Professional Documents
Culture Documents
www.elsevier.com/locate/ces
Received 25 May 2004; received in revised form 15 October 2004; accepted 7 March 2005
Abstract
The paper presents a systematic approach for the synthesis of flexible utility systems satisfying varying energy demands. The approach
combines benefits of total site analysis, thermodynamic analysis and mathematical optimisation. A thermodynamic efficiency curve (TEC)
is developed, which gives an overview of the maximum thermodynamic efficiencies of all possible design alternatives. TEC and hardware
composites guide the selection of candidate structures in the superstructure, excluding uneconomic options from the synthesis model.
The integration of thermodynamics yields significant reduction in the synthesis model, addresses the impact of variable loads on the unit
efficiencies, and enables a compact formulation of the design problem over long horizons of operation. The optimisation is formulated as
a multi-period MILP problem that relies on new target models to describe the performance of steam turbines, condensing turbines, gas
turbines and boilers. Target models account for the variation of efficiency with unit size, load and operating conditions in a simple, yet
accurate way. As a result, these models are capable of accounting for the efficiency trends of realistic units.
䉷 2005 Elsevier Ltd. All rights reserved.
Keywords: Optimisation; Modelling; Process design; Utility systems; Thermodynamic analysis; Operational variations
vary with time, it is important that the utility system main- synthesis formulations in the form of multi-period MILP
tain high efficiency over the entire variation range. On the problems. These include boiler hardware models, steam tur-
other hand, the optimum trade-off between flexibility and bine hardware models and gas turbine hardware model. They
capital cost needs to be identified. In order to evaluate the account for the variability of equipment efficiency with size,
alternative design options and distinguish amongst the as- load and operating conditions. Thermodynamics are em-
sociated efficiencies, the effects of the unit size, as well as ployed to reduce the size of the superstructure and integrate
load and operating conditions on the unit efficiencies, need only units required to achieve maximum performance. The
to be taken into account. These effects generally involve approach is illustrated in several design problems most of
non-linear relations that give rise to complex models and which represent real-life applications.
formulations.
In the last two decades, a number of approaches have
been reported for the synthesis and design of utility systems. 2. Problem definition
Papoulias and Grossmann (1983) proposed an MILP ap-
proach for the synthesis of flexible utility systems accounting Given are
for anticipated variations in process demands in the shape of
a multiperiod utility demand pattern. Hui and Natori (1996) (i) a set of chemical processes whose requirements for
presented a mixed-integer formulation for multiperiod steam and power are addressed by a system of fixed
synthesis and operation planning for utility systems and steam levels;
discussed the industrial relevance. A simulated annealing (ii) a presumed horizon of operation;
algorithm was used by Maia and Qassim (1997) for the (iii) power and steam demands at each level;
synthesis of utility systems with variable utility demands. (iv) a set of units that could generate steam and power.
Iyer and Grossmann (1998) proposed a multi-period MILP
It is assumed that power can be generated by gas turbines,
approach for the synthesis and planning of utility sys-
steam turbines and diesel engines or by importing electricity
tems under multiple periods. Oliveira Francisco and Matos
from the utility grid. Boilers include
(2003) extended the model by Iyer and Grossmann to in-
clude global emissions of atmospheric pollutants from fuels (1) very high pressure (VHP) boilers fired by fuel;
combustion. (2) heat recovery steam generators (HRSG) which recover
It is well documented that the appropriate selection of heat contained in the gas turbine or the furnace exhaust
the different superstructure units/components reflects on gases (supplementary firing is allowed for these units);
the actual value of the synthesis work. Unless containing (3) waste heat boilers recovering heat from chemical pro-
appropriate candidates, the superstructure approach deliv- cesses;
ers inferior results. At the same time, exhaustive or blind (4) medium pressure boilers fired by fuel, which reheat
integration of potential units is pointless and ineffective. steam in reheat cycle;
Multiple operational scenarios simply increase the size of
the synthesis model, whereas efficiencies are complicated Gas turbines are available through the following configura-
enough to be treated as parameters by the majority of re- tions:
searchers. None of the previous approaches have addressed (1) simple gas turbine cycles, and
the challenge to select superstructure units as a result of (2) regenerative gas turbine cycles.
