Smartplant Electrical Installation & Configuration Checklist
Smartplant Electrical Installation & Configuration Checklist
Installation of this version is from a DVD or a set of files downloaded from Intergraph's eCustomer web site.
Unless otherwise specified, the topics listed in the Documentation Reference column can be found in the SmartPlant Electrical Installation Guide.
The checklist below applies to the standalone installation of SmartPlant Electrical. For guidelines about using SmartPlant Electrical in an integrated
environment, see the SmartPlant Foundation Installation and Configuration Checklist.
Note: To run SmartPlant Electrical you must connect to a site and plant that were created using SmartPlant Engineering Manager. A plant created in
SmartPlant Engineering Manager with the SmartPlant Electrical application associated is a prerequisite for being able to use SmartPlant Electrical.
Task
Component or Tool Step Description / Software Version Details Documentation Reference Setup Notes
Number
Install Database Software or verify that the Supported Database Platforms: See SmartPlant Engineering Manager
installed software is compatible with * Microsoft SQL Server 2012 Installation and Upgrade Guide:
* Oracle Database 11g R2 (11.2.0.4), 64-bit (Standard or Enterprise) Installing and Configuring Oracle or
2.0 Database Platform SmartPlant Electrical Database Server
Installing and Configuring Microsoft
recommendations SQL Server
Installation of this version is from a DVD or a set of files downloaded from Intergraph's eCustomer web site.
Unless otherwise specified, the topics listed in the Documentation Reference column can be found in the SmartPlant Electrical Installation Guide.
The checklist below applies to the standalone installation of SmartPlant Electrical. For guidelines about using SmartPlant Electrical in an integrated
environment, see the SmartPlant Foundation Installation and Configuration Checklist.
Note: To run SmartPlant Electrical you must connect to a site and plant that were created using SmartPlant Engineering Manager. A plant created in
SmartPlant Engineering Manager with the SmartPlant Electrical application associated is a prerequisite for being able to use SmartPlant Electrical.
Task
Component or Tool Step Description / Software Version Details Documentation Reference Setup Notes
Number
Verify that the network can be accessed Supports Internet Protocol IPv4 only
1.1 Operating System
Install SmartPlant Electrical Reference Data Delivered on the SmartPlant Electrical Installation DVD. To launch the Configuring Reference Data for Microsoft .Net Framework 4.0 is
SmartPlant Electrical setup, click the 'Additional Software' link on the SmartPlant Electrical SmartPlant Electrical > Install required for Reference Data
3.0 Installation Wizard 'Welcome' page and then click the 'SmartPlant SmartPlant Electrical Reference Data installation
Installation DVD
Electrical Reference Data' link.
SmartPlant Electrical
Installation & Configuration Checklist
Software Version: 2015 (07.00.00) (SmartPlant Engineering Manager 2014 R1)
Installation of this version is from a DVD or a set of files downloaded from Intergraph's eCustomer web site.
Unless otherwise specified, the topics listed in the Documentation Reference column can be found in the SmartPlant Electrical Installation Guide.
The checklist below applies to the standalone installation of SmartPlant Electrical. For guidelines about using SmartPlant Electrical in an integrated
environment, see the SmartPlant Foundation Installation and Configuration Checklist.
Note: To run SmartPlant Electrical you must connect to a site and plant that were created using SmartPlant Engineering Manager. A plant created in
SmartPlant Engineering Manager with the SmartPlant Electrical application associated is a prerequisite for being able to use SmartPlant Electrical.
Task
Component or Tool Step Description / Software Version Details Documentation Reference Setup Notes
Number
Verify that the network can be accessed Supports Internet Protocol IPv4 only
1.1 Operating System
Microsoft .NET Framework 4.0 and 4.5 Microsoft .Net Framework 4.0 is required for launching the setup.exe file Loading SmartPlant Electrical If not already installed when
for SmartPlant Electrical and for connectivity when installing Oracle Prerequisite Software installing SmartPlant Electrical,
Client. It must be installed before installing Oracle Client. .NET Framework 4.0 will be
installed with the SmartPlant
Microsoft .Net Framework 4.5 is required for working with SmartPlant Electrical Setup.
Electrical.
1.2 .NET Framework If Oracle Client was already
installed prior to installing .NET
Framework 4.5 Extended, refer to
the Installation Guide under the
section: 'Before You Install' >
'Loading SmartPlant Electrical
Prerequisite Software'
SmartPlant Electrical
Installation & Configuration Checklist
Software Version: 2015 (07.00.00) (SmartPlant Engineering Manager 2014 R1)
Installation of this version is from a DVD or a set of files downloaded from Intergraph's eCustomer web site.
