JULY 24, 2019

HP3 - MONTHLY COORDINATION MEETING


WORKS SUMMARY
% WT. OF TARGET DATE
TRADES CONTRACTOR REMARKS
ACCOMPLISHMENT COMPLETION

STRUCTURAL VISION PROPERTIES DEVELOPMENT


100%
CORPORATION

 • ON GOING PAINTING WORKS AT ELEV. A & C


• ELEVATION B = QC ACCEPTED
• ELEVATION D = QC ACCEPTED
ARCHITECTURAL VISION PROPERTIES DEVELOPMENT
• ELEVATION E = QC ACCEPTED
EXTERIOR CORPORATION 90% PROGRESS JULY 30,2019
• ELEVATION A = PARTIALLY ACCEPTED FOR QC VALIDATION ON
JULY 24,2019
• ELEVATION C = FOR QC VALIDATION ON JULY 24,2019

• 1ST FLOOR – 10 OUT 11 QC ACCEPTED


• 2ND FLOOR – 6 UNITS QC INSPECTED; ALL UNITS JULY 30,2019 – FOR QC
ACCEPTANCE
RVN CONSTRUCTION & TRADING INT’L,INC. • 3RD FLOOR – AUGUST 6, 2019 – FOR QC ACCEPTANCE
60% JULY 30,2019
(GROUND – 6TH FLOOR) • 4TH FLOOR – AUGUST 6, 2019 – FOR QC ACCEPTANCE
• 5TH FLOOR – AUGUST 16, 2019 – FOR QC ACCEPTANCE
• 6TH FLOOR – AUGUST 20, 2019 – FOR QC ACCEPTANCE
ARCHITECTURAL • GROUND FLOOR – AUGUST 20,2019 – FOR QC ACCEPTANCE
INTERIOR FIT-OUT (UNITS)

• 7TH FLOOR – (6 OUT 16 QC INSPECTED) – QC ACCEPTANCE: JULY 26,2019


• 8TH FLOOR – JULY 31, 2019 – FOR QC ACCEPTANCE
MEGALUX CONSTRUCTION & DEVT.CORP. • 9TH FLOOR – AUGUST 22, 2019 – FOR QC ACCEPTANCE
60% JULY 30,2019
(7TH – 12TH FLOOR) • 10TH FLOOR – AUGUST 22, 2019 – FOR QC ACCEPTANCE
• 11TH FLOOR – AUGUST 22, 2019 – FOR QC ACCEPTANCE
• 12TH FLOOR – AUGUST 22, 2019 – FOR QC ACCEPTANCE

• GROUND – 4TH & 7TH FLOOR– QC ACCEPTED


ARCHITECTURAL • 8TH FLOOR – QC VALIDATION ON JULY 25,2019
INTERIOR FIT-OUT (HALLWAY) MEGALUX CONSTRUCTION & DEVT CORP. 80 % PROGRESS AUGUST 20,2019 • 5TH, 6TH , 9TH -12TH FLOOR – UNTIL AUGUST 20,2019

ARCHITECTURAL
INTERIOR FIT-OUT (LOUNGE) ONGPENG-SANTOS CONSTRUCTION CORP. 95% • FOR PTO

WINDOWS SEAPAC PHILIPPINES INC. 100% • FOR QC ACCEPTANCE


% WT. OF
TRADES CONTRACTOR TARGET DATE COMPLETION REMARKS
ACCOMPLISHMENT

• INSTALLED WINDOW EXHAUST FANS AT LVSG, POWER CENTER, MDF


ROOM AND STORAGE ROOM
• TESTED AND ACCEPTED CEILING EXHAUST FANS WITNESS BY GERI
MECHANICAL TRIA 88% PROGRESS AUGUST 30, 2019
SITE AND QC AT 1ST, 2ND AND 7TH FLOOR
• INITIALTEST OF FANS AND BLOWERS AT ROOFDECK
• AIR BALANCING OF FANS AND BLOWERS ON JULY 30, 2019

• COMPLETED POWER CENTER.


• ENERGIZATION OF HP3 – NOVEMBER 16, 2018
• COMPLETED GENSET ELECTRICAL WORKS.
• COMPLETED KWH METERS GROUND TO 12TH FLOORS
ELECTRICAL / AUXILLIARY ECEAS 94% PROGRESS AUGUST 30, 2019 • INSTALLED DEVICES AT 1ST , 2ND, 3RD ,4TH ,7TH , 8TH AND 12TH FLOOR
FLOORS
• TESTED AND ACCEPTED ELECTRICAL DEVICES AT 1ST, 2ND, 7TH AND
8TH FLOORS
• TESTED AND ACCEPTED AUXILIARY DEVICES AT 1ST TO 12TH FLOORS

• TESTED AND ACCEPTED PLUMBING/SANITARY PIPING BY GERI & QC


FROM 1ST TO 12TH FLOOR.
• INSTALLED PLUMBING ACCESSORIES AT 1ST,2ND , 7TH AND 8TH FLOOR
• TESTED AND ACCEPTED FUNCTIONALITY 10 OUT OF 11 UNITS AT 1ST
FLOOR.
PLUMBING / SANITARY SGX 85% PROGRESS AUGUST 30, 2019
• TESTED AND ACCEPTED FUNCTIONALITY 8 OUT OF 16 UNITS AT 7TH
FLOOR.
• 2ND FLOOR FOR FUNCTIONALITY TESTING ON JULY 29, 2019
• 8TH FLOOR FOR FUNCTIONALITY TESTING ON JULY 31, 2019

WATERTANK CHRYSALIS 85% PROGRESS AUGUST 15, 2019 • MINOR RECTIFICATION WORKS

• TESTED AND ACCEPTED HYDROTEST BY GERI SITE AND


FIRE PROTECTION QUEST-AIR TECH PHILS. 98% PROGRESS AUGUST 15, 2019
GERI QC: GF TO 12TH FLOORS (Hallway and Units)

• • HALLWAY CAMERA VIEWING FROM GF TO 9TH AND 12TH FLOOR.


• • INSTALLED FDAS DEVICES (UNITS) FROM 1ST - 4TH, 7TH , 9TH AND 12TH
FLOOR
FIRE DETECTION AND ALARM SYSTEM, • • TESTED AND ACCEPTED FDAS DEVICES WITNESS BY GERI SITE AND QC
MULTILINE 88% PROGRESS
CCTV AND INTERCOM SYSTEMS AUGUST 30, 2019 (HALLWAY) GF TO 9TH FROM FLOOR; (UNITS) 1ST,2ND , 7TH AND 8TH FLOOR.
• • TESTED AND ACCEPTED INTERCOM DEVICES (UNITS) AT 1ST , 2ND , 7TH
AND 8TH FLOOR
• • TESTED AND ACCEPTED FDAS DEVICES WITNESS BY GERI SITE AND QC
(UNITS) AT 1ST ,2ND , 7TH AND 8TH FLOOR
•Critical items

 PRIORITY UNITS
 2ND FLOOR UNIT E
 2ND FLOOR UNIT F
 3RD FLOOR UNIT K
 4TH FLOOR UNIT O
 4TH FLOOR UNIT P
 5TH FLOOR UNIT F
 5TH FLOOR UNIT J
 6TH FLOOR UNIT A
 6TH FLOOR UNIT P
 7TH FLOOR UNIT B
 7TH FLOOR UNIT G
 8TH FLOOR UNIT G
 10TH FLOOR UNIT C
 GROUND FLOOR UNIT D

HP3 - MONTHLY COORDINATION MEETING


•Critical items
AS OF JULY 23, 2019

 2ND Floor unit E


ARCHITECTURAL WORK BALANCED
 WATERPROOFING WORKS
 LIVING AREA & T&B TILE WORKS
 PAINTING WORKS
MEPFS WORK BALANCED
 INSTALLATION OF DEVICE &
FIXTURES 2ND FLOOR PLAN
 FUNCTIONALITY

