Professional Documents
Culture Documents
Janipaan Cip PDF
Janipaan Cip PDF
JANIPAAN CIP
A. TYPE OF VEHICLE
TYPE OF VEHICLE TO BE USED RENTAL RATE FUEL CONSUMPTION
1-unit of pick-up 21.00 P/km 11.36 P/km
LABORER - 503.09 per day 62.89 per hr. 350.00 per day 43.75 per hr.
CARPENTER - 636.68 per day 79.59 per hr. 450.00 per day 56.25 per hr.
MASON - 636.68 per day 79.59 per hr. 450.00 per day 56.25 per hr.
STEELMAN - 636.68 per day 79.59 per hr. 450.00 per day 56.25 per hr.
LIGHT EQUIPMENT - 674.86 per day 84.36 per hr. 480.00 per day 60.00 per hr.
OPERATOR
DRIVER/MECHANIC - 715.36 per day 89.42 per hr. 500.00 per day 62.50 per hr.
HEAVY EQUIPMENT - 817.04 per day 102.13 per hr. 580.00 per day 72.50 per hr.
OPERATOR
FOREMAN B - 874.23 per day 109.28 per hr. 600.00 per day 75.00 per hr.
Note : The travel time on with or without were only considered and the loading and unloading time were
excluded on the consumption.
SUMMARY
Note : The travel time on with or without were only considered and the loading and unloading time were
excluded on the consumption.
SUMMARY
Note : The travel time on with or without were only considered and the loading and unloading time were
excluded on the consumption.
SUMMARY
Note : The travel time on with or without were only considered and the loading and unloading time were
excluded on the consumption.
SUMMARY
Note : The travel time on with or without were only considered and the loading and unloading time were
on the consumption.
SUMMARY
Note : The travel time on with or without were only considered and the loading and unloading time were
excluded on the consumption.
SUMMARY
JANIPAAN CIP
CABATUAN, ILOILO
BY CONTRACT:
A. SAND BAGGING
1. Material Cost Estimate
Cost of Sacks = 15.00 /pc
No.of Pcs. = 1,000.00
Cost = 15,000.00
2. Labor Cost
a. Filling of Sack, Hauling and Laying
Crew: 10 laborers
Capacity : 300 /day
No. Of Days = 1,000.00 / 300 sacks/day = 4.00 days
Cost = 350.00 /day 4.00 days x 10 laborers = 14,000.00
JANIPAAN CIP
CABATUAN, ILOILO
JANIPAAN CIP
CABATUAN, ILOILO
MANUAL BACKFILL
Utilize 1.00 - Laborer 350.00 / day
Capability = 3.00 cu.m. / day
LABOR COST
MANUAL COMPACTION
Utilize 1.00 - Laborer
Capability = 5.00 cu.m. / day
LABOR COST
JANIPAAN CIP
CABATUAN, ILOILO
JANIPAAN CIP
CABATUAN, ILOILO
b. Backfill
Equipment Used: : 0.5 cu.m.-Backhoe (Hitachi EX 150)
Capability : 15.00 cu.m. / hr.
c, Equipment (Compaction)
Equipment Used: : 4.39 MT-Single Smooth Drum Vibratory CATERPILLAR CS323C 83 HP
Capability : 35.00 cu.m. / hr.
JANIPAAN CIP
CABATUAN, ILOILO
b. Backfill
Equipment Used: : 0.5 cu.m.-Backhoe (Hitachi EX 150)
Capability : 15.00 cu.m. / hr.
c, Equipment (Compaction)
Equipment Used: : 4.39 MT-Single Smooth Drum Vibratory CATERPILLAR CS323C 83 HP
Capability : 35.00 cu.m. / hr.
JANIPAAN CIP
CABATUAN, ILOILO
1. MATERIAL COST
Hauling Cost
MATERIALS Per Cu.m. Base Cost
Labor Rental Fuel
Cement 9.00 2,520.00 265.13 171.69 -
R.S.B. 60.00 2,700.00 68.56 11.91 -
Gravel 0.90 1,170.00 799.20 276.30 -
Sand 0.45 540.00 399.60 138.15 -
Form Lumber 25.00 1,000.00 30.55 23.73 -
Plywood 1.25 875.00 35.69 18.99 -
C.W. Nails 2.00 180.00 2.29 1.22 -
Tie Wire 0.50 45.00 0.57 0.31 -
Boulder
G.I. Sheet
C.H.B.
TOTAL COST 9,030.00 1,601.58 642.30 -
Utilize : 1 - 1 1/2"ø (38-40mm) x 4-6m flexible shaft type pendulum concrete vibrator w/ gasoline drive unit
Total Time of vibrator/day = 5.25 hr. / day
Rental Rate/week = 2,480.00 / week
Capability = 3.50 cu.m. / day
Equipment Rental = 2,480.00 / week / 7.00 day / week = 354.29 / day
Equipment cost/cu.m. = 101.22 / cu.m.
JANIPAAN CIP
CABATUAN, ILOILO
GRAVEL BEDDING
Item of Work
1. MATERIAL COST
Hauling Cost
MATERIALS Per Cu.m. Base Cost
Labor Rental Fuel
Cement - - -
R.S.B. - - -
Gravel 0.80 1,040.00 710.40 245.60 -
Sand 0.45 540.00 399.60 138.15 -
Form Lumber - - -
Plywood - - -
C.W. Nails - - -
Tie Wire - - -
Boulder - - -
G.I. Sheet
C.H.B.
