Professional Documents
Culture Documents
Problem
A distribution system and its data are as given below. Calculate the total revenue loss of the
system, considering momentary outages, if the system is:
(i) Unprotected
(ii) Protected with Recloser in F2, Sectionalizing switch in F3, Fuse-blow fuse in F4
and Fuse-save fuse in F5.
F5 L5
Sub
Station
1 2 3
F1 F2 F3
CB
L1 L2 L3
F4 4
L4
1) Sustained fault
When sustained fault occurs on the any feeder at that time CB situated at the Substation
operates and all the feeder trips. The disadvantage of this method is that though fault happens
only in the one feeder all other feeder is being tripped. So, in despite of the fault on any
feeder all the loads are being interrupted. The table of outage rates and repair time for all the
feeder during faults are given below:
Table 1 Permanent outage due to permanent fault (PO-PF)
Feede L1 L2 L3 L4 L5
r
λ r λ r λ r λ r λ r
/load
F1 0.1 4 0.1 4 0.1 4 0.1 4 0.1 4
F2 0.1 4 0.1 4 0.1 4 0.1 4 0.1 4
F3 0.1 4 0.1 4 0.1 4 0.1 4 0.1 4
F4 0.15 5 0.15 5 0.15 5 0.15 5 0.15 5
F5 0.15 5 0.15 5 0.15 5 0.15 5 0.15 5
2) Momentary fault
Most of the fault occurring are momentary in the nature. The rate at which momentary fault
occurs is almost three times than the permanent outage rate. When momentary fault occurs on
the either feeder, ideally no protective device should operate. But here CB do not have
reclosing capability, which leads to the unwanted tripping of the CB during temporary fault.
The repair time or CB reclosing time during momentary fault is taken as 0.5 hour. Though
fault is momentary in nature but due to unavailability of reclosing will lead to the permanent
outage. Further, momentary fault on the any feeder will lead to the tripping of the CB and all
the loads connected to all feeder will be tripped which will cause higher loss of revenue.
Table 2 Permanent outage due to momentary fault (PO-TF)
Feede L1 L2 L3 L4 L5
r
λ r λ r λ r λ r λ r
/load
F1 0.3 0.5 0.3 0.5 0.3 0.5 0.3 0.5 0.3 0.5
F2 0.3 0.5 0.3 0.5 0.3 0.5 0.3 0.5 0.3 0.5
F3 0.3 0.5 0.3 0.5 0.3 0.5 0.3 0.5 0.3 0.5
F4 0.45 0.5 0.45 0.5 0.45 0.5 0.45 0.5 0.45 0.5
F5 0.45 0.5 0.45 0.5 0.45 0.5 0.45 0.5 0.45 0.5
After simulating monte-carlo simulation for 5000 runs the value of TIC, ENS and total
revenue loss of the unprotected system is shown in the table 2. Further, the probability
density functions (p.d.f.s) of the same is shown in fig. 2.
Standard
Standard deviation in
Mean
deviation percentage 3rd central 4th central
(1st central
(2nd central (coefficient moment moment
moment)
moment) of
variation)
TIC (sustained)
9792110 4678804 47.78% 1.0151×1020 2.1807×1027
(in Rs.)
TIC (momentary)
2190785 926703 42.30% 6.3474×1017 2.9912×1024
(in Rs.)
ENS (in Rs.) 23550 8204 34.83% 3.7287×1011 1.7102×1016
Total Revenue
12100649 5088386 42.05% 1.2020×1020 2.9563×1027
Loss (in Rs.)
F5 L5
Sub Fuse-save fuse
Station
1 2 3
F1 F2 F3
CB Recloser Sectionalizer
Fuse-blow fuse
L1 L2 L3
F4 4
L4
Fault on feeder F1
During the sustained fault on F1 leads to the tripping of the CB located at substation
and all the feeder will be tripped.
For momentary fault on F1 will also lead to the tripping of the CB for higher time
(time equal to the 0.5 hour) because CB do not have reclosing capacity.
Fault on feeder F2
Sustained fault on F2 leads to tripping of recloser and feeder F2, F3 and F5 will be
disconnected. F1 and F4 will not be affected.
During momentary faults, recloser will try its reclosing attempts and L2, L3 and L5
will experience momentary outage. The outage time will be equal to 5 min.
Fault on feeder F3
Sustained fault on F3, the recloser will try to do its reclosing attempt and after last
attempt, setionalizer will sense that it is sustained fault on F3 and it will open. During
reclosing attempts load L2 and L5 will experience momentary outages. Here
momentary outage time of L2 and L5 will be equal to 5 min.
During momentary faults, recloser will try its reclosing attempts and L2, L3 and L5
will experience momentary outage. The outage time will be equal to 5 min.
Fault on feeder F4
Sustained fault on F4 will lead to blowing of the fuse and load L4 will be
disconnected
Momentary fault on F4 the fuse will be blown again though there is momentary fault
due to fuse-blow scheme. Here, though momentary fault occurs L4 will have
permanent outage and can be reconnected to supply after fuse replacemen. The fuse
replacement time can be taken 1 hr.
