Professional Documents
Culture Documents
Ml14191a459 PDF
Ml14191a459 PDF
&
LIK2096
F07090284 9006.29
PDR ADOCK 05000261
P' PD r:
EFFECTS OF REMOVING THE
TURBINE REDUNDANT OVERSPEED TRIP SYSTEM
AT H. B. ROBINSON UNIT 2
(Revised June 1989)
Contents
Section Pace
A. Purpcse of Study
8. Summary anc Conclusions
C. BacKgrounc and Description of TROTS 2
D. Analysis and Methodology 4
E. Discussion of Results a
F. References C
G. Addenaum 1 -7
499x: 1C.3O2S9
List of Tables
Table
Number Title Paqe
23 - 32
Figure 1: Destructive Overspeed Fault Tree, H. B. Robinson Unit 2
0499x:1 0/070789
A. Purpose of Study
04
99x: 10/070689 1
well below the criterion of 105 per year. Therefore,
a
probabilistic basis is established which
supports the current Robinson
test intervals of the mechanical overspeed trip
mechanism, overspeed
protection controller, electrical solenoid
trip mechanism, and turbine
valves.
0499x:1 0/070789
2
issue of turbine missile damage, the design of a new trip system that would
meet the most stringent criteria for nuclear protection systems was judged to
be a prudent and satisfactory solution.
0499x:10/070689 3
TROTS has three speed detectors at the generator end of the
turbine that send
speed signals to three separate conditioning and logic circuits.
The
conditioning and logic sections of the system send a
continuous output signal
to the coils of six hermetically sealed overspeed detection
relays as long as
the turbine speed is less than 111 percent. In the event
that the TROTS
overspeed setpoint of 111 percent is reached, the signal
to the coils of the
overspeed detection relays is terminated which opens the
contacts of the
relays. This, in turn, terminates the voltage to the coils
of four control
relays. The deenergization of the control relays results
in the closing of
contacts which apply DC control power to the solenoid dump
valves, thereby
opening the dump valves, thereby closing the turbine valves
through their
springs.
0499x:1 0/070689
4
simulating the outer casing of the LP turbine.
The ejection of disc fragments
from fully-integral LP rotors at runaway speed
has not been simulated in
physical model tests. However, analysis indicates
that runaway speeds of FI
rotors could cause the generation of a missile. It
was assumed in the risk
analysis that fully-integral LP rotors behaved
the same as built-up rotors at
destructive overspeed.
0499x:1 0/071089
5
The Robinson plant Os surveillance test
procedures for turbine components
such as inlet valves, turbine trip systems,
and the overspeed protection
controller system. At the request of Carolina
Power and Light, the test
procedures and specific test frequencies
were reviewed and the fault tree
analysis models were constructed to accurately
incorporate the effects of
testing. The analyses and calculations
of design, intermediate, and
destructive overspeed probability all incorporate
the effect of the test
frequency of turbine valves.
0499x:1 0/070689 6
'Plant information o )the steam extraction lines
from the turbines was also
reviewed and compared to the fault tree
of extraction nonreturn valve failure
in Reference 5. In Reference 5, a failure
to block reverse steam flow in any
two of the extraction lines to the turbine
following a loss of load and
turbine trip results in design overspeed. The
Robinson plant has six LP
extraction lines for feedwater heating which
originate at locations on the LP
turbines where sufficient blading exists downstream
of the extraction points
to drive the unit to overspeed. These six
extraction lines combine into four
lines, each of which has an extraction nonreturn
valve. The HP turbine has
two extraction lines with double valving in
each. The general fault tree of
the system in Reference 5 is representative
of the system at Robinson with the.
-- exception that the lines with double valving
are not modeled. However,
probability of reverse steam flow would be
significantly less in the lines
with double nonreturn valves, and this additional
probability would not have a
significant effect on the system failure probability.
0 4 9 9x: 10/070689 7
The conditional probabilities
of missile ejection, P(M/A),
indicate the probability of missile and P(M/B),
ejection once the turbine reaches
overspeed. Conditional probabilities
have been calculated by Westinghouse
based on the specific properties
of many LP rotors at operating
the current study, the fully-integral plants. In
(FI) rotors installed at the plant
considered. The source of conditional were
probability data for the FI
Reference 5. rotors is
0499x:1 0/070689
8
criteria of the
0
*
NRC.
Table 6 gives probabilities of turbine missile
ejection
for the current monthly testing of turbine valves and for extended
test
intervals. All other turbine components are assumed to be
tested in
accordance with the Robinson intervals given in Table 4.
Destructive
overspeed accounts for almost all of the
total turbine missile probability in
Table 6 because fully integral L.P. rotors
are very unlikely to eject missiles
at design and intermediate overspeed.
B. 10- < P(1) < 10- Plant may operate until next scheduled
outage at which time action must be
taken to reduce P(1) to A above.
F. References
049
9x:1 0/070689
9
0g
4. "Analysis of the Probability of
a Nuclear Turbine Reaching Destructive
Overspeed," WSTG-3-P-A, Westinghouse
Steam Turbine Generator Division,
1981 (Revised-July 1, 1987) [PROPRIETARY] May
0499x: 1D/070689
10
TABLE 1
GENERAL TURBINE FAILURE SEQUENCES
RESULTING IN OVERSPEED
ROBINSON UNIT 2
0499x: 10/070689 11
TABLE 2
LIST OF DESIGN INFORMATION AND SURVEILLANCE
TEST PROCEDURE DOCUMENTS
H. B. ROBINSON UNIT 2
0499x: 10/070689
12
TABLE 3
DESCRIPTION OF TURBINE TRIP AND
OVERSPEED PROTECTION SYSTEMS AT ROBINSON
UNIT 2
Additional Note:
04
99x:10/070689
13
TABLE 4
COMPARISON OF TEST INTERVALS OF TURBINE COMPONENTS
INVOLVED IN ANALYSIS OF DESTRUCTIVE OVERSPEED
PROBABILITY
NOTES:
04 9 9x:1 0/070689
14
TABLE 5
GENERAL METHODOLOGY OF PROBABILISTIC
CALCULATIONS
OF TURBINE MISSILE EJECTION
Where:
0499x:10/07068
15
TABLE 6
RESULTS OF TURBINE MISSILE PROBABILITY
CALCULATIONS
ROBINSON UNIT 2 WITH TROTS REMOVED
A. CONDITIONAL PROBABILITIES OF
MISSILE EJECTION DURING LAST YEAR
0499x: 1D/070689
16
. 0 0
ADDENDUM 1
EVALUATION OF SURVEILLANCE TESTING AT ROBINSON UNIