KEBUK SAMPAH,
DI ATAS LOT PTD 200670, MUKIM PULAI, DAERAH JOHOR BAHRU, JOHOR DARUL TA'ZIM
Date : 20/4/2020
APPROXIMATE COST FOR DOUBLE STORY PROVISION
OMISSION ADDITION
Rate Amount Rate Amount
Item Description Unit Qty
(RM) (RM) (RM) (RM)
A Oversite excavation; max depth n.e 1.0m deep m3 25.00 246 6,150.00 289 7,225.00
E Reinforcement
- Apron slab kg 3.60 1,411 5,079.60 3,812 13,721.40
- Raft slab kg 3.60 3,592 12,931.20 5,544 19,958.40
- Pad footing kg 3.60 189 680.40 189 680.40
- Ground beam kg 3.60 3,619 13,028.40 3,619 13,028.40
F Sawn formwork
- Side of pad footing m2 45.00 10 450.00 10 450.00
- Sides of ground beam m2 45.00 121 5,445.00 121 5,445.00
- Edge of slab/drop; 100mm - 200m thick m 15.00 97 1,455.00 - -
- Edge of slab/drop; 200mm - 300mm thick m 18.00 - - 98 1,764.00
FRAME
J Column
- Vibrated reinforced concrete (G25) m3 280.00 7 1,960.00 10 2,800.00
- Reinforcement kg 3.60 1,704 6,134.40 3,000 10,800.00
- Sides of formwork m2 45.00 131 5,895.00 146 6,570.00