Unless otherwise specified, the topics listed in the Documentation Reference column can be found in the SmartPlant Electrical Installation Guide.
The checklist below applies to the standalone installation of SmartPlant Electrical. For guidelines about using SmartPlant Electrical in an integrated
environment, see the SmartPlant Foundation Installation and Configuration Checklist.
Note: To run SmartPlant Electrical you must connect to a site and plant that were created using SmartPlant Engineering Manager. A plant created in
SmartPlant Engineering Manager with the SmartPlant Electrical application associated is a prerequisite for being able to use SmartPlant Electrical.
Task
Component or Tool Step Description / Software Version Details Documentation Reference Setup Notes
Number
Install Database Client Software or verify Supported Database Client: Hardware and Software The client database software must
that the installed software is compatible * Oracle 11g R2 Client (11.2.0.4), 32-bit Recommendations > SmartPlant be of the same version as the
Electrical Workstation server database software.
with SmartPlant Electrical Database Server For SQL Server, no client installation is required.
recommendations Oracle 32-bit Client is required for
2.0 Database Platform both 32-bit and 64-bit Oracle
databases.
Installation of this version is from a DVD or a set of files downloaded from Intergraph's eCustomer web site.
Unless otherwise specified, the topics listed in the Documentation Reference column can be found in the SmartPlant Electrical Installation Guide.
The checklist below applies to the standalone installation of SmartPlant Electrical. For guidelines about using SmartPlant Electrical in an integrated
environment, see the SmartPlant Foundation Installation and Configuration Checklist.
Note: To run SmartPlant Electrical you must connect to a site and plant that were created using SmartPlant Engineering Manager. A plant created in
SmartPlant Engineering Manager with the SmartPlant Electrical application associated is a prerequisite for being able to use SmartPlant Electrical.
Task
Component or Tool Step Description / Software Version Details Documentation Reference Setup Notes
Number
Required for reading the print documentation delivered with the software Hardware and Software
Recommendations > SmartPlant
4.2 PDF Reader Electrical Workstation > Software
Prerequisites
Microsoft Excel (32-bit only) from Office 2010, SP1 Microsoft Excel is required for working with report templates and Hardware and Software
or generating reports. Recommendations > SmartPlant
4.4 Microsoft Office Office 2013 Service Pack 1 (32-bit only) Electrical Workstation > Software
Prerequisites
Citrix XenDesktop 7.0 RDS on Windows Server 2008 Needed for working in a thin-client environment Hardware and Software
R2 Service Pack 1, 64-bit (Standard or Enterprise) Recommendations > SmartPlant
4.5 Citrix Electrical Workstation > Optional
Software
Autodesk AutoCAD 2014 Used for viewing files generated using the 'Save As' feature Hardware and Software
Recommendations > SmartPlant
4.6 AutoCAD Electrical Workstation > Optional
Software
Bentley MicroStation J (not certified on Vista, Windows Hardware and Software
7, or a 64-bit machine) Recommendations > SmartPlant
4.7 MicroStation Electrical Workstation > Optional
Software
Visual Studio 2012 or 2013 Used for API Hardware and Software
Integrated Development Recommendations > SmartPlant
4.8 Electrical Workstation > Optional
Environment (IDE)
Software
SmartPlant Electrical
Installation & Configuration Checklist
Software Version: 2015 (07.00.00) (SmartPlant Engineering Manager 2014 R1)
Installation of this version is from a DVD or a set of files downloaded from Intergraph's eCustomer web site.
Unless otherwise specified, the topics listed in the Documentation Reference column can be found in the SmartPlant Electrical Installation Guide.
The checklist below applies to the standalone installation of SmartPlant Electrical. For guidelines about using SmartPlant Electrical in an integrated
environment, see the SmartPlant Foundation Installation and Configuration Checklist.
Note: To run SmartPlant Electrical you must connect to a site and plant that were created using SmartPlant Engineering Manager. A plant created in
SmartPlant Engineering Manager with the SmartPlant Electrical application associated is a prerequisite for being able to use SmartPlant Electrical.
Task
Component or Tool Step Description / Software Version Details Documentation Reference Setup Notes
Number
Delivered on the SPLM Installation CD: Hardware and Software
* SPLM 2012 (12.00) Recommendations > SmartPlant
Electrical Workstation > Software
Prerequisites
License Manager
4.9 Install SmartPlant License Manager 2012
Installation CD Installing the Software > Install
SmartPlant Electrical