Professional Documents
Culture Documents
Estimate Dumshar Bazar Kirtinasha River To Sharanga Gov. Primary School Khal
Estimate Dumshar Bazar Kirtinasha River To Sharanga Gov. Primary School Khal
00 km to Km 2.800 =2.800Km in
C/W "Re-excavation of Sureswar Khal & Drainage Project" under Shariatpur O&M Division, BWDB, Shariatpur during the year 2019-20.
C/S at Km 0.000
Pre-work Post-work
Column B
6.00
C/S at Km 0.300 4.00 4.90
2.00
Pre-work Post-work
0.00
-0.49 -0.49
Distance RL Avarage Interval Area Distance RL Avarage Interval Area -2.00
(m) (m) RL (m) distance (m2) (m) (m) RL (m) distance (m2) 0.00 5.00 10.00 15.0
C/S at Km 0.750
Pre-work Post-work
C/S at Km 1.050
Column B
Pre-work Post-work 4.50
4.40
2.50
Distance RL Avarage Interval Area Distance RL Avarage Interval Area 0.50
(m) (m) RL (m) distance (m2) (m) (m) RL (m) distance (m2) -1.50 -0.44 -0.44
0.00 5.36 2.34 0.00 5.00 10.00 15.0
5.00
2.34 5.00 10.50 -0.44 2.28 8.16 18.60
3.00 4.99 5.00 0.66 3.30 13.50 -0.44 -0.44 3.00 -1.32
7.00 2.82 3.91 4.00 15.62 18.66 3.00 1.28 5.16 6.60
9.00 1.81 2.32 2.00 4.63 16.32 23.890
11.00 1.71 1.76 2.00 3.52
14.00 1.93 1.82 3.00 5.46
17.00 2.63 2.28 3.00 6.84
18.66 3.00 2.82 1.66 4.67 N/A= 20.15 Sqm
20.00 3.49
23.00 3.43
16.32 44.04
Column B
6.50
C/S at Km 1.200 4.50
4.50
Pre-work Post-work 2.50
0.50
Distance RL Avarage Interval Area Distance RL Avarage Interval Area -1.50 -0.43 -0.43
(m) (m) RL (m) distance (m2) (m) (m) RL (m) distance (m2) 0.00 5.00 10.00 15.0
0.00 4.89 3.74 4.40
3.00 4.67 11.00 -0.44 1.98 7.26 14.37
3.74 4.40 14.00 -0.44 -0.44 3.00 -1.32
7.00 3.74 4.07 3.26 13.27 19.76 3.40 1.48 5.76 8.52
9.00 2.07 2.91 2.00 5.81 16.02 21.580
11.00 1.46 1.77 2.00 3.53
14.00 1.74 1.60 3.00 4.80
17.00 2.67 2.21 3.00 6.62
19.76 3.40 3.04 2.76 8.38 N/A= 20.82 Sqm
20.00 3.40
23.00 4.57 Column B
6.50
16.02 42.40
4.50
4.60
2.50
0.50
-1.50 -0.43 -0.43
0.00 5.00 10.00 15.0
C/S at Km 1.350
Pre-work Post-work
Distance RL Avarage Interval Area Distance RL Avarage Interval Area
(m) (m) RL (m) distance (m2) (m) (m) RL (m) distance (m2)
0.00 5.55 3.61 4.50
3.00 4.78 11.00 -0.43 2.04 7.40 15.05
3.61 4.50 14.00 -0.43 -0.43 3.00 -1.29
7.00 3.41 3.96 3.40 13.43 19.15 3.00 1.29 5.15 6.61
9.00 2.65 3.03 2.00 6.06 15.54 20.370
11.00 1.57 2.11 2.00 4.22
14.00 2.01 1.79 3.00 5.37
17.00 2.14 2.08 3.00 6.23
19.15 3.00 2.57 2.15 5.51 N/A= 20.44 Sqm
