Information Management System Daily Report

Team: Hindi HOD: Ms. Sujata Wankhede


Full Time Members: 7 Part Time Members: None

Feedback for the period: 10th April to 17th April


Member/s on Leave: - Date of Leave: -

Check For Details/Remarks


Filling of Workload sheet by the HOD Yes
Distribution of work amongst team members Yes Preity’s workload seems to be more
compared to the rest of the team.
Task assigned in workload sheet matches task Yes None
logged in individual tracker sheets

Regularity and Detailing of the IMS filled by the Yes HOD and team both are regular in
HOD filling in the IMS
Regularity and Detailing of the IMS filled by Yes All members fill the IMS every day.
Team Members
HOD’s remarks on the work logged by team Yes Generic remarks and specific remarks
members are seen on the sheet,
Average time spent by team on coordination 1-2 Sometimes cumulative time spent by
and liaising amongst themselves (per week) hours HOD is over 3-4 hours. The time is
spent interacting with different team
members on different topics
On an average, how many hours do the team 7- 8 None
members work for in a day? hours
Does the time spent on various tasks reflect fair Yes Wherever the task taken by any team
usage of time by team? is unrealistic. HOD has put the
required remark
General Remarks: