Professional Documents
Culture Documents
Design and Implementation of A Hybrid Regenerative Power System Combining Grid-Tie
Design and Implementation of A Hybrid Regenerative Power System Combining Grid-Tie
org
ISSN 1752-1416
Abstract: A hybrid regenerative power system including photovoltaic (PV) and wind powers and combining the
functions of the grid – tie system and uninterruptible power supply (UPS) for critical load applications is
presented. The proposed system employs six-arm converter topology with three arms for the rectifier –
inverter, one arm for battery charging/discharging and two arms for power conversion of the PV module and
wind turbine generator. The operation modes include the grid –tie mode and the UPS mode depending on the
grid status. A power balance control scheme is presented, which can reduce the grid power and utilise the
regenerative power in the most effective way for fulfilling the two requirements of a three-stage charging of
the battery and no interruption of the load. Also, the PV and wind powers can be utilised with priority in
order to provide the flexibility for adapting to local circumstances. A single-phase 1.2 kW/110 V system is
designed and implemented, and the effectiveness of the proposed system and control methodology are
verified with some experimental results.
boost the voltage to a level that is high enough for the rear the UPS mode is activated to avoid a power interruption of
stage DC-to-AC Inverter; otherwise this stage can be the load. In this case, if the total power from the PV and
omitted. A grid – tie hybrid system allowing the injection of WTG is less than the load demand, the battery bank
extra power from the WTG and PV to the grid is shown discharges power to compensate for the gap of total power
in Fig. 1c [7]. In some design cases, the stand-alone and demand from the load as shown in Fig. 2c; this is called
grid – tie configurations are combined as shown in Fig. 1d the discharge mode. If the total power from the PV and
to achieve better operating flexibility [8, 9]. It should be WTG is greater than the load demand and the charging
noted that the load voltage in these two configurations is need from the battery, the WTG has a higher priority to
not regulated and will be floating with the grid voltage. So, remain in its MPP operation and the MPPT control
for the critical load applications, the configuration function of the PV module is stopped as shown in Fig. 2d.
combining on-line uninterruptible power supply (UPS) This is called the partial MPPT mode, whose aim is to
shown in Fig. 1e [10] must be used. Although Burgio et al. ensure a stable DC-link voltage and a balance power flow
[10] have demonstrated the operation and reliability of the between the hybrid generation system and the load. For the
system, detailed converter circuit, control algorithm and same power balance reasons, if just the output power from
power management of the system have not been presented the WTG is higher than the load demand and the
till now. In this paper, we propose a six-arm converter charging need, then the PV module is off and the MPPT
topology with three arms for the UPS rectifier– inverter function of the WTG should also be stopped immediately
and three arms for the PV, WTG and battery to combine as shown in Fig. 2e; this is called the OFF MPPT mode.
the on-line UPS and the grid –tie regenerative power
system. A novel power balance control scheme is presented. In the above partial MPPT mode and OFF MPPT mode,
It is designed so as to reduce the grid power and utilise the the WTG power is designed to be with higher priority than
regenerative power in the most effective way and, most the PV power. There can also be PV power having higher
importantly, to satisfy the two requirements of a three-stage priority. The best design has to consider many factors such
charging of the battery for a high state of charge and no as the daytime, nighttime, the season, the local weather
interruption of the load for high reliability. In addition, the condition, the wind condition and so on. The objective is
utilisation of PV and wind powers can be designed with to utilise the regenerative power in the most effective way
priority. This feature is important for adapting to weather and thus reduce the grid power as much as possible on the
variations and local circumstances to enhance the flexibility premise of ensuring system stability. For example, if the
and performance of the system. The detailed modelling and wind condition is very stable, it is best to have higher
controller design of the converter is provided. A single- priority, since deviating from the MPP of PV is faster and
phase 1.2 kW/110 V system is designed and implemented, easier. On the contrary, if the wind is not consistent but
and the effectiveness of the proposed system and control the PV power is very stable it is better to be with PV
methodology is verified with some experimental results. having higher priority. The priority can be easily switched
if the operation modes are judged with a program. In the
above grid supply mode, the operation can also turn to be
2 Circuit configuration and in grid feed mode if the system is designed to have the
energy storage function at the peak load period of the grid.