Fault on feeder F5
Though fuse is connected on F5, the sustained fault on F5 will not lead to blowing of
the fuse because of the fuse-save scheme. The recloser will try its reclosing attempts
meanwhile load L2 and L3will go through momentary outage due to reclosing
attempts and found that sustained fault occurred so it will blow the fuse.
Momentary fault on F5 will not lead to blowing of the fuse because of the fuse-save
scheme. The recloser will try its reclosing attempts and due to that L2, L3 and L5 will
go through momentary outages.
So there are total four types of outage table:
(1) PO-PF (Permanent outage due to permanent fault) (Table 4)
(2) TO-PF (Momentary outage due to permanent fault) (Table 5)
(3) PO-TF (Permanent outage due to momentary fault) (Table 6)
(4) TO-TF (Momentary outage due to momentary fault) (Table 7)
Table 4 Permanent outage due to permanent fault (PO-PF)
Feede L1 L2 L3 L4 L5
r
λ r λ r λ r λ r λ r
/load
F1 0.1 4 0.1 4 0.1 4 0.1 4 0.1 4
F2 0 0 0.1 4 0.1 4 0 0 0.1 4
F3 0 0 0 0 0.1 4 0 0 0 0
F4 0 0 0 0 0 0 0.15 5 0 0
F5 0 0 0 0 0 0 0 0 0.15 5
Feede L1 L2 L3 L4 L5
r
λ r λ r λ r λ r λ r
/load
F1 0 0 0 0 0 0 0 0 0 0
F2 0 0 0 0 0 0 0 0 0 0
F3 0 0 0.1 5 min 0 0 0 0 0.1 5 min
F4 0 0 0 0 0 0 0 0 0 0
F5 0 0 0.15 5 min 0.15 5 min 0 0 0 0
Feede L1 L2 L3 L4 L5
r
λ r λ r λ r λ r λ r
/load
F1 0.3 0.5 0.3 0.5 0.3 0.5 0.3 0.5 0.3 0.5
F2 0 0 0 0 0 0 0 0 0 0
F3 0 0 0 0 0 0 0 0 0 0
F4 0 0 0 0 0 0 0.45 1 0 0
F5 0 0 0 0 0 0 0 0 0 0
Feede L1 L2 L3 L4 L5
r
λ r λ r λ r λ r λ r
/load
F1 0 0 0 0 0 0 0 0 0 0
F2 0 0 0.3 5 min 0.3 5 min 0 0 0.3 5 min
F3 0 0 0.3 5 min 0.3 5 min 0 0 0.3 5 min
F4 0 0 0 0 0 0 0 0 0 0
F5 0 0 0.45 5 min 0.45 5 min 0 0 0.45 5 min
TIC_pf(k)=70*((sum(sum(TIC)))+(sum(sum(TIC_po))));
TIC_tf(k)=70*((sum(sum(TIC_mo)))+(sum(sum(TIC_mo1))));
ENS(k)=(sum(U_T.*L)+sum(U_T1.*L));
CENS(k)=ENS(k)*5;
TRL(k)=CENS(k)+TIC_pf(k)+TIC_tf(k);
end
subplot(2,2,1)
[p,x] = hist(TIC_pf); plot(x,p/sum(p))
title('TIC (sustained)')
xlabel('x')
ylabel('p(x)')
grid on
subplot(2,2,2)
[p,x] = hist(TIC_tf); plot(x,p/sum(p))
title('TIC (momentary)')
xlabel('x')
ylabel('p(x)')
grid on
subplot(2,2,3)
[p,x] = hist(ENS); plot(x,p/sum(p))
title('ENS')
xlabel('x')
ylabel('p(x)')
grid on
subplot(2,2,4)
[p,x] = hist(TRL); plot(x,p/sum(p))
title('Total revenue loss')
xlabel('x')
ylabel('p(x)')
grid on
a=findobj(gcf);
allaxes=findall(a,'Type','axes');
alllines=findall(a,'Type','line');
alltext=findall(a,'Type','text');
set(allaxes,'FontName','ARIAL','FontWeight','Bold','LineWidth'
,3,...
'FontSize',16);
set(alllines,'Linewidth',3);
set(alltext,'FontName','ARIAL','FontWeight','Bold','FontSize',
16);
Analysis
After simulating monte-carlo simulation for 5000 runs the value of TIC, ENS and total
revenue loss of the unprotected system is shown in the table 8. Further, the probability
density functions (p.d.f.s) of the same is shown in fig. 4.
Standard
Standard deviation in
Mean
deviation percentage 3rd central 4th central
(1st central
(2nd central (coefficient moment moment
moment)
moment) of
variation)
TIC (sustained)
5273476 2194132 41.68% 1.0573×1019 1.1798×1026
(in Rs.)
TIC (momentary)
22400 7981 35.63% 2.722×1011 1.3890×1016
(in Rs.)
ENS (in Rs.) 7229 2850 39.42% 1.841×1010 2.844×1014
Total Revenue
5332024 2210965 41.46% 1.078×1019 1.2133×1026
Loss (in Rs.)
Figure 4 Probability density functions for protected system