20.00 3.24
23.00 3.51
15.54 40.81 Column B
6.50
4.50
C/S at Km 1.500 2.50 4.00
C/S at Km 1.650
Pre-work Post-work
C/S at Km 1.800
Pre-work Post-work
Distance RL Avarage Interval Area Distance RL Avarage Interval Area
(m) (m) RL (m) distance (m2) (m) (m) RL (m) distance (m2)
Column B
0.00 5.60 5.69 3.80 6.50
4.00 4.52 12.00 -0.41 1.70 6.32 10.70 4.50
2.50 4.50
5.69 3.80 15.00 -0.41 -0.41 3.00 -1.23 3
8.00 3.24 3.52 2.32 8.15 21.02 3.60 1.60 6.02 9.59 0.50
-1.50 -0.40 -0.40
0.00 5.00 10.00 15.00
3
0.50
9.00 2.75 15.33 19.068 -1.50 -0.40 -0.40
3.00 1.00 3.00
0.00 5.00 10.00 15.00
13.00 1.73 2.24 4.00 8.96
16.00 2.04 1.89 3.00 5.66
18.00 2.57 2.31 2.00 4.61
20.00 3.52 3.05 2.00 6.09 N/A= 21.00 Sqm
21.02 3.60 3.56 1.02 3.61
25.00 4.12 15.33 40.07
C/S at Km 1.950
Pre-work Post-work
Distance RL Avarage Interval Area Distance RL Avarage Interval Area
(m) (m) RL (m) distance (m2) (m) (m) RL (m) distance (m2)
0.00 5.61 4.80 4.40 Column B
4.00 4.72 12.00 -0.40 2.00 7.20 14.40 6.50
4.80 4.40 15.00 -0.40 -0.40 3.00 -1.20 4.50
8.00 3.41 3.91 3.20 12.50 20.85 3.50 1.55 5.85 9.07 2.50 3.50
9.00 2.80 3.11 1.00 3.11 16.05 22.268 0.50
13.00 1.83 2.32 4.00 9.26 -1.50 -0.39 -0.39
0.00 5.00 10.00 15.00
16.00 2.21 2.02 3.00 6.06
18.00 2.64 2.43 2.00 4.85
20.00 3.52 3.08 2.00 6.16 N/A= 22.65 Sqm
20.85 3.50 3.51 0.85 2.98
25.00 4.13 16.05 44.91
C/S at Km 2.100
Pre-work Post-work
Column B
Distance RL Avarage Interval Area Distance RL Avarage Interval Area
6.50
(m) (m) RL (m) distance (m2) (m) (m) RL (m) distance (m2)
4.50
0.00 5.65 3.65 4.50 2.50 3.50
3.65 4.50 11.00 -0.40 2.05 7.35 15.07 0.50
4.00 4.52 4.51 0.35 1.58 14.00 -0.40 -0.40 3.00 -1.20 -1.50 -0.38 -0.38
8.00 3.14 3.83 4.00 15.32 19.40 3.20 1.40 5.40 7.56 0.00 5.00 10.00 15.00
9.00 2.14 2.64 1.00 2.64 15.75 21.428
13.00 1.54 1.84 4.00 7.36
16.00 2.21 1.88 3.00 5.63
18.00 2.65 2.43 2.00 4.86
19.40 3.20 2.93 1.40 4.10 N/A= 20.05 Sqm
20.00 3.49 15.75 41.48
25.00 4.10
Column B
C/S at Km 2.250 6.50
4.50
Pre-work Post-work 2.50
0.50 2.20
Distance RL Avarage Interval Area Distance RL Avarage Interval Area -1.50 -0.37 -0.37
(m) (m) RL (m) distance (m2) (m) (m) RL (m) distance (m2) 0.00 5.00 10.00 15.00
C/S at Km 2.550
Pre-work Post-work
Distance RL Avarage Interval Area Distance RL Avarage Interval Area
(m) (m) RL (m) distance (m2) (m) (m) RL (m) distance (m2)
0.00 6.78 11.15 2.20