operational variations. This is particularly important as unit
sizes directly relate—and have a major impact—on the net- Steam turbines may include
work efficiency. At the same time, size and efficiency count
as complicating variables since, if introduced to the formula- (1) BP steam turbines.
tion, they both lead to significant complexities. Mavromatis (2) extraction BP steam turbines, and
and Kokossis (1998a, b) have presented an approach to de- (3) condensing turbines.
couple the non-linear components of unit efficiencies with
the use of thermodynamic models. They accordingly man- The design problem is to determine the structure of the site
aged to formulate an MILP model for the design of steam utility system that minimises the total cost so that to satisfy
turbine networks that takes into account the impact of op- utility demands across the selected operation horizon. The
erational variations on the efficiencies. Tested on real-life optimisation of the steam levels has been addressed previ-
problems, and although limited to BP turbines, the approach ously by Shang and Kokossis (2004). The horizon is com-
reports improvements of 11% against cases that neglect posed by a number of periods whose length may be different.
variations or consider unit efficiencies as constant. The boiler capacities should be determined by the optimi-
This paper presents a methodology inspired by these last sation, and their efficiencies depend on their capacity, heat
developments. The approach is not limited to particular units load and operating conditions. Steam is collected and dis-
though but includes boilers, gas turbines and all types of tributed to the chemical processes, the steam turbines, the
steam turbines. Thermodynamic models are used to develop reheat cycles or to the next low pressure steam level through
Z. Shang, A. Kokossis / Chemical Engineering Science 60 (2005) 4431 – 4451 4433
VHP VHP
HP HP
Q1
MP
MP
Q2
LP
LP
Q3
CW
is developed with the use of the SCC. The sizes and posi-
tions of the turbines can also be identified using the curves.
Qsteam Qsteam
Qfuel
Qfuel
Boiler Boiler VHP
6. Thermodynamic analysis
B
Ff Qfuel
Qwaste
Qsteam
WB WB
Fa WG
GT QG
VHP VHP
+
VHP +
HP
HP MP
WC
MP LP
LP CW
CW VAC
Fig. 5. Integration of the GTWB cycle. Fig. 6. Integration of the BCT cycle.
process heat, therefore the VHP steam load is where T out can be calculated by using Eq. (B.18) (see Ap-
p pendix B). The steam load of the boiler is given by
QBsteam = Wi + Qi . (3)
where B
t is the thermodynamic efficiency of the boilers. 6.1.3. Integration of the boiler and condensing turbine
(BCT) cycle
6.1.2. Integration of the gas turbine and waste heat boiler The BCT cycle is shown in Fig. 6. As the exhaust heat
(GTWB) cycle of the condensing turbine is lost to cooling water, the useful
The GTWB cycle is shown in Fig. 5. The gas turbine is energy is the power output of the condensing turbine and
integrated with the waste heat boiler to generate power, and the efficiency is calculated by
the waste heat boiler is used to raise steam. It is assumed that
the gas turbine works at full load (i.e., maximum efficiency WC
BCT
t = , (9)
load). The useful energy is the power output of the gas tur- QB
fuel
bine and the steam load raised by the waste heat boiler. The
efficiency is calculated as where W C is the power output of the condensing turbine
and QB fuel is the fuel consumption. It is assumed that the
W G + QG
GTWB
t = , (5) condensing turbine works at full load. Hence, on the basis
F f Hf of the CTHM (see Appendix A), the relation between the
power output and the steam load crossing the condensing
where W G is the power output, QG the steam load generated
turbine is
in the waste heat boiler; F f the fuel consumption. On the
basis of the GTHM, the fuel consumption is given by 1
M= (Ac + B c W C ). (10)
1 H is
Ff = (Ag + B g W G ). (6)
Hf The fuel requirement is given by
As presented by Cohen et al. (1987), the stack temperature
1
is assumed as 170 ◦ C. The useful waste heat from the gas QB
fuel = qM, (11)
turbine to the boiler is B
t
Qwaste = F f
1+
1
Cp g (T out − 170), (7) where q is the specific heat load of the steam and B
t is the
f thermodynamic efficiency of the boiler.
