INSPECTION QUALITY PLAN Form No.

: MTD-QF-15-07

Rev. No.: 00 Date :02/03/2009

Activity Description Procedure/ Specification Doc. Number Testing Frequency Responsibility Remarks
1 Incoming material Visual inspection As per spec. MTD-QF-15-04 100% QCI
inspection

2 In process stage Fabrication inspection As per drawing MTD-QF-15-02 10% QCI


inspection
Dimensional inspection As per drawing MTD-QF-15-02
Welding inspection ASME Sec. IX AWS D1.1 MTD-QF-15-02 100% QCI

4 NDT DPT/MPI/UT/RT ASME Sec V MTD-QF-03-01 20% TP

5 Leak test Hydro/ pneumatic ASME Sec-VIII DIV 1 MTD-QF-15-06 100% QCI

6 Painting & blasting With DFT meter Drawing / specification MTD-QF-15-05 SA-2.5 QCI

7 Final piping work Visual inspection Drawing / specification MTD-QF-15-02 100% Production

8 Final accessories visual Drawing/ specification MTD-QF-15-02 100% Production


fixing

9 Pre- delivery visual Drawing / specification JOB FILE 100% QCI


inspection

10 Delivery Job file Drawing / specification MTD-QF-15-02 100% Shipping