RPF)
a period of six (6) months, the fee for the for Detailed
remaining works shall be doubled. Architectural and
Engineering Design
7.9 Services of Specialist Consultants Services (DAEDS)
If the Owner requires the services of P50.0 million and 7o/o
specialist consultants, they shall be less
engaged with the consent of the Architect. Over P50.0 million to P3,500,000 plus 6%
The cost of their services shall be paid for
separately by the Owner and shall not P100.0 million of excess of P50.0
be deducted from the Architect’s fee. million
Over P100.0 million to P 6,000,000 plus 5%
P200.0 million of excess of P100.0
million
Over P200.0 million P 11,500,000 plus 4%
to P500.0 million of excess of P200.0
million
Over 500.0 million to P23,500,000 plus 3%
P1.0 billion of excess of P500
million
Over P1.0 billion P38,500,000 plus 2% of
excess of P1.0
billion
6.3.4 Group 4
Residences (single-detached, single-attached or
duplex, row-houses or shop houses), small
apartment houses and townhouses.
Recommended
Professional Fee (RPF)
Detailed Architectural 10% of PCC
and Engineering Design
Services (DAEOS)
Detailed Architectural 6% of PCC
Design Services (DADS)
6.3.5 Group 5
Monumental buildings and other facilities
requiring consummate design skill and much
precise detailing.
Recommended
Professional Fee (RPF)
Detailed Architectural 12% of PCC
and Engineering
Design Services(DAEDS)
Detailed Architectural 7.5o% of PCC
Design Services (DADS)
6.3.6 Group 6
When the plan/design and related Contract
Documents are re-used for the repetitive
construction of similar buildings without
amending the drawing and the specifications,
the Architect's fee is computed as follows:
Recommended
Professional Fee(RPF)
First (1st) Building 100% of RPF for type
of building
Second (2nd) 50% of RPF for type
Building of building
Third (3rd) Building 40% of RPF for type
of building
Fourth (4th) and 30% of RPF for type
succeeding Buildings of building
6.3.7 Group 7
When the Architect is engaged to undertake a
Housing Project involving the construction of
several residential units on a single site with
the use of one (1) set of plans/design,
specifications and related documents, the
Architect's Fee chargeable shall conform with
the following:
No. of Units Detailed Detailed
Architectural & Architectural
Engineering Design
Design Services(DADS)
Services(DAEDS)
First (1st) 10% of PCC 6% of PCC
Unit
From two To Fee for one Fee for one
ten units unit plus unit plus
(2-10) 50% of RPF for 30% of RPF for
each each
additional additional
unit unit
Eleven units Fee for 10 Fee for 10
To thirty units plus units plus
units (11- 40% of RPF for 24% of RPF for
30) each each
additional additional
unit unit
Thirty-one Fee for 30 unit Fee for 30
units To plus units plus
fifty units 25% of RPF for 15% of RPF for
(31-50) each additional each
unit additional
unit
Fifty-one Fee for 50 Fee for 50
units and units plus 15% units plus
above (51+) of RPF for each 9% of RPF for
additional unit each
additional
unit
6.3.8 Group 8
Projects involving extensive detail such as
designs for built-in components or elements,
built in equipment, special fittings,
screens, counters, architectural interiors, and
development planning and/or design.
Recommended Professional
Fee(RPF) 15% of the PCC
6.3.9 Group 9
For alterations, renovations, rehabilitations,
retrofit and expansion/additions to existing
buildings belonging to Groups 1 to 5 enumerated
above, the compensation of services should
be increased to fifty percent (50%) or a
total of one hundred fifty percent (150%)
of the RPF.
6.3.10 Group 10
Where the Architect is engaged to render
opinion or give advice, clarifications or
explanation on technical matters pertaining to
his profession, (also refer to Pre-Design
Services SPP Doc. 201 under Consultation)
the chargeable RPF shall not be less than
One Thousand Pesos (Pl,000.00) per hour
subject to increase depending on the extent
and coverage of service required and the
location where the Architect shall render his
services. When rendering services as an
expert witness, the Architect's fee shall
not be less than Five Thousand Pesos
(P5,000.00) per appearance regardless as to
whether the scheduled hearing took place
or not.
Adjustment of the price shall be made at
the time of the signing of the Architect's
contract of service. The amount excludes
the cost of transportation and
accommodations when and where required.
Another sixty percent (60%) of the amount
shall be charged for the travel period in
case of locations that are in excess of
one hundred kilometers (100.0 km, air
straight line or radial distance) of
the Architect's office (as stated in his
letterhead).
(Note; All references to fixed amount shall
refer to the value of the Philippine Peso
as of October,2014).
Note:
1 . Based on the original SPPCC included
as Annex to the Service Agreement.
2. Based on the SPPCC submitted at that
particular stage.
3. Based on the winning Bid price.
4. Based on the FPPCC.
4.2 Should the Owner/Client hire separately 7.2.3 Should the Owner/Client hire
the services of other Specialist separately the services of other Specialist
Consultants(SCs), their fee shall be for the Consultants (SCs), their fee shall be on
account of the Owner/ Client and shall be the account of the Owner/ Client and shall
paid directly to the SC. be paid directly to the SC. ln such case,
4.3 For this Specialized Service, the the fee of the Architect for coordinating
payment of the Architect’s services shall be and relating the work of the Specialist
as stated in the Architect’s Guidelines. Consultant to the design concept of the
Architect will be 5% of the SC's fee.