4436 Z. Shang, A. Kokossis / Chemical Engineering Science 60 (2005) 4431 – 4451
VHP
Ff Qwaste
Qsteam
WB
Fa WG
GT HP
VHP VHP
+ MP
HP Qsurp
MP
MP
WC
LP
LP
CW
Wsurp
VAC
SCT BCT
6.1.4. Integration of the gas turbine, waste heat boiler and IP
condensing turbine (GTWBCT) cycle PSCT PBBPT PGTWB PGTWBCT PBCT PIP
The GTWBCT cycle is shown in Fig. 7. If the gas turbine
and the waste heat boiler cycle produce more steam than re- PA PB PC PD Power (MW)
quired, a condensing turbine is integrated to generate addi-
tional power by using the surplus heat. The thermodynamic Fig. 9. The TEC.
efficiency for the cycle is accordingly
WC + WG either buy W impt power or Qfuel fuel to generate power with
GTWBCT
t = , (13)
F f Hf the same cost). The thermal efficiency for generating power
using Qfuel fuel is equal to the power generated over Qfuel .
where W C and W G are the power outputs of the condensing Similarly, the imported power efficiency is defined as
turbine and the gas turbine respectively. W C is calculated by
applying the CTHM and W G is calculated by the GTHM. W impt CF
impt = = P, (15)
Qfuel C
6.1.5. Integration of the surplus steam condensing turbine
(SCT) where C F is the unit fuel price and C P is the unit power
The SCT is defined as the condensing turbine using sur- price. The concept provides the efficiency for importing
plus steam from chemical processes as shown in Fig. 8. Con- power and is used to compare operation with alternative
densing turbines are integrated to generate power with the structures.
surplus heat. As the SCT uses surplus heat, it is the one to
first consider for power and the efficiency is given by 6.2. Thermodynamic efficiency curve (TEC)
surp W surp
t = , (14) The TEC plots efficiencies vs. power demands for the dif-
Qsurp
ferent utility structures discussed earlier. Its graphical pre-
where W surp is the power output of the condensing turbine sentation is given in Fig. 9. Its first horizontal section ac-
and Qsurp is the surplus heat of the chemical processes. The counts for the units using surplus heat from the chemical
W surp can be calculated by using the CTHM. processes (SCT). The step length is determined by the max-
imum capacity of the units involved. From left to right—and
6.1.6. Import of power (IP) with the exception of its first section—the TEC expands to
The thermodynamic efficiency for importing power fol- sections with lower efficiency.
lows the top level analysis (Makwana, 1997) that assumes Once the energy requirements are determined (by the to-
that the cost of Qfuel fuel can buy W impt power (one could tal site analysis), the appropriate structures and sizes of the
Z. Shang, A. Kokossis / Chemical Engineering Science 60 (2005) 4431 – 4451 4437
7.1. Superset of BP steam turbines The capacity of the gas turbine for each scenario is deter-
mined by using the TEC. For multiple operation scenarios
As discussed by Mavromatis and Kokossis (1998b), both the number, sizes and types of candidate gas turbines of the
complex turbines and multistage turbines are equivalent to a superset depend on the specific problem, as explained in the
cascade of simple turbines, each taking up potential from a following section.
single expansion zone, as shown in Fig. 10. On the grounds
of the equivalence, all possible combinations of turbine lay- 7.2.1. Types of gas turbines in the superset
outs can be reduced to a single superset of component cylin- The types of the gas turbine cycles are concerned with
ders as illustrated by Fig. 11. This superset of design com- simple and regenerative gas turbine cycles. The major differ-
ponents is adequate to achieve the targets expected by the ence between the simple and regenerative gas turbine cycles
BP steam turbine network. The assumption is apparently is the addition of a recuperator for heat exchange between
correct from the thermodynamic point of view, as the total the turbine outlet and the compressor outlet as shown in
4438 Z. Shang, A. Kokossis / Chemical Engineering Science 60 (2005) 4431 – 4451
Scenario B 0.5
Scenario A 40MW
HP HP 60MW
0.4
T1 T2 T3 20MW
0.3
ηe
MP MP 0.2
T2
T1
T3 Superset of BP steam turbines 0.1
0
η η η 0 10 20 30 40 50 60
W (MW)
T1 T2 T2
T1 T3
Fig. 14. The effect of part load operation prevails over the increase of
Q efficiency with gas turbine size.
Q Q
Option 1 Option 2 Option 3
Fig. 12. The candidate BP steam turbines for the case of two scenarios.