operation mode of the proposed
hybrid generation system 2.2 Converter configuration of the
2.1 System description and operating proposed system
modes To achieve the grid – tie and UPS functions and satisfy all
According to the status of the grid, the proposed system can possible operating modes of the proposed hybrid system, a
be divided into the grid – tie mode and the UPS mode. In six-arm power converter topology shown in Fig. 3 is
practical operations, the grid – tie mode and the UPS mode employed in this paper. As shown in Fig. 3, the ABC arms
also can be catalogued into two and three operation modes, constitute a common neutral-line single-phase rectifier –
respectively, based on various conditions of the PV, WTG, inverter [11], whereas the DEF arms are, respectively,
battery bank and the grid. In the grid –tie mode, the PV designed for the power conversions of PV, WTG and the
and WTG are operated at their maximum power point charging/discharging operation of the battery bank. In
(MPP). As shown in Fig. 2a, if the total output power the grid –tie operating mode, the A-arm is used to regulate
from the PV and WTG is higher than the load demand the DC-link voltage and ensure a unity power factor by
and the charging need of the battery bank, the extra power controlling the current of the grid. As the grid failure has
is injected into the grid. This is called the grid feed mode. been detected the A-arm is not operated under the UPS
On the contrary, if the total output power from the PV and operating mode. The C-arm is designed for inverter
WTG is less than the load demand and the charging need operation and controlled to provide the load a low
of the battery bank, the insufficient power is supplied from distorted, sinusoidal voltage all the time. The PV and
the grid as shown in Fig. 2b, this is called the grid supply WTG, respectively, use the D-arm and E-arm to boost
mode. In the case of an abnormal grid condition detected, their terminal voltages up to the designed voltage level of
Figure 2 Continued
d The partial MPPT mode
e The OFF MPPT mode
the DC-link. The F-arm is utilised to control the charging of outer loops are, respectively, dedicated for the DC-link voltage
the battery bank in the grid – tie operation mode and is turned regulation and the AC voltage controller. For designing the
to regulate the DC-link voltage and allow the charging and related controllers, the three-arm mathematical models of
discharging of the battery bank under the UPS operating the rectifier/inverter must be derived first. Based on Fig. 4 the
mode as shown in Figs. 2c – e. equations describing the inductor currents on both the
rectifier and inverter sides can be expressed by Kirhoff’s
3 System modelling and design of voltage law (KVL) as follows
controllers dIs
L ¼ VAN VBN Vs (1)
3.1 Modelling the three-arm rectifier– dt
inverter
dIC
As addressed previously, the control structure shown in Fig. 4 is L ¼ VCN VBN Vo (2)
used for the proposed three-arm rectifier–inverter. The dual dt
loop control strategy is implemented in the design of
controllers for both rectifier and inverter operations. The inner If sinusoidal pulse width modulation (PWM) is employed for
loop is designed for inductor current control, whereas the each of the three arms and the high-order switching terms are
neglected, one can derive the following output voltage equation and inverter currents, the B-arm control voltage can be
assigned as follows
1 vconi
ViN ¼ þ V , i ¼ A, B, C (3) Vo
2 2vtm d vconB ¼ (6)
2kpwm
where vconi is the control voltage of the i-arm (i ¼ A, B, C), and Using (6), (4) and (5) can be rewritten as follows
vtm is the triangular wave amplitude of the PWM. By putting
(3) into (1) and (2), the following voltage equations can be dIs V
L ¼ kpwm vconA þ o Vs (7)
obtained dt 2
dIs V V dI V
L ¼ d vconA d vconB Vs (4) L C ¼ kpwm vconC o (8)
dt 2vtm 2vtm dt 2
dIC V V The kpwm in (6) and (7) can be seen as the voltage gain of the
L ¼ d vconC d vconB Vo (5) converter and has the following form
dt 2vtm 2vtm
Vd
Equations (4) and (5) indicate that both the output currents of kpwm ¼ (9)
2vtm
the rectifier and inverter are affected by the control voltage of the
B-arm (vconB ). To achieve a decoupled control of the rectifier The output current equation of the capacitor on the inverter side
is given by
dVo
Co ¼ IC IL (10)
dt
loop can be obtained and expressed mathematically as follows order ripple in the DC voltage. The average power of the
DC side equals the DC term of the input power on the
is (ks k1 kpwm =L) uR ks k1 kpwm AC side
¼ ¼ , uR ¼ (11)
is s þ (ks k1 kpwm =L) s þ uR L
P AC ¼ PDC (13)
In (11), the uR is the bandwidth of the input current loop and
can be set by k1 . In a normal design criterion, the bandwidth By reflecting the AC current source to the DC side, the
is designed as 1/10– 1/5 of the switching frequency. The equivalent circuit can be obtained as shown in Fig. 6b.
