QUALITY ASSEMBLY PLAN Doc.

No: MTD - QP-01 -01- d


Rev : 0 Date: 03-05-06
Mounting of Brake System

Sl No: Phase Production Quality Specification Frequency Approved Rejected Comments Record Ref
Collect material as per Check against material list
1 Prepration Spot Check
enclosed list and circuit and circuit
Fix emergency and service
Visual check for compliance On Completion of phase
plam couplers
Fix air hose from service
emergency couplers to air Check for hose routing On Completion of phase
hose filters
Fix the load sensing valve
Visual check for compliance On Completion of phase
near the axle
Connect air hose from air
Check for hose routing On Completion of phase
filter to the emergency valve
Fix the Air Tank Visual check for compliance Spot Check
2 Assembly
Connect air hose between
load sensing valve and air Check for hose routing On Completion of phase
tank
Fix the booster on the
bracket provided on the axle Visual check for compliance On Completion of phase
beam
Fix the air hose from the
load sensing valve to the Check for hose routing On Completion of phase
booster
Fix the load sensing valve
lever to the valve and axle Visual check for compliance On Completion of phase
beam
Connect air supply to the
coupler and check for
3 Final On Completion of phase
possible leak in the brake
system

Checked By : ……………………………………………………

Approved By : …………………………………………………..