7.2.2. Number and sizes of gas turbines in the superset
The GTHM relates the power output to the fuel load and
the size of the gas turbine as shown in Eq. (B.17) in Ap-
pendix B. As both the load and size of the unit need to
Heat-exchanger be optimised, straightforward modelling would result in an
MINLP formulation. The discretisation method enables in-
stead the formulation of an MILP problem. The economic
Fuel analysis of the gas turbine operation suggests the discrete
Air sizes and number of the candidate gas turbines. As elec-
trical efficiency increases with size but decreases with par-
Power tial load, the highest efficiency is obtained for gas turbines
Compressor Turbine
sized and operating at full load. This is shown in Fig. 14.
Fig. 13. The regenerative gas turbine. In terms of efficiency, the optimum size for each scenario
exactly matches its power demand. Following the discretisa-
tion scheme used for BP steam turbines, a similar discreti-
sation method is proposed whereby gas turbines are sized
Table 1
to match the power demand of every scenario as well as all
P /H characteristics of gas turbine cycles
their possible combinations.
Gas turbine cycle P /H ratio
Waste heat namic analysis, rather than for the exhaustive structures. The
binary variables account for the selection of units and their
Fuel Fuel Fuel operation status at each scenario. The continuous variables
relate to the stream flowrates (steam, fuel), the power out-
Water
VHP puts and the operating and capital costs.
The optimisation problem involves the following defini-
Fig. 15. Superset of boilers. tions for sets, parameters and variables:
Sets
saturation temperature of the steam generated in the boiler
and the temperature of the boiler inlet water; q the specific I B = {ib|candidate boilers},
heat load of the steam generated in the boiler; M the steam I T = {it|candidate BP steam turbines},
load; M max the maximum steam load; a and b the regression I C = {ic|candidate condensing turbines},
parameters. The above expression relates to the fuel flowrate V C = {vc|candidate VHP condensing turbines},
with the steam load and the boiler size. The superset of the P = {pi|power generation units},
boilers is shown in Fig. 15. The waste heat is the waste heat I = {i|selected units},
from gas turbine cycles. The number, sizes and fuel require- I G = {ig|candidate gas turbines},
ments of the boilers are determined by the optimisation. K = {k|operation scenarios},
Z = {z|expansion zones}.
7.4. VHP condensing steam turbines, surplus steam
condensing turbines, and reheat cycles Parameters
For each scenario, the power output of the VHP condens- a, b regression parameters of the BHM
ing turbine is determined by the TECs. For a single scenario, Aic , Bic regression parameters of the CTHM
the optimum size matches exactly the power demand. For Ag , B g regression parameters of the GTHM
multiple scenarios, the number and sizes of candidate con- Az , Bz regression parameters of the THM for BP steam
densing turbines of the superset for multiple operation sce- turbines of expansion zone z
narios are determined by the discretisation scheme followed Cp specific heat of boiler water
for the gas turbines. Cpg specific heat of gas turbine flue gas
For each steam level, the surplus heat of the processes is Cpa specific heat of gas turbine combustion air
obtained by total site analysis. The number and sizes of the Cpf specific heat of gas turbine fuel
surplus condensing turbines are determined in a similar way EI S ic isentropic enthalpy change of condensing tur-
as VHP condensing steam turbines. For multiple operation bine ic
scenarios, the surplus steam condensing turbines are sized EI S z isentropic enthalpy change of BP steam turbines
to match the demands of each individual scenario as well as of expansion zone z
f,max
all their different combinations. Fig maximum fuel load of gas turbine ig
In a reheat cycle, steam is first expanded to some interme- H operating hours per year
diate pressure and then reheated in the boiler. It next expands Hf specific fuel combustion heat
in the turbine to the exhaust pressure. Following Chou and LB lower bound of boiler capacities
Shih (1987), the reheat cycle can improve the overall ther- BT ,max
Mib maximum steam load of boiler ib
mal efficiency only if the thermal efficiency contributed by BT ,max
the reheat part is greater than that of the remaining parts. The Mz,it maximum steam load of BP steam turbine it of
required large heat-exchange area and the increased com- expansion zone z
CT ,max
plexity in system design detract from the gain in efficiency Mic maximum steam load of condensing turbine ic