TARGET COMPLETION :
AUGUST 7,2019

HP3 - MONTHLY COORDINATION MEETING


•Critical items
AS OF JULY 23, 2019

 2ND Floor unit F


ARCHITECTURAL WORK BALANCED
 WATERPROOFING WORKS
 LIVING AREA & T&B TILE WORKS
 PAINTING WORKS
MEPFS WORK BALANCED
 INSTALLATION OF DEVICE &
2ND FLOOR PLAN
FIXTURES
 FUNCTIONALITY

TARGET COMPLETION :
AUGUST 7,2019

HP3 - MONTHLY COORDINATION MEETING


•Critical items
AS OF JULY 23, 2019

 3RD Floor unit K


ARCHITECTURAL WORK BALANCED
 WATERPROOFING WORKS
 LIVING AREA & T&B TILE WORKS
 PAINTING WORKS
MEPFS WORK BALANCED
 INSTALLATION OF DEVICE &
FIXTURES 3RD FLOOR PLAN
 FUNCTIONALITY
TARGET COMPLETION :
AUGUST 4,2019

HP3 - MONTHLY COORDINATION MEETING


•Critical items
AS OF JULY 23, 2019

 4TH Floor unit O


ARCHITECTURAL WORK BALANCED
 WATERPROOFING WORKS
 LIVING AREA & T&B TILE WORKS
 PAINTING WORKS
MEPFS WORK BALANCED
 INSTALLATION OF DEVICE &
FIXTURES 4TH FLOOR PLAN
 FUNCTIONALITY
TARGET COMPLETION :
AUGUST 4,2019

HP3 - MONTHLY COORDINATION MEETING


•Critical items
AS OF JULY 23, 2019

 4TH Floor unit P


ARCHITECTURAL WORK BALANCED
 WATERPROOFING WORKS
 LIVING AREA & T&B TILE WORKS
 PAINTING WORKS
MEPFS WORK BALANCED
 INSTALLATION OF DEVICE &
FIXTURES 4TH FLOOR PLAN
 FUNCTIONALITY
TARGET COMPLETION :
AUGUST 4,2019

HP3 - MONTHLY COORDINATION MEETING


•Critical items
AS OF JULY 23, 2019

 5TH Floor unit F


ARCHITECTURAL WORK BALANCED
 WATERPROOFING WORKS
 LIVING AREA & T&B TILE WORKS
 PAINTING WORKS
MEPFS WORK BALANCED
 INSTALLATION OF DEVICE &
FIXTURES 5TH FLOOR PLAN
 FUNCTIONALITY
TARGET COMPLETION :
AUGUST 5,2019

HP3 - MONTHLY COORDINATION MEETING


•Critical items
AS OF JULY 23, 2019

 5TH Floor unit J


ARCHITECTURAL WORK BALANCED
 WATERPROOFING WORKS
 LIVING AREA & T&B TILE WORKS
 PAINTING WORKS
MEPFS WORK BALANCED
 INSTALLATION OF DEVICE &
FIXTURES
5TH FLOOR PLAN
 FUNCTIONALITY
TARGET COMPLETION :
AUGUST 5,2019

HP3 - MONTHLY COORDINATION MEETING


•Critical items
AS OF JULY 23, 2019

 6TH Floor unit A


ARCHITECTURAL WORK BALANCED
 WATERPROOFING WORKS
 LIVING AREA & T&B TILE WORKS
 PAINTING WORKS
MEPFS WORK BALANCED
 INSTALLATION OF DEVICE &
FIXTURES
6TH FLOOR PLAN
 FUNCTIONALITY
TARGET COMPLETION :
AUGUST 5,2019