METHOD OF COMPENSATION
4.1 The Architect’s Fee for lighting layout 7.2.4 When using Multiple of Direct Personnel
and design services shall depend on the Expense, the compensation can also be
complexity of the works to be undertaken. computed through man-months i.e. 22 man-
days multiplied by 8 man-hours, and
4.2 Should the Owner/Client hire separately multiplied by a factor to cover other
the services of Specialist Consultants, the direct and indirect costs e.g. overhead,
fee shall be for the account of the etc.
Owner/Client and shall be paid directly to 7.3 Recommended Professional Fee
the Consultant. 7.3.1 Architectural interior (Al), Acoustic
Design, Architectural Lighting Layout and
4.3 “Cost of the Work” means the total cost Design and Site Development Planning(SDP)
of all fixtures and accessories, which were 7.3.1.1 Recommended Professional Fee (RPF)
either designed, specified or procured by is 10% to 15% of the cost of work
the Specialist Architect and/or his depending on the complexity of the work
Specialist Consultants (SCs) for the required by the project.
Owner/Client, and that were used or 7.3.1.2 The Manner of Payment for the above
installed in the project. services shall be as follows:
Upon submission of 30% of the fee
4.4 For this Special Service, the payment of the preliminary
the Architect’s services shall be as stated design
in the Architect’s Guidelines Upon submission of 50% of the fee
the final design
MANNER OF COMPENSATION Upon completion of 50% of the fee
4.1 The Architect’s Fee for site development the project
planning (SDP) services shall depend on the 7.3.1.3 The Architect may bill and be paid
estimated cost of the civil works and for the progress payments during
landscaping works i.e. hardscape and soft construction proportional to the percentage
cape, depending on the magnitude and of progress of completion of the construction
complexity of the work required by the work. Should the work be not completed,
project. If the Architect is also certified the Architect’s hall be paid by the Client
and licensed as a separate RLP e.g. a the amount proportional to the work
Landscape Architect, and is suitably completed at the stage when the project was
experienced, the Architect’s fee shall abandoned.
increase correspondingly, depending on the
magnitude and complexity of the work 7.3.2 Physical Planning for building sites
required by the project. such as industrial Estates, Commercial,
Religious, institutional and Government Civic
4.2 Should the Owner/ Client separately Centers, Sports Complexes, Tourist Centers/
engage the services of a Landscape Tourism Estates/Resorts, Amusement Parks,
Architect, the fee of the said Specialist Educational Facilities, Residential and
Consultant shall be for the account of the Housing Subdivisions and the like.
Owner/Client and paid directly to the SC. 7.3.2.1 The Recommended Professional Fee
(RPF) is P50,000.00 per hectare for the
4.3 For this Specialized Service, the first five (5 has.) hectares net to the
payment of the Architect’s services shall be architect.
as stated in the Architect’s Guidelines. Area Recommended Amount
Professional
2. MANNER OF COMPENSATION Fee (RPF)
The fee structure for Site and Physical Basic rate P5.00 per sq. P250,000.00
Planning Services by the Architect shall be
as stated in the Architect’s Guidelines. for the meter
first
3. MANNER OF COMPENSATION 5 hectares
Compensation for the foregoing specialized or less (1
architectural service shall be through man- hectare:10,000
months i.e. 22 man-days multiplied by 8 man- sq.meters)
hours, and multiplied by a factor to cover Over 5 P4.00 P250,000.00
other direct and indirect costs e.g. hectares up per sq. meter + P40,000.00
overhead, etc. or as prescribed by the to per hectare
Architect’s Guidelines. 10 hectares in excess of
5
General Notes: hectares
METHOD OF COMPENSATION FOR SPECIALIZED Over 10 P3.00 P450,000.00
ARCHITECTURAL SERVICES hectares up per sq. +
Compensation for the foregoing specialized to meter P30,000.00
architectural services, all of which may be 50 hectares per hectare
classified as additional or extra services, in excess of
shall be through man-months i.e. 22 man- 10
days multiplied by 8 man-hours, and hectares
multiplied by a factor to cover other direct Over 50 P1.50 P1,650,000.00
and indirect costs e.g. overhead, etc. or hectares and per sq. meter + P15,000.00
any other applicable mode of determination above per
of the Architect’s fee as stated in Doc. Hectare in
201, Doc. 202 and the Architect’s excess of 50
Guidelines. hectares
FORMULA
Assume:
A = Architect’s rate / hour
C = Consultant’s rate / hour
T = Rate per hour of Technical Staff,
Inspectors and others involved in the
Project
AN, CN, TN = No. of hours spent by
Architect, Consultants and Technical Staff
M = Multiplier to account for overhead and
reasonable profit. The value may range from
1.5 to 2.5 depending on the set-up of the
Architect’s office and the complexity of the
Project.
R = Reimbursable expenses such as
transportation, housing and living allowance
of Consultant, transportation, per diem,
housing and living allowance of local
consultants and technical staff if assigned
to places over 100km. from area of
operation of the Architect.
Direct cost = AN + CN + TN
Fee = Direct Cost x M
Total Cost of Service charged to Client =
Fee + R