TOTAL COST 1,580.00 1,110.00 383.75
JANIPAAN CIP
CABATUAN, ILOILO
BOULDER RIPRAP
Item of Work
1. MATERIAL COST
Hauling Cost
MATERIALS Per Cu.m. Base Cost
Labor Rental Fuel
Cement - - -
R.S.B. - - -
Gravel 0.10 130.00 88.80 30.70 -
Sand - - -
Form Lumber - - -
Plywood - - -
C.W. Nails - - -
Tie Wire - - -
Boulder 1.00 3,000.00 888.00 307.00 -
G.I. Sheet
C.H.B.
TOTAL COST 3,130.00 976.80 337.70
JANIPAAN CIP
CABATUAN, ILOILO
1. MATERIAL COST
Hauling Cost
MATERIALS Per l.s Total Cost
Labor Rental Fuel
1.00 2,634.89
1.00 120.00
1.00 1,600.00
Utilize :
1 Steelman @ P 450.00 / day
4 Laborer @ P 350.00 / day
Capability = 2.00 unit / day
EQUIPMENT UTILIZATION
Utilize: 250 amperes diesel driven welding machine
rental = 330.00 /hr.
Expected duration to complete the activities
1 days or
8.00 hrs.
Equipment Utilization Cost = 2,640.00 / day
Capability = 2.00 unit / day
Equipment cost/pc. = 1,320.00 / unit
MATERIALS
ITEM DESCRIPTION QTY UNIT UNIT PRICE TOTAL AMOUNT
PVC PIPE 8" x 20' 1 pcs. 18,000.00 18,000.00
TOTAL 18,000.00
MATERIALS
ITEM DESCRIPTION QTY UNIT UNIT PRICE TOTAL AMOUNT
Standard Check Valve
for 20cm∅ Pipe) 1 pcs. 40,000.00 40,000.00
TOTAL 40,000.00
JANIPAAN CIP
CABATUAN, ILOILO
JANIPAAN CIP
CABATUAN, ILOILO
1. MATERIAL COST
Hauling Cost
MATERIALS Per Cu.m. Base Cost
Labor Rental Fuel
Cement 7.00 1,960.00 206.21 133.54 -
R.S.B. 40.00 1,800.00 45.71 7.94 -
Gravel 1.00 1,300.00 888.00 307.00 -
Sand 0.50 600.00 444.00 153.50 -
Form Lumber 25.00 1,000.00 30.55 23.73 -
Plywood 1.25 875.00 35.69 18.99 -
C.W. Nails 2.00 180.00 2.29 1.22 -
Tie Wire 0.50 45.00 0.57 0.31 -
Boulder
G.I. Sheet
C.H.B.
TOTAL COST 7,760.00 1,653.01 646.22 -
Utilize : 1 - 1 1/2"ø (38-40mm) x 4-6m flexible shaft type pendulum concrete vibrator w/ gasoline drive unit
Total Time of vibrator/day = 5.83 hr. / day
Rental Rate/week = 2,480.00 / week
Capability = 5.00 cu.m. / day
Equipment Rental = 2,480.00 / week / 7.00 day / week = 354.29 / day
Equipment cost/cu.m. = 70.86 / cu.m.
AREA FILL AREA FILL AREA AREA VOLUME VOLUME VOLUME VOLUME VOLUME
LENGTH AREA CUT REMARKS
STATION L/S R/S STRIPPING CLAY FILL L/S FILL R/S STRIPPING CUT CLAY
33.00
GRAVEL BLANKET
Length Width h1 volume set total volume
3.30 3.00 0.20 1.98 1.00 1.98
0.02
2.00
BOULDER RIPRAP
Length Width h1 volume set total volume
3.30 3.00 0.40 3.96 1.00 3.96
0.04
4.00
EXCAVATION
Length Width h1 volume set total volume
cut-off wall upstream 3.30 0.75 1.00 2.48 1.00 2.48
bottom pool 4.30 2.50 1.15 12.36 1.00 12.36
cut-off wall downstream 3.30 0.75 1.00 2.48 1.00 2.48
boulder riprap & gravel bedding 3.30 3.00 0.60 5.94 1.00 5.94
BARREL 3.00 4.30 1.20 15.48 2.00 30.96
5.42
- 60.00
BACKFILL
Length Width h1 volume set total volume
cut-off wall upstream 3.30 0.60 1.00 1.98 1.00 1.98
bottom pool 1.00 2.50 1.15 2.88 1.00 2.88
cut-off wall downstream 3.30 0.60 1.00 1.98 1.00 1.98
BARREL 3.00 1.00 1.20 3.60 1.00 3.60
2.00
13.00
PVC PIPE
Length Width h1 volume set total volume
18.00 - -
-
VOLUMETRIC COMPUTATION (Excavation and Backfill)
Name of Project : JANIPAAN CIP
Location : CABATUAN, ILOILO
STATION AREA CUT AREA FILL VOLUME CUT VOLUME FILL REMARKS
Main Canal 1
1+102.00 0.60 0.30
1+120.00 18.00 0.60 0.30 10.80 5.40
1+140.00 20.00 0.60 0.30 12.00 6.00
1+160.00 20.00 0.59 0.30 11.90 6.00
1+180.00 20.00 0.55 0.30 11.40 6.00
1+200.00 20.00 0.58 0.30 11.30 6.00
1+220.00 20.00 0.58 0.30 11.60 6.00
1+240.00 20.00 0.59 0.30 11.70 6.00
1+260.00 20.00 0.58 0.30 11.70 6.00
1+280.00 20.00 0.58 0.30 11.60 6.00
1+300.00 20.00 0.58 0.30 11.60 6.00
1+320.00 20.00 0.58 0.30 11.60 6.00
1+340.00 20.00 0.58 0.30 11.60 6.00
1+360.00 20.00 0.58 0.30 11.60 6.00
1+380.00 20.00 0.58 0.30 11.60 6.00
1+391.00 11.00 0.59 0.30 6.41 3.30
0.10
0.13