HP3 - MONTHLY COORDINATION MEETING


•Critical items
AS OF JULY 23, 2019

 6TH Floor unit N


ARCHITECTURAL WORK BALANCED
 WATERPROOFING WORKS
 LIVING AREA & T&B TILE WORKS
 PAINTING WORKS
MEPFS WORK BALANCED
 INSTALLATION OF DEVICE &
FIXTURES 6TH FLOOR PLAN
 FUNCTIONALITY
TARGET COMPLETION :
AUGUST 5,2019

HP3 - MONTHLY COORDINATION MEETING


•Critical items
AS OF JULY 23, 2019

 7TH Floor unit B


ARCHITECTURAL WORKS
 FOR CLOSE OUT OF PUNCHLIST

MEPFS WORKS
 FUNCTIONAL
 FOR QC INSPECTION 7TH FLOOR PLAN

TARGET COMPLETION :
JULY 26,2019

HP3 - MONTHLY COORDINATION MEETING


•Critical items
AS OF JULY 23, 2019

 7TH Floor unit G


ARCHITECTURAL WORKS
 FOR CLOSE OUT OF PUNCHLIST

MEPFS WORKS
 FUNCTIONAL
 FOR QC INSPECTION 7TH FLOOR PLAN

TARGET COMPLETION :
JULY 26,2019

HP3 - MONTHLY COORDINATION MEETING


•Critical items
AS OF JULY 23, 2019

 10TH Floor unit C


ARCHITECTURAL WORK BALANCED
 WATERPROOFING WORKS
 LIVING AREA & T&B TILE
WORKS
 PAINTING WORKS

MEPFS WORK BALANCED 10TH FLOOR PLAN


7TH FLOOR PLAN
 INSTALLATION OF DEVICE &
FIXTURES
 FUNCTIONALITY
TARGET COMPLETION :
AUGUST 07,2019
HP3 - MONTHLY COORDINATION MEETING
EXTERIOR WORKS
ELEVATION B AS OF JULY 23, 2019

REMARKS :

QC ACCEPTED LAST JUNE 10,2019


 PAINTED WALLS
 COMPLETE INSTALLED BALCONY (34/34)

HP3 - MONTHLY COORDINATION MEETING


EXTERIOR WORKS
ELEVATION E AS OF JULY 23, 2019

REMARKS :

QC ACCEPTED LAST JUNE 3,2019

INSTALLATION OF MOULDING :

TARGET TO START : AUGUST 5,2019


TARGET COMPLETION : AUGUST 17,2019

HP3 - MONTHLY COORDINATION MEETING


EXTERIOR WORKS
ELEVATION D

REMARKS :

QC ACCEPTED LAST MAY 27,2019


 PAINTED WALLS
 PAINTED PATIO FENCE AND RAILINGS
 INSTALLED GLASS CANOPY

BALANCED : PATIO FENCE DOWNLIGHT

INSTALLATION OF MOULDING :

TARGET TO START : AUGUST 1,2019


TARGET COMPLETION : AUGUST 15,2019

HP3 - MONTHLY COORDINATION MEETING


ELEVATION A
EXTERIOR WORKS
AS OF JULY 23, 2019
TARGET DATE COMPLETION :
JULY 24, 2019
ACCOMPLISHMENT : 95%

QC ACCEPTED

JULY 25,2019

HP3 - MONTHLY COORDINATION MEETING


ELEVATION C EXTERIOR WORKS
AS OF JULY 23, 2019
TARGET DATE COMPLETION :
JULY 24, 2019
ACCOMPLISHMENT : 95%

INSTALLATION OF
MOULDING
TARGET COMPLETION :
JULY 31,2019

HP3 - MONTHLY COORDINATION MEETING


LOUNGE
SCOPE STATUS TARGET DATE REMARKS

95%
FIT-OUT PROGRESS • FOR PTO

95%
MECHANICAL JULY 30, 2019 • BALANCE TESTING AND
PROGRESS
COMMISIONING OF ACU

PLUMBING 100% • COMPLETED.

ELECTRICAL 100% • COMPLETED.

FIRE PROTECTION 100% • COMPLETED.