current command (i s) of the rectifier is generated from the Using (13), the following relations can be derived
DC voltage controller Gv by multiplying a synchronous
sinusoidal signal (sin vt) to the control error of the voltage Vs(p) Im
¼ Vd Id (14)
regulating loop. The design of Gv can be accomplished by 2
deriving the small signal model of the DC voltage loop
using Fig. 6a of the unity power factor equivalent circuit. Vs(p) Im
Id ¼ ¼ kDC Im (15)
Due to the fact that the DC-link has connections with 2Vd
other converters and the grid, the DC interface can be
simply modelled by a DC capacitor [12]. The input power The mathematical model of the voltage loop can be
on the AC side is given by formulated by expressing the charging action of Cd by
using the DC current source Id
PAC ¼ Vs(p) sin vt Im sin vt ¼ P AC þ P~ AC2
Vd kDC Vs(p)
Vs(p) Im Vs(p) Im ¼ , kDC ¼ (16)
¼ cos 2vt (12) Im sCd 2Vd
2 2
Figure 6 Modelling of the DC-link voltage control link Figure 7 DC-link voltage controller design
a Power flow on the rectifier side a Voltage control loop
b Equivalent circuit on the DC-link capacitor side b Bode plot of voltage
Using Fig. 7a, the voltage controller Gv can be developed. block diagram of the voltage loop can be simplified and
Because in this design case, the bandwidth of the current shown in Fig. 8b. Based on the same approach, both the
loop is much wider than that of the voltage loop, the feedback and feed forward techniques are used in designing
current loop response of (11) can be simplified as ideal the voltage controller, in which the interference on voltage
(¼1) and the gain of Is/Im is the inverse of current sensing loop caused by the load current is eliminated by the
factor ks . The bode plot of the voltage loop HDC is feedback signal of load current. The response of the voltage
presented in Fig. 7b. As addressed previously, the DC control loop can be derived from Fig. 8b as follows
voltage contains the second-order harmonics. Therefore it
is necessary to design the bandwidth of the voltage loop to vo (kv k3 =ks C) uv
¼ ¼ (18)
be much lower than 120 Hz to reduce the second-order vo s þ (kv k3 =ks C) s þ uv
voltage ripple. In this paper, the type II compensator
(PI þ Low-Pass) is used in designing Gv . For comparison In (18), the uv is the bandwidth of the voltage loop and can be
purposes, the close-loop response of using PI control is also directly calculated as uI/4 and set by k3 .
shown in Fig. 7b.
performing the power balance function, the battery-arm still handled by a criterion considering the balance of the
takes care of the battery charging. The power balance control system power and the security of the WTG system. To
function is achieved by connecting the output of the charging have a clear picture of the proposed energy arrangement
controller to a number of limiters to obtain the control signals concepts, Figs. 2c – e depict three typical operating
of VL1 and VL2 used by MS1 and MS2 under this operating conditions. In Fig. 2c, the maximum output power from
mode. As stated in the previous section, in the UPS operating the PV and WTG is not enough for the load demand;
mode, the function of MPPT used in the PV and WTG is thus the battery bank is discharging to support the DC-
link voltage and to cover the power gap of load demand. in Fig. 9b. To achieve the above functions, the braking
Because charge current (Ib) in Fig. 9 is negative, the output control unit possesses a constant power controller and a
of the charge controller will be positive and will be limited constant speed controller. The constant power controller
by the positive limiter of the power balance controller. VL will produce a control voltage of the PWM aimed to limit
will be zero and thus VL1 ¼ VL2 ¼ 0; as a result, both the maximum output power of the WTG as the wind
voltages calculated from the MPPT controllers of the PV speed is too high. The constant speed controller will
and WTG will not change. PV and WTG will operate at produce a control voltage of the PWM aimed to regulate
their MPP voltages. the WTG voltage in order to limit the rotor speed for
preventing attainment of the cut-off speed at the normal
As shown in Figs. 2d and e, when the output power of the wind speed. It should be noted that because of the boost
PV module and WTG is sufficient for supplying the load topology of the WTG arm, the WTG voltage will be
demand and the need of charging the battery bank, the limited by the DC-link voltage and the WTG speed will
battery-arm is controlled to support the DC voltage at a thus be limited. If the cut-off speed is set such that its
preset value via charging the battery bank. Before the corresponding WTG voltage is larger than the DC-link
charging current (Ib) can reach its command (I b) in voltage, the cut-off speed will not be reached except that
Fig. 9a, the output of the charge controller will still be the braking resistor does not have enough capability to
positive and be limited by the positive limiter of the power absorb the OFF MPPT energy such that the DC-link
balance controller. As a result the limiting voltage will be voltage is raised to the cut-off voltage.