c
Mz,k total steam load across each expansion zone z
due to reheating. The reheat cycle, therefore, will be of in-
terest to site utility system design only when a lot of heat is under scenario k
exhausted to cooling water. qib specific heat load of the steam generated in
boiler ib
Ta temperature of inlet air of gas turbines
8. Optimisation model Tf temperature of gas turbine fuel
Tib,k
sat temperature difference between the saturation
In this section, a multi-period MILP model is presented temperature of the steam generated in the boiler
for the minimisation of capital investment and operating and the temperature of the boiler inlet water
cost. The model incorporates the BHM, THM, CTHM and TkS time fraction of scenario k
GTHM models. The optimisation is a screening tool for the UB upper bound of boiler capacities
f
selected alternative design options by using the thermody- Uk unit cost of fuel for boilers under scenario k
4440 Z. Shang, A. Kokossis / Chemical Engineering Science 60 (2005) 4431 – 4451
GT ,f
Uk unit cost of fuel for gas turbines under scenario The above bilinear model is replaced by the following mixed
k integer linear model:
Wkdem power demand of site processes under scenario B,f
k Qib,k + QB,w
ib,k = (Cp Tk + q)
sat
B
Binary variables ((1 + b)Mib,k + aX B
ib,k ), ib ∈ I B, k ∈ K. (18)
The load of the steam turbine should not be larger than its valves (in case the installation of a turbine is not cost effec-
capacity: tive). The mass balances give
BT ,o BT ,max
BT BT t c
Mz,it,k − yz,it,k Mz,it 0, z ∈ Z, it ∈ I T , k ∈ K Mz,it,k + Mz,k = Mz,k , z ∈ Z, k ∈ K. (36)
(28) it∈I T
(c) Condensing steam turbines: The CTHM applied for The VHP steam requirement is equal to the sum of the
the power output of a condensing turbine under scenario k amount of steam across the first expansion zone plus the
yields: amount of the steam through the VHP condensing turbines.
B c CT
6 1 Aic Mib,k = M1,k + Mvc,k , k ∈ K. (37)
CT
Wic,k = EI S ic − CT ,max ib∈I B vc∈V C
5 Bic Mic
(f) Power balance: The electricity balance under scenario
CT 1 CT ,max CT ,o
× Mic,k − Mic yit,k , k is expressed as
6
ic ∈ I C, k ∈ K. (29) buy
Wpi,k + Wk = Wkdem , k ∈ K. (38)
If the condensing turbine is not selected, it cannot operate: pi∈P
Table 2
Capital cost data (Bruno et al., 1998)
Even though the primitive approach to the problem yields an VHP header Saturation temperature: 303 ◦ C
HP header Saturation temperature: 275 ◦ C
MINLP formulation with a very large number of variables,
MP header Saturation temperature: 210 ◦ C
the use of total site analysis and the TCE reduces it into a LP header Saturation temperature: 140 ◦ C
reasonably sized MILP. The optimisation yields a layout of Vacuum header Temperature: 60 ◦ C, Pressure: 0.02 MPa
simple turbines that are post-processed to synthesise com- Deaerator Vent ratio: 0.0015
plex or multi-stage turbines. For two cylinders to merge into
a complex unit, they both have to be loaded during the same
scenario. Depending on whether the steam flow through the Table 4
upper cylinders is larger or smaller than that in the lower Utility data
sections, the turbines can be of an extraction or induced type. Demineralized water Fuel (natural gas) Electricity
When considering different operating scenarios, Shang the aim is to find the optimal configuration of the site utility
and Kokossis (2004) presented an approach to optimise the system that satisfies the utility demands and minimises the
steam levels of a total site. Having specified the optimal annual total cost.
steam levels, the optimal configuration of the site utility sys-
tem is determined with the approach presented in this work. 9.1.1. Totals site analysis
Two case studies are selected to illustrate the capabilities of The SUGCCs are given in Fig. 16. The steam across
the methodology. The operating conditions of the four steam each expansion zone is obtained in Table 6. LP steam is in
levels, the vacuum header and the deaerator are shown in surplus and used by the condensing turbines. BP turbines
Table 3. The pressures for VHP, HP, MP and LP are, re- are installed in the steam expansion zones of VHP–HP and
spectively, 9, 6, 1.9, 0.36 MPa. The steam used for heating HP–MP. The power outputs for the possible SCT and BBPT
returns as condensate. The case studies feature different util- cycles are calculated using CTHM and THM models based
ity demands. The utility costs are shown in Table 4 and the on the inlet and outlet steam conditions and the resulting
capital costs are presented in Table 2. values are shown in Table 7.
