Peshawar Sustainable Bus Rapid Transit
Corridor Project – Project Management and
Construction Supervision Consultants
(PMCSC)
This document is issued for the party which commissioned it We accept no responsibility for the consequences of this
and for specific purposes connected with the above-captioned document being relied upon by any other party, or being used
project only. It should not be relied upon by any other party or for any other purpose, or containing any error or omission
used for any other purpose. which is due to an error or omission in data supplied to us by
other parties
Table of Contents
Summary.....................................................................................................................8
1 Introduction........................................................................................................10
2 Scope of Works....................................................................................................11
List of Tables
Table 2-1 Status of Key Contractual Obligations....................................................................................................11
Table 3-1 Site Meetings.......................................................................................................................................... 12
Table 3-2 Environment Meetings............................................................................................................................12
Table 3-3 H&S Meetings......................................................................................................................................... 12
Table 3-4 Material Delivered on site (Please add the material as per requirement)...............................................13
Table 3-5 Number of contractor staff Lot-II (Insert Rows if required).....................................................................13
Table 3-6 Equipment and Vehicles deployed by the Contractor (Insert Rows if required).....................................14
Table 3-7 Bus Parking Area Works status (Insert Rows if required)......................................................................15
Table 3-8 Status of work on Boundary Wall (Insert Rows if required)....................................................................15
Table 3-9 Progress at Workshop (Insert Rows if required).....................................................................................16
Table 3-10 Progress at Park & Ride (Insert Rows if required)................................................................................16
Table 3-11 Progress on Office Bulidings (Insert Rows if required).........................................................................17
Table 3-12 Progress on Drainage (Insert Rows if required).....................................Error! Bookmark not defined.
Table 3-13 Electric Work Progress (Insert Rows if required)..................................................................................18
Table 3-14 Number of Site Instructions..................................................................................................................21
Table 3-15 Number of Site Inspections..................................................................................................................21
Table 3-16 Laboratory Test Lot II...........................................................................................................................22
Table 3-17 Financial Profile Lot II (PKR in Millions)...............................................................................................22
Table 3-18 Number of Grievances Received and Redressed................................................................................22
Table 4-1 Overall number of staff deployed up to 31st January 2019 (Lot II & Cross Cutting)...............................29
Table 4-2 Correspondence with Client and Contractor...........................................................................................29
Table 4-3 Consultant Invoicing Status (Local Currency)........................................................................................30
Table 4-4 Consultant Invoicing Status (Foreign Currency).....................................................................................30
Table of Figures
Figure 0-1 Lot II Buildings Location..........................................................................................................................9
Summary
1 Introduction
2 Scope of Works
The major developments related with design changes and design adjustments happened during the
reporting months, are presented hereunder. (The detailed inventory of the design changes is provided
as Annex VI)
2.3 Contractual obligation status and Contract variations during January 2019
Please also provide the list of variation orders issued in Annex VIII
3 Monthly Progress:
3.2 Activities.
Table 3-5 Material Delivered on site (Please add the material as per requirement)
Sr. No. Material Categories Unit Actually Delivered (Quantity)
1 Steel Tons 58
2 Cement Tons 225.687
3 Concrete A2 m3 107
4 Concrete A3 m3 250
5 Lean Concrete m3 60
6 Backfilling Material ft3 3000
7 Bricks Number 12000
9 Sand for Plaster ft3 829
Table 3-7 Equipment and Vehicles deployed by the Contractor (Insert Rows if required)
Added Removed
Sr. By the end of By the end of
Equipment Category in Feb in Feb
No. Jan 2019 Feb 2020
2020 2020
1 Transits Mixer 4 2 2
2 Grader 1 1
3 Tractor 1 1 0
4 Batching Plant 1 1
5 Roller 1 1
6 Compactor 0 0
7 Generator 1 1 2
8 Vibrator 2 2
9 Water Pump 1 1 2
10 Welding Plant 2 2
11 Excavator 1 1 0
12 Loader 2 1 1
13 Cutting tools 1 1 0
14 Concrete pump 1 1 0
15 Double Cabins 1 2 3
16 Water tanker 2 2
17 Cranes 5 to 10 tons 0 0
18 Cranes 25 to 50 tons 0 0
19 Dumper 0 0
20 Asphalt Cutter 0 0
21 Total Station 1 1
22 Level machine 2 1 1
23 Ambulance 1 1 0
24 Jack Hammers 0 0
25 Boring Machines 0 0
26 Flat body Trolleys 0 0
27 Tower Lights 0 0
28 Steel bending Machines 2 2 0
29 Steel Cutting Machines 2 2 0
30 Steel sheet rolling Machines 0 0
31 Auger Machine 0 0
32 Rebar Cutting Machine 2 2
33 Rebar Bending Machine 2 2
34 Concrete Batching Plant 1 1
3.5.3 Workshop
2
2,049.3
Emulsion Paint M2 2,105.00 2,049.35 97.36%
5
Overall percentage Achievement (Rest Area)
Building
UPVC Pipe 25mm Electrical
m 12246 12246 12246 100%
Conduit 0
UPVC Pipe 150mm class D M 653 653 0 653 100%
UPVC Pipe 100mm class B M 6250 4250 2000 6250 100%
3.5.13 U.G.W.T/O.H.W.T
Table 3-20 UGWT/OHWT Progress
%
Total Quantity Executed by Executed
Total Achieved
Work Activity Unit Planned in the the end of in Feb
Executed by 29th
project Jan 2020 2020
Feb 2020
Internal Roads
Excavation of unsuitable Material CM 11,119.69 11,119.69 11,119.69 100.00%
Granular Filling (River Bed
M3 8,630.99 8,630.99 8,630.99 100.00%
Material)
Granular Sub-Base CM 4,076.48 4,076.48 4,076.48 100.00%
Aggregate Base Course CM 3,627.15 3,627.15 3,627.15 100.00%
Plain cement Concrete(Lean
CM 1,660.00 1,660.00 1,660.00 100.00%
concrete)
Rigid Pavement floor 1:2:4 CM 3,903.00 3,846.42 24.00 3,870.42 99.17%
Dowels with PVC Pipe Each 3,374.68 3,329.91 16.87 3,346.78 99.17%
Steel Welded Mesh in Rigid
M2 11,242.00 11,035.34 56.21 11,091.55 98.66%
Pavement
TUFF TILES M2 2,400.00 2,018.00 240.00 2,258.00 94.08%
Kerb stone (18''x6'') M 4,184.28 3,447.42 418.43 3,865.85 92.39%
Bus Station 00 & Rest/ Toilet
Block
BS STRUCTURAL STEEL WORKS SM 2,500.00 2,495.00 2,495.00 99.80%
The table below shows the financial profile of the contractor at Buildings Lot-II.
3.10 Resettlement
3.10.2 Gender
Following major developments took place during the reporting months
3.10.3 Social
Following major developments took place during the reporting months
Table 4-25 Overall number of staff deployed up to 31th October 2019 (Lot II & Cross Cutting)
Overall
Categories Number
Key Experts
Technical Support Team
Administration
Staff deployed at the Reaches
Total
Staff working Across all the Lots and Reaches
Key Experts
Technical Support Team
Administration
Total
Staff Deployed Exclusively at Lot-II
Staff deployed at Lot-II
Please provide the detailed list of the deployed staff and dated in organogram in Annex III
The activities of the M&E team carried out during the reporting period include:
The tables below provide the financial status of the consultant in the local and foreign currencies.
Annex III: List of deployed staff by the Consultant with dated organogram