VL ¼ VL1 ¼ VL2 ¼ 0, PV and WTG will thus operate at
their MPP voltages. When the charge current (Ib) can
attain the charge current command (I b) in Fig. 9a, VL will
3.4 Design of input voltage controllers for
be negative. If VL is not negative enough to reach the limit the PV and WTG converters
of the negative limiter, VL ¼ VL1 and VL2 ¼ 0. VL1 will Due to that fact that the same control structure and design
increase the voltage command calculated by the PV MPPT method can be used for developing the related voltage
controller but VL2 will not change the voltage command controllers used in the PV and WTG, in this subsection, only
generated by the WTG MPPT controller. Therefore the the design details concerning the PV module are addressed.
PV module will deviate from its MPP and WTG still stay In this particular application case, the voltage to be regulated
at MPP as shown in Fig. 2d. On the contrary, if VL is is on the input side of the converter rather than the voltage at
negative enough to reach the limit of the negative limiter, its output terminal. To design the voltage controller, the
VL ¼ VL1 and VL2 ¼ VL 2 VL1 = 0, then VL1 and VL2 will transfer function describing the input voltage and the
increase the voltage command calculated by the MPPT controlled voltage must be derived first. The designed
controllers of PV and WTG. The limit level of the converter system can be treated as a boost-type converter as
negative limiter is set such that the PV module can attain shown in Fig. 10, in which the outputs of PV or WTG are
its open circuit voltage such that the PV module output modelled as a current source. Although the PV module
power is zero and the load power and battery charge power characteristic is equivalent to a voltage source in series with a
are all supplied by the WTG as shown in Fig. 2e. It should resistance near the MPP as well as the negative dP/dVp
be noted that the operating point of the PV and WTG can region, it can also be equivalent to a current source like the
be shifted to the negative slope region or the positive slope positive dP/dVp region by employing Norton’s theorem. As
region of the power curve at the OFF MPPT mode. The for the WTG, the large stator inductance and low rotating
negative slope region in the power curve is a nature- speed make the three-phase rectified current slow-varying and
unstable region. Shifting of the operating point to this continuous and it also can be seen as a current source in
region should ensure stability by closed-loop control. modelling the converter, the switching frequency of which is
However, the negative slope region has the significant much higher than that of the current variation.
advantage of higher voltage, which is beneficial in converter
efficiency for the voltage step-up applications. Therefore
the operating point in this paper is designed to be the
negative slope region in the OFF MPPT mode of the PV
and WTG. The stability in this region is controlled
through the voltage loop control of WTG and PV. The
only problem in this region is that the WTG may
experience an over-speed situation as the wind speed is
increased too much at the OFF MPPT mode. As a result,
the system is equipped with a chopper and a braking
control unit to control the braking resistor with PWM to
dissipate the excessive energy. In addition, the chopper and
braking resistor should also be active as the wind speed is
too high in order to limit the maximum power of the
WTG. The active region of the braking resistor is shown Figure 10 Designed boost-type converter
Vp ¼ (1 D)Vd (22)
Ip ¼ Ii (23)
Applying a small disturbance to (19) –(21) and using Figure 11 Design of the input voltage controller for PV and
linearisation techniques, one can have the small signal WTG
model of the converter formulated as follows a Control block diagram
b Frequency response of the input voltage control loop
dI~ i
L ¼ V~ p þ Vd D
~ (24)
dt the incremental conductance method for PV and the
hill-climb searching (HCS) method for WTG. Let us take
dV~
C ¼ I~ i (25) the PV module as an example to address the control
dt actions of the proposed MPPT. Fig. 12a shows the P–V
dV~ characteristic of the PV module used. In the positive slope
Re C þ V~ ¼ V~ p (26) region (dP/dVp . 0) the operation voltage needs to
dt
increase. On the other hand, in the negative slope region
By applying the Laplace transformation to (24) – (26), the (dP/dVp , 0) the operation voltage needs to decrease. In
transfer function of input voltage of the converter to the this study, the MPPT controller is implemented in
control duty can be obtained as expressed in (27) MATLAB real-time control as shown in Fig. 12b.