5.00 5.55 15.00 -0.37 0.92 3.86 3.53
10.00 2.68 18.00 -0.37 -0.37 3.00 -1.11
11.15 2.20 20.51 1.30 0.47 2.51 1.16
15.00 1.80 2.00 3.86 7.71 9.36 3.582
17.00 1.10 1.45 2.00 2.90
20.51 1.30 1.20 3.51 4.21
20.00 1.30
23.00 2.80 N/A= 11.23 Sqm
26.00 6.81
9.36 14.82
C/S at Km 2.700
Pre-work Post-work
Distance RL Avarage Interval Area Distance RL Avarage Interval Area
(m) (m) RL (m) distance (m2) (m) (m) RL (m) distance (m2)
0.00 3.35 3.35 3.40
3.35 3.40 9.00 -0.37 1.52 5.66 8.57
4.00 3.40 3.40 0.66 2.23 12.00 -0.37 -0.37 3.00 -1.11
6.00 2.47 2.94 2.00 5.87 16.31 2.50 1.07 4.31 4.58
8.00 1.45 1.96 2.00 3.92 12.96 12.042
10.00 1.02 1.24 2.00 2.47
12.00 1.20 1.11 2.00 2.22
15.00 2.30 1.75 3.00 5.25
16.31 2.50 2.40 1.31 3.13 N/A= 13.05 Sqm
18.00 2.75
12.96 25.09
C/S at Km 2.800
Pre-work Post-work
Distance RL Avarage Interval Area Distance RL Avarage Interval Area
(m) (m) RL (m) distance (m2) (m) (m) RL (m) distance (m2)
0.00 3.30 4.71 2.50
4.00 2.70 9.00 -0.36 1.07 4.29 4.59
4.71 2.50 12.00 -0.36 -0.36 3.00 -1.08
6.00 2.14 2.32 1.29 2.99 15.84 2.20 0.92 3.84 3.53
8.00 1.42 1.78 2.00 3.56 11.13 7.043
10.00 1.09 1.26 2.00 2.51
12.00 1.25 1.17 2.00 2.34
15.00 2.30 1.78 3.00 5.33
15.84 2.20 2.25 0.84 1.89 N/A= 11.57 Sqm
18.00 2.25 11.13 18.62
Abstract of earth calculation for Re-excavation of Dumshar Bazar Kirtinasha River to Sharanga
Gov. Proimary School Khal 0.00 km to Km 2.800 = 2.800 Km in C/W "Re-excavation of Sureswar
Khal & Drainage Project" under Shariatpur O&M Division, BWDB, Shariatpur during the year 2019-
20.
Volume of
Chainage Net Area Mean Area Distance
SL No. earth Remarks
(Km) (Sqm) (Sqm) (m)
(Cum)
1 0.000 20.38
3 0.150 22.78 21.58 150.00 3236.35
4 0.300 28.06 25.42 150.00 3812.79
5 0.450 24.52 26.29 150.00 3943.32
6 0.600 21.31 22.91 150.00 3436.87
7 0.750 17.98 19.64 150.00 2946.41
8 0.900 20.10 19.04 150.00 2855.67
9 1.050 20.15 20.12 150.00 3018.69
10 1.200 20.82 20.48 150.00 3072.71
11 1.350 20.44 20.63 150.00 3094.85
12 1.500 23.31 21.88 150.00 3281.59
13 1.650 20.21 21.76 150.00 3264.06
14 1.800 21.00 20.61 150.00 3091.15
15 1.950 22.65 21.83 150.00 3273.80
16 2.100 20.05 21.35 150.00 3202.28
17 2.250 12.70 16.38 150.00 2456.27
18 2.400 20.22 16.46 150.00 2469.01
19 2.550 11.23 15.73 150.00 2359.07
20 2.700 13.05 12.14 150.00 1821.08
21 2.800 11.57 12.31 100.00 1231.09
Total= 2800.00 55867.048