Information Management System Daily Report

Team: Hindi HOD: Ms. Sujata Wankhede


Full Time Members: 7 Part Time Members: None

Feedback for the period: 20th April to 24th April


Member/s on Leave: - Date of Leave: -

Check For Details/Remarks


Filling of Workload sheet by the HOD Yes
Distribution of work amongst team members Yes Workload for the month of May
filled.
Task assigned in workload sheet matches task Yes None
logged in individual tracker sheets

Regularity and Detailing of the IMS filled by the Yes HOD and team both are regular in
HOD filling in the IMS
Regularity and Detailing of the IMS filled by Yes All members fill the IMS every day.
Team Members
HOD’s remarks on the work logged by team Yes Generic remarks and specific remarks
members are seen on the sheet,
Average time spent by team on coordination 1 hour HOD is regular in coordinating with
and liaising amongst themselves (per week) the team. There is no mention of
team meeting during the week in the
team members sheet or HOD’s
sheet.
On an average, how many hours do the team 7- 8 Tara logged on Saturday also 7-8
members work for in a day? hours hours. Sarita logged on Saturday (7-
8) and Sunday (3-4) hours.
Does the time spent on various tasks reflect fair Yes HOD has spent considerable time in
usage of time by team? uploading.
General Remarks: The team is regular in filling the track sheet and HOD is providing remarks.
HOD is coordinating and liaising with individual members, however no mention of team meeting
seen in any of the individual track sheets.