T T Scenario B T Scenario C
Scenario A 220 260
180 VHP VHP
VHP 40 40
HP HP HP
50 MP MP
MP 300
130 50 260 60
LP 30 LP LP
VAC VAC VAC
H(t/h) H(t/h)
H(t/h)
9.1.4. Optimisation
Table 7
The superstructure is formulated as an MILP model. The
Power outputs of possible SCT and BBPT cycles of Case 1
optimisation minimises the total annual cost. The model is
Scenario A Scenario B Scenario C developed using GAMS and the optimisation is conducted
SCT (MW) 2.5 4.1 5 by employing the OSL solver. The model involves 195 con-
BBPT (MW) 13 22.9 26.7 tinuous variables, 92 binary variables and 242 constraints.
The optimum configuration is given in Fig. 19. The se-
lected units include three BP steam turbines, one condens-
ing turbine, one gas turbine, a VHP boiler, an HP waste
Table 8 heat boiler, an MP waste heat boiler and the deaerator. The
P /H characteristics of Case 1 HP and MP waste heat boilers are selected to produce HP
Scenario A Scenario B Scenario C
and MP steam, respectively. One of the BP turbines oper-
ates between the VHP and the HP levels. The other two
P /H ratio 0.22 0.285 0.29 BP turbines operate between the HP and MP levels. They
supply power by exploiting the cogeneration potential. The
condensing turbine is employed to generate power by using
surplus heat from the site processes. The BP turbines and
of a regenerative gas turbine cycle. By calculating the ef- the condensing turbine do not meet the power demands. The
ficiency and the maximum power output for each potential gas turbine is installed to supply the remaining power. The
cycle, the TEC is constructed for each one of the three op- total annual cost is 33.341 mUS$. The annual fuel cost is
eration scenarios as shown in Fig. 17. On the basis of the 27.718 mUS$ and the annual capital cost is 5.623 mUS$.
TECs and the utility demands, the promising candidate util- The capacities of the selected units are given in Fig. 19.
ity structures include the BBPT cycles, the SCT cycles and The optimal loads of the units are obtained under each
the GTWB cycles; all other design options are excluded as scenario. These are given in Table 13. The BP turbine BT1
less efficient. By using the TECs, the power outputs of the (HP–MP) operates during A, but not during B and C. Turbine
GTWB cycles are obtained for all the scenarios as shown in BT3 (HP–MP) operates during B and C, but not during
Table 9. A. During A turbine BT1 (HP–MP) is more efficient than
4444 Z. Shang, A. Kokossis / Chemical Engineering Science 60 (2005) 4431 – 4451
Scenario A ηe Scenario B
ηe BBPT
BBPT GTWB
GTWB
GTWBCT GTWBCT
BCT BCT
Simple GT Simple GT
IP
SCT IP SCT
P (MW) P (MW)
ηe Scenario C
BBPT
GTWB
GTWBCT
BCT
Simple GT
IP
SCT
P (MW)
B1 B2
VHP
BT1 BT2 BT3 BT4 BT5
HP
BT1 BT2 BT3 BT4 BT5
HPWHB
MP
LP
VAC.
DW COND.
Deaerator
Max 10.32MW
GT3
Max 260t/h
B1
VHP
BT3 Max 6.91MW
Max 50t/h
HP
BT1 Max 8.38MW BT3 Max 19.78MW
HPWHB
MP
Max 60t/h
LP
DW COND.
Deaerator
Although the SUGCCs of the two studied cases are the A systematic methodology is presented for the optimal
same, the optimal configurations of the site utility systems design of flexible site utility systems. The methodology
are different because of the different power demands. The combines the benefits of total site analysis, thermodynamic
studies imply that different P/H ratios assume different op- analysis and optimisation techniques. The approach ac-
timal structures. counts for the interactions between the site utility systems
A reduced superstructure is obtained by using thermody- and the site processes. The design task is addressed in view
namic analysis to screen out inefficient options. The reduc- of the anticipated variations in the process demands and the
tion is significant as it further replaces the need to solve the effect of the unit capacities and varying loads on the efficien-
MINLP with a need to solve an MILP problem instead. cies of the selected units. These aspects normally give rise to
B1 B2
VHP
HP
BT1 BT2 BT3 BT4 BT5
HPWHB
MP
LP
VAC.