To avoid possible slope calculation error induced by the
V~ p (Re Vb =L)(s þ (1=CRe )) voltage and current ripples, a fourth-order moving
¼ 2 (27) average filter is used. As can be seen from Fig. 12b, the
D~ s þ (Re =L)s þ (1=LC)
amount of change and the direction of the voltage
Based on (27), the block diagram showing the related command after each sampling time are decided by
multiplying DP/DVp and Gain 1 and working with a
parameters of the voltage controller is presented in
Fig. 11a. The Vt is the amplitude of the sawtooth limiter (limiter 1). This voltage control signal with
waveform and kv is the voltage sensing factor. It should be direction information is accumulated with a memory cell
and operated with a gain factor (Gain 2) to adjust the
noted that there is a minus sign in (27); therefore the
designed PI controller with a positive feedback path is used control voltage within a proper range. The summation of
here as shown in Fig. 11a. The related parameters of the this control voltage and a given initial voltage (init voltage)
passes through a limiter (Limiter 2) to generate the final
controller can be decided after a proper crossover frequency
is given as shown in Fig. 11b. voltage command.
The HCS method of the WTG in the proposed paper also braking resistor 33 V, PWM chopping frequency 5 kHz,
employs the same MPPT controller shown in Fig. 12b as the PWM actives at Pwtg . 1 kW or Vg . 195 V (a little lower
PV module, except that the sampling time is longer than the DC-link voltage), cut-off voltage Vg ¼ 240 V.
to consider the WTG having a larger mechanical time
constant. HCS is designed to work below the rated wind 4. Control and switching frequency of the converter:
speed condition. As at over wind speed condition, the 20 kHz, PWM.
WTG would be charged to be constant power control.
5. Battery bank: 10 12 V with the rated charging current
of 4 A.
4 Experimental test and
verification 6. MPPT sampling frequency: PV 500 Hz, WTG 50 Hz.
To verify the feasibility and effectiveness of the proposed
hybrid generation system and the designed controllers, a The typical experimental results are shown in Figs. 14–17.
110 V/60 Hz, 1200 W experimental system is constructed For testing the dynamic response of the system, Fig. 14a shows
as shown in Fig. 13. The details of the experimental system the measured results in the UPS mode with a step load (pure
are briefed as follows: resistor load) change from 1260 to 117 W and the maximum
charging current is set as 2 A. It can be seen from Fig. 14a that
1. DC-link voltage: 200 V. before and after the change of load demand, both the PV and
the WTG are operating around their MPP, that is, 348 W
2. PV module: 4 150 W. (Ppv) at 127 V for the PV module and 733 W (Pwtg) at
165 V for the WTG. At the very beginning, the total
3. WT generator: PMSM-type WTG rated at 740 W, output power of the PV and the WTG is lower than the
162 V, emulated with a close-loop controlled M-G set, load demand; thus the battery bank is discharging with a Pch
Figure 14 Measured results in the UPS mode with a step Figure 15 Measured results of mode change from the
load change grid – tie mode to the UPS mode at heavy load
of 253 W to compensate for the insufficiency in supplying the respectively, Ppv ¼ 2 W and Pwtg ¼ 388 W (about 195 V).
load demand. When the load demand is reduced to 117 W, The load voltage and current waveforms are shown in
the total output power of the PV and the WTG is higher Fig. 14b to verify the performance of the related controllers.
than the sum of the load demand (PLoad ¼ 117 W) and the Observing the transient period, the fast response of the
charging power (Pch ¼ 242 W); thus the MPPT controller proposed system can be found from the waveforms of
of the PV module is stopped first followed by the WT Fig. 14a, in which the MPPT response speed is fast and the
generator as planned. After quitting the MPPT functions, DC-link voltage, PV voltage and WTG voltage are well
the measured output power of the PV and WTG are, regulated. Although there is some overshoot in the response
change is large in the battery-arm. This paper employs the [5] VALENCIAGA F., PULESTON P.F.: ‘Supervisor control for a
current limitation to suppress this phenomenon. A better stand-alone hybrid generation system using wind and
solution is to add a current loop to improve the power photovoltaic energy’, IEEE Trans. Energy Convers., 2005,
change response, which will be done in the future improved 20, (2), pp. 398– 405
version.