FDAS (DEVICES &


100% •COMPLETED
INTERFACING)

90% • CAMERA VIEWING FROM GF TO 9TH


CCTV
PROGRESS AND 12TH FLOOR

HP3 - MONTHLY COORDINATION MEETING


LOUNGE
FOR PTO
95 % COMPLETED

HP3 - MONTHLY COORDINATION MEETING


ROOF DECK
SCOPE STATUS TARGET DATE REMARKS

• TRUSS - COMPLETED
100 % • GUTTER - COMPLETED
ROOFING WORKS
• UNDERSHEETING &ROOF TILE
- COMPLETED

50% TARGET COMPLETION:


PAINTING WORKS
PROGREES AUGUST 10,2019

95%
WATERPROOFING PROGRESS UPON DUCTING COMPLETION

95% TARGET COMPLETION: • BALANCED AIR BALANCING


MECHANICAL
PROGRESS JULY 30, 2019 OF EQUIPMENTS .

75% TARGET COMPLETION: • ON GOING INSTALLATION OF


ELECTRICAL
PROGRESS JULY 30, 2019 LIGHTING FIXTURES AND T&C

PLUMBING &
100% • COMPLETED.
SANITARY

FIRE PROTECTION 100% • COMPLETED.

FDAS (DEVICES & UPON HANDOVER OF AREA • BALANCE INSTALLATION OF


80% PROGRESS
INTERFACING) FIVE DAYS DURATION DEVICES AND T&C

• BALANCE
CCTV (FOR UPON HANDOVER OF AREA
85% PROGRESS INSTALLATION OF
ELEVATORS) THREE DAYS DURATION
CAMERAS AND T&C

HP3 - MONTHLY COORDINATION MEETING


ROOF DECK
AS OF JULY 23, 2019
ARCHITECTURAL WORKS
 PAINTING – 50% COMPLETED

MEPFS

 FANS & BLOWERS – 95%


COMPLETED
 PLUMBING LOW ZONE AND HIGH
ZONE – 100% COMPLETED

TARGET DATEWATER TANK – 85%
OVERHEAD
COMPLETION :
COMPLETED
JULY 15, 2019
ACCOMPLISHMENT : 80%

HP3 - MONTHLY COORDINATION MEETING


ROOFING WORKS ROOF DECK

100 % COMPLETED

HP3 - MONTHLY COORDINATION MEETING


HALLWAY
SCOPE STATUS TARGET DATE REMARKS

• GROUND TO 4TH & 7TH FLOOR – QC ACCEPTED


80% PROGRESS
FITOUT AUGUST 20, 2019 • 5TH , 6TH , 8TH – 12TH FLOOR –AUGUST 20,2019

PRIOR TO FINAL
PAINTING • INSTALLED LIGHTING FIXTURES AT GF TO 9TH
ELECTRICAL 95% PROGRESS
ONE WEEK AND 12TH FLOORS
DURATION

TARGET
PLUMBING &
100% COMPLETION: COMPLETED.
SANITARY
JULY 10, 2019

FIRE
100% COMPLETED.
PROTECTION

PRIOR TO FINAL
FDAS
PAINTING •INSTALLED SMOKE DETECTORS AT GF TO 9TH
(DEVICES & 95% PROGRESS
ONE WEEK AND 12TH FLOORS.
INTERFACING)
DURATION