DW COND.
Deaerator
Max 260t/h
B1
VHP
BT2 Max 5.78MW
Max 50t/h
HP
BT3 Max19.78MW
HPWHB
MP
Max 60t/h
LP
VAC.
DW COND.
Deaerator
Table 15 The total site analysis is employed to screen and identify all
Optimal loads of the units of Case 2 possible design options. A thermodynamic curve is proposed
Unit Scenario A Scenario B Scenario C in this approach. It is a useful tool to identify the promising
candidate design options to be included in the superstructure
BT2 (VHP–HP) 180 t/h 220 t/h 220 t/h
by screening among all alternative design options. The size
(steam load/ power output) 4.52 MW 5.78 MW 5.78 MW
BT3 (HP–MP) 119 t/h 243 t/h 300 t/h of the optimisation problem can be reduced by screening
(steam load/ power output) 5.49 MW 15.23 MW 19.78 MW out the uneconomic design options. The proposed approach
CT3 30 t/h 50 t/h 60 t/h has been illustrated with two case studies. The optimisation
(steam load/ power output) 2.0 MW 4.0 MW 5.0 MW problems of the two cases have been reduced significantly
VHP B1 (steam load) 180 t/h 220 t/h 260 t/h
compared to the full superstructure approach. As a result, the
HP WB (steam load) 50 t/h 0 t/h 0 t/h
LP WB (steam load) 30 t/h 50 t/h 60 t/h optimal solutions have been obtained in a reasonable time
Deaerator (water load) 210.3 t/h 310.5 t/h 360.5 t/h for the proposed approach.
By using the engineering knowledge and analytical in-
sight, a discrete scheme is proposed to identify the sizes of
Table 16 the candidate steam turbines, condensing turbines and gas
Results for the two approaches for Case 1 turbines. The optimisation problem is formulated as a multi-
Method Number of Number of period MILP model that relies on the THM, CTHM, GTHM
binary variables continuous variables and the BHM to describe the performance of the BP steam
Reduced superstructure 92 195 turbines, condensing turbines, gas turbines and boilers. The
Full superstructure 1628 2697 models account for the efficiency variations with operating
conditions and capacity. It should be emphasised that, had
conventional models for the units been applied, the use of
Table 17 an MINLP formulation would be inevitable.
Results for the two approaches for Case 2
Method Number of Number of
binary variables continuous variables
Reduced superstructure 60 97
Full superstructure 1140 1905 Appendix A. Condensing turbine hardware model
(CTHM)
0.85 0.35
0.8 0.3
0.25
0.75 0.2
Ac
0.7 0.15
ηis,max
0.65 0.1
14bar 0.05
0.6 28bar
41bar 0
0.55 62bar 150 200 250 300 350
83bar Tsat (°C)
0.5 103bar
0.45 Fig. 23. Regression parameter Ac as a function of inlet saturation tem-
0.1 1 10 100 perature.
Emax(MW)
Fig. 22. Typical data on the efficiency of condensing turbines (Peterson 1.35
and Mann, 1985).
1.3
Bc
given by
1.25
6 1 Ac
W= H is −
5 Bc M max
1.2
1 150 200 250 300 350
× M − M max . (A.1)
6 Tsat (°C)
W stands for the shaft-work of the condensing turbine; Ac , Fig. 24. Regression parameter B c as a function of inlet saturation tem-
B c are the regression parameters, H is the isentropic en- perature.
thalpy change; M the steam flowrate; and M max the steam
turbine capacity.