[6] GIRAUD F., SALAMEH Z.M.: ‘Steady-state performance of a
5 Conclusion grid – tie rooftop hybrid wind – photovoltaic power system
with battery storage’, IEEE Trans. Energy Convers., 2001,
This paper has investigated a hybrid generation system 16, (1), pp. 1– 7
consisting of wind, PV and battery storage energy modules
designed to supply continuous and high-quality power to [7] CARRASCO J.M., FRANQUELO L.G. , BIALASIEWICZ J.T., ET AL .:
critical loads. A versatile energy management and control ‘Power-electronic systems for the grid integration of
scheme has been presented to determine the operation renewable energy sources: a survey’, IEEE Trans. Ind.
mode of the hybrid generation system and to improve the Electron., 2006, 53, (4), pp. 1002 – 1016
overall controllability and flexibility. The dynamic analysis
of various models of the system components and the [8] ORTJOHANN1 E., OMARI O., LINGEMANN M., ET AL .: ‘An online
design of related power controllers are addressed in detail. control strategy for a modular dc coupled hybrid power
The feasibility and performance of the proposed hybrid system’. 2007 European Conf. Power Electronics and
generation system operated by the designed controllers are Applications, 2 – 5 September 2007, pp. 1 – 10
verified with a series of tests and the measured results on
a 110 V/60 Hz, 1200 W experimental system. The proposed [9] KIM S.K., JEON J.H., CHO C.H., AHN J.B., KWON S.H.: ‘Dynamic
hybrid system can also be extended to the three-phase modeling and control of a grid – tie hybrid generation
system just by replacing the three-arm rectifier–inverter with system with versatile power transfer’, IEEE Trans. Ind.
the three-phase rectifier and the three-phase inverter. Electron., 2008, 55, (4), pp. 1677 – 1688
6 References [10] BURGIO A., MENNITI D. , PINNARELLI A., SORRENTINO N.: ‘The
reliability evaluation of a power system in presence of
[1] NEHRIR M.H. , LAMERES B.J. , VENKATARAMANAN G. , GEREZ V. ,
photovoltaic and wind power generation plants and UPS’.
ALVARADO L.A. :
‘An approach to evaluate the general The Ninth Int. Conf. Electrical Power Quality and
performance of stand-alone wind/photovoltaic generating Utilisation, 9– 11 October 2007, pp. 1 – 6
systems’, IEEE Trans. Energy Convers., 2000, 15, (4),
pp. 433– 439 [11] CHIANG S.J., LEE T.S., CHANG J.M.: ‘Design and
implementation of a single-phase three-arms rectifier –
[2] NEHRIR M.H., WANG C., GUDA S.R.: ‘Alternative energy inverter’, IEE Proc. Electric Power Appl., 2000, 147, (5),
distributed generation: need for multi-source operation’. pp. 379– 384
38th North American Power Symp. (NAPS), 2006,
pp. 547– 551 [12] ERICKSON W.R.: ‘Fundamental of power electronics’
(Kluwer Academic Publisher (KAP), 2001)
[3] WANG L. , LIN T.J.: ‘Stability and performance of an
autonomous hybrid wind-pv-battery system’. Int. Conf. [13] WASYNCZUCK O.: ‘Dynamic behavior of a class of
Intelligent Systems Applications to Power System (ISAP), photovoltaic power system’, IEEE Trans. Power Appar.
2007, pp. 1 – 6 Syst., 1983, 102, (9), pp. 3031 – 3037
[4] VALENCIAGA F., PULESTON P.F.: ‘Supervisor control for a [14] WANG Q., CHANG L.: ‘An intelligent maximum power
stand-alone hybrid generation system using wind and extraction algorithm for inverter-based variable speed
photovoltaic energy’, IEEE Trans. Energy Convers., 2005, wind turbine systems’, IEEE Trans. Power Electron., 2004,
20, pp. 398 – 405 19, (5), pp. 1242– 1248