PRIOR TO FINAL
PAINTING •INSTALLED CCTV CAMERAS AT GF TO 9TH AND
CCTV 85% PROGRESS
ONE WEEK 12TH FLOORS.
DURATION

HP3 - MONTHLY COORDINATION MEETING


HALLWAY
AS OF JULY 23, 2019
QC ACCEPTED

QC ACCEPTED

Ground Floor

1st Floor
HP3 - MONTHLY COORDINATION MEETING
HALLWAY
AS OF JULY 23, 2019

QC ACCEPTED
QC ACCEPTED

2nd Floor

3rd Floor

HP3 - MONTHLY COORDINATION MEETING


HALLWAY
AS OF JULY 23, 2019

QC ACCEPTED PAINTING WORKS

4th Floor

5th Floor

HP3 - MONTHLY COORDINATION MEETING


HALLWAY
PAINTING WORKS
AS OF JULY 23, 2019

QC ACCEPTED

6th Floor
7th Floor

HP3 - MONTHLY COORDINATION MEETING


HALLWAY
PAINTING WORKS AS OF JULY 23, 2019
PAINTING WORKS

8th Floor
9th Floor
HP3 - MONTHLY COORDINATION MEETING
HALLWAY
AS OF JULY 23, 2019
PAINTING WORKS

PAINTING WORKS

10th Floor
11th Floor
HP3 - MONTHLY COORDINATION MEETING
HALLWAY
AS OF JULY 23, 2019

12th Floor

HP3 - MONTHLY COORDINATION MEETING


UNITS
SCOPE STATUS TARGET DATE REMARKS

TARGET COMPLETION:
RVN 2nd FLOOR
60% JULY 30, 2019 •FOR CLOSE OUT OF QC
FITOUT
PROGRESS MEGALUX 7TH FLOOR PUNCHLIST
JULY 27,,2019

UPON HANDOVER OF T&B • INSTALLED TOILET EXHAUST


89%
MECHANICAL CEILING FANS AT 1ST, 2ND AND 7TH
PROGRESS
FIVE DAYS FLOORS

PRIOR TO FITOUT •ACCEPTED FUNCTIONALITY TEST


84%
ELECTRICAL CONTRACTOR WITNESS BY GERI SITE AND QC AT
PROGRESS
TWO WEEKS DURATION 1ST, 2ND , 7TH AND 8TH FLOORS

•INSTALLED PLUMBING FIXTURES


AND ACCESSORIES AT 1ST, 2ND , 7TH
UPON HANDOVER OF T&B
PLUMBING & 90% AND 8TH FLOOR.
AND KITCHEN AREA
SANITARY PROGRESS •ACCEPTED FUNCTIONALITY TEST
FIVE DAYS
WITNESS BY GERI SITE AND QC AT
1ST AND 7TH FLOORS

FIRE
100% COMPLETED.
PROTECTION

•INSTALLED FDAS DEVICES AT 1ST ,


2ND , 7TH - 9TH FLOORS
FDAS (DEVICES & 85% PRIOR TO FINAL PAINT • ACCEPTED FUNCTIONALITY
INTERFACING) PROGRESS ONE WEEK DURATION TEST WITH GERI SITE AND QC
AT 1ST , 2ND , 7TH AND 8TH
FLOOR.

• • ACCEPTED FUNCTIONALITY
95% ONE WEEK PRIOR TO TEST CATV, DATA AND
AUXILLIARY
PROGRESS FINAL PAINT TELEPHONE WITH GERI SITE
ST TH
1st Floor - UNITS
AS OF JULY 23, 2019
ARCHITECTURAL WORKS
• FOR CLOSE-OUT OF PUNCHLIST
 QC ACCEPTED – A-D,F-K (10/11)

MEPFS WORKS
Unit A
• FOR CLOSE-OUT OF PUNCHLIST
 QC ACCEPTED – BCDH&K (5/11)
 QC PARTIALLY ACCEPTED – AFGIJ
(5/6)
 ALL UNITS– FUNCTIONAL

TARGET COMPLETION :
JULY 26,2019
Unit B
HP3 - MONTHLY COORDINATION MEETING
2ND Floor - UNITS
AS OF JULY 23, 2019
ARCHITECTURAL WORKS
• FOR QC INSPECTION/VALIDATION
 QC INSPECTED - DHKMNP 6/16
Unit F
MEPFS WORKS
• FOR INSPECTION/VALIDATION
 ALL UNITS– FUNCTIONAL

