Rajesh is on leave from his MBA course and he is visiting his parents who
operate a small bed and breakfast hotel. In the hotel there are 10 guests who
have ordered 50 pairs of toast bread. Rajesh has a cassette-deck type toaster
that can toast two slices at a time. Each slice must be toasted for exactly 20
seconds before it is taken out.
Rajesh is contemplating when he must get up if he has to deliver these 50 pairs
of toasts at 7.00 am. Given below is a sequence of operations with the duration
for each operation.
a) Assuming that Rajesh can not open or close both the doors simultaneously
with two hands, can you suggest a better way of finishing the job in less than 40
minutes?
b) Assuming that Rajesh can open or close both doors simultaneously and
place or remove two slices using both his hands, what is the best you think
Rajesh can do?
Page 2 of 4
Original
Person Machine - Door 1 Machine - Door 2 Toaster
Duration Transport/ Transport/ Transport/ Transport/
Sr Activity (sec) Repeat Operation Delay Operation Delay Operation Delay Operation Delay
A1 Get Bread 30 N 30 0 30 30 30
A2 Switch on the Toaster 5 N 5 0 5 5 5
A3 Wait for Toaster to heat 30 N 30 30 0 30 0 30 0
B1 Open Door 1 2 Y 2 0 2 2 2
B2 Place Slice in Cavity 1 5 Y 5 0 5 5 5
B3 Close Door 1 2 Y 2 0 2 2 2
B4 Open Door 2 2 Y 2 0 2 0 2 2 0
B5 Place Slice in Cavity 2 5 Y 5 0 5 0 5 5 0
B6 Close Door 2 2 Y 2 0 2 0 2 2 0
B7 Wait for Slice-1 to be toasted 11 Y 11 11 0 11 0 11 0
B8 Open Door 1 2 Y 2 0 2 2 0 2 0
B9 Pull Slice from Cavity 1 & Place in Tray 5 Y 5 0 5 5 0 5 0
B10 Wait for Slice-2 to be toasted 2 Y 2 2 2 0 2 0
B11 Open Door 2 2 Y 2 0 2 2 2
B12 Pull Slice from Cavity 2 & Place in Tray 5 Y 5 0 5 5 5
B13 Close Door 1 2 Y 2 0 2 2 2
B14 Close Door 2 2 Y 2 0 2 2 2
B15 Cut the two toasts 5 Y 5 0 5 5 5
C1 Switch Off the Toaster 5 N 5 0 5 5 5
Total 2770 2090 680 1030 1740 1030 1740 1480 1290
Total 1853 1168 685 1030 823 1030 823 1130 723
Total 1749 964 785 1030 719 1030 719 1030 719