The isentropic efficiency is given by 0.25
6 1 Ac 1 M max 0.2
cis = 1 − 1 − . (A.2)
5 Bc H is M max 6 M 0.15
Ac
The differences between the CTHM and the THM relate to 0.1
the regression parameters Ac and B c . Typical data on the
efficiency of condensing turbines are found from plots of 0.05
the maximum efficiency, as shown in Fig. 22 (Peterson and 0
Mann, 1985). The regression parameters are derived from 150 200 250 300 350
the data on the figure. By definition, the maximum efficiency Tsat(°C)
is
Fig. 25. Regression parameter Ac as a function of inlet saturation tem-
E max perature (E max 1.5 MW).
is,max = . (A.3)
His M max
Hence
are given in Figs. 23 and 24, respectively. These parameters
E max are in turn approximated by the following expressions:
H is M max
= . (A.4)
is,max
Ac = −0.0896 + 0.0013T sat , (A.6)
E max is the maximum power output of the turbine. For each
potential inlet pressure, the curves of Fig. 22 are represented B c = 1.1752 + 0.0003T sat , (A.7)
by
where the inlet saturation temperature is in ◦ C. However,
E max the above expressions do not give accurate estimates of
His M max = = Ac + B c E max . (A.5) the maximum efficiency when the power output is below
is,max
1.5 MW. More accurate estimates for the efficiency are ob-
Parameters Ac and B c are extracted by regression for each tained by conducting regression below 1.5 MW and above
inlet pressure. The plots of parameters Ac and B c against that 1.5 MW. The two segments’ regression gives efficiency es-
saturation temperature corresponding to the inlet pressure timates within 3% error (Figs. 25–28). The corresponding
Z. Shang, A. Kokossis / Chemical Engineering Science 60 (2005) 4431 – 4451 4449
1.3
150 200 250 300 350 Appendix B. Gas turbine hardware model (GTHM)
Tsat(°C)
The GTHM makes use of basic thermodynamic princi-
Fig. 26. Regression parameter B c as a function of inlet saturation tem-
perature (E max 1.5 MW).
ples and available information for gas turbine equipment.
Fig. 29 illustrates the basic structure of a gas turbine cycle.
The model relates the power output (W ), the total power
0.5
loss of the gas turbine cycle (W loss ), the fuel mass flowrate
(F f ), the fuel temperature (T f ), the air mass flowrate (F a ),
0.4 the air temperature (T a ) and the outlet temperature T out in
0.3
the expression:
Ac
0
Cpa is the specific heat of air, Cp f the specific heat of
150 200 250 300 350 fuel; Cpg the specific heat of flue gas; Hf the specific fuel
Tsat(°C) combustion heat, and W loss mechanical losses, heat loss and
so on.
Fig. 27. Regression parameter Ac as a function of inlet saturation tem- If we define f = F f /F a , Eq. (B.1) becomes
perature (E max 1.5 MW).
1
W= Cp a T a + Cp f T f + Hf
f
1.29 1
− 1+ Cp g T out F f − W loss . (B.2)
1.28 f
1.27 Defining,
Bc
1.26
1
1.25 h = Cp a T a + CP f T f + Hf
f
1.24
1
− 1+ Cp g T out . (B.3)
1.23 f
150 200 250 300 350
Tsat(°C) Eq. (B.2) yields
Fig. 28. Regression parameter B c as a function of inlet saturation tem- W = hF f − W loss . (B.4)
perature (E max 1.5 MW).
The parameters h and W loss depend on the size of the gas
turbine. The electrical efficiency increases with size with
expressions for the regression parameters are indicative dependencies shown in Fig. 30 (Marechal and
for E max < 1.5 MW Kalitventzeff, 1998). The plot illustrates the influence of
turbines size on efficiencies at full load but not on partly
Ac = −0.0981 + 0.001T sat , (A.8) loaded units. The curve fitting of the plot in Fig. 30 yields
the following expression:
B c = 1.2059 + 0.0006T sat , (A.9)
W max
= Ag + B g W max . (B.5)
for E max > 1.5 MW e,max
Ac = −0.0376 + 0.0014T sat , (A.10) The parameters Ag and B g are obtained by conducting re-
gression for the curve in Fig. 30. The resulting values of Ag
B c = 1.1718 + 0.0003T sat . (A.11) and B g are 6.7571 and 2.4381, respectively. But the above
4450 Z. Shang, A. Kokossis / Chemical Engineering Science 60 (2005) 4431 – 4451
Tout W max
e,max = . (B.11)
Hf F f,max
Combustor
It is assumed that
Fa,Ta
W W loss = nW max (B.12)
Compressor Turbine
Wloss n is a constant parameter. According to Eqs. (B.4) and (B.12)
the maximum power output is equal to
Fig. 29. Simple gas turbine cycle.
W max = hF f,max − nW max . (B.13)