TARGET COMPLETION :
JULY 30,2019

Unit B
HP3 - MONTHLY COORDINATION MEETING
7TH Floor - UNITS
AS OF JULY 23, 2019
ARCHITECTURAL WORKS
• FOR INSPECTION/VALIDATION
 QC INSPECTED - UNITS ABCDKN

unit H
MEPFS WORKS
• FOR INSPECTION/VALIDATION
 UNIT A-P – FUNCTIONAL

TARGET COMPLETION :
JULY 26,2019

unit G
HP3 - MONTHLY COORDINATION MEETING
8TH Floor - UNITS
AS OF JULY 23, 2019
ARCHITECTURAL WORKS
• FOR INSPECTION/VALIDATION
 UNIT A – P

unit L
MEPFS WORKS
• FOR INSPECTION/VALIDATION
 UNIT A-P – FUNCTIONAL

TARGET COMPLETION :
JULY 31,2019

unit A
HP3 - MONTHLY COORDINATION MEETING
FIRE EXITS
SCOPE STATUS TARGET DATE REMARKS

TARGET COMPLETION:
ARCHITECTURAL 95% • RAILING INSTALLED 100%
JULY 26,2019
FIRE EXIT 5 PROGRESS • PAINTING 95%

• MASONRY WORKS 95%


85% • RAILING INSTALLED 100%
ARCHITECTURAL TARGET COMPLETION:
PROGRESS • PAINTING 80%
FIRE EXIT 1 JULY 31,2019

90% TARGET COMPLETION:


MECHANICAL • BALANCE INSTALLATION OF
PROGRESS AUGUST 15, 2019
EXHAUST GRILLES AND T&C

• GERI SITE AND QC ACCEPTED


UPON COMPLETION OF
75% FUNCTIONALITY TEST AT FIRE EXIT1
ELECTRICAL PAINTING WORKS.
PROGRESS • BALANCE INSTALLATION OF
ONE WEEK DURATION
DEVICES AND T&C AT FIRE EXIT 2.

FIRE
100% • COMPLETED.
PROTECTION

HP3 - MONTHLY COORDINATION MEETING


FIRE EXIT - 5
FOR QC VALIDATION ON
JULY 24,2019

95 % COMPLETED

HP3 - MONTHLY COORDINATION MEETING


FIRE EXIT - 1
FOR QC INSPECTION ON
JULY 28,2019

70 % COMPLETED

HP3 - MONTHLY COORDINATION MEETING


RAILINGS
FIRE EXITS

100 % RAILINGS
INSTALLED

70% PAINTING WORKS

HP3 - MONTHLY COORDINATION MEETING


ELEVATOR
SCOPE STATUS TARGET DATE REMARKS

STRUCTURAL 100%

• BALANCE INSTALLATION
95%
ELECTRICAL AUGUST 3, 2019 OF CCTV CAMERAS IN
PROGRESS
ELEVATOR AND T&C.

PE- FOR HANDOVER ON JUNE


45% TDC OF PE-1 – MAY
28,2019
SCHINDLER PROGRESS 16,2019
PE-2 FOR HANDOVER ON JULY
10,2019

HP3 - MONTHLY COORDINATION MEETING


ELECTRICAL/AUXILLIARY ROOM
SCOPE STATUS TARGET DATE REMARKS

2ND TO 7TH FLOOR – FOR VDC


80% CLOSEOUT OF PUNCHLISTS
ARCHITECTURAL DECEMBER 5,2018
PROGRESS 8TH TO 12TH FLOOR – FOR ECEAS
CLOSEOUT OF PUNCHLISTS

98% • BALANCE INSTALLATION OF


MECHANICAL
PROGRESS EXHAUST GRILLES

ELECTRICAL 100% • COMPLETED.

VERTICAL BUS
100% • COMPLETED.
DUCT

FDAS (DEVICES &


100% • COMPLETED.
INTERFACING)

AUXILIARY 100% • COMPLETED.

HP3 - MONTHLY COORDINATION MEETING


OSVP - Project Manager

Sr. Site Engineer - CE

Site Engineer - EE

HP3 - MONTHLY COORDINATION MEETING


HP3 - MONTHLY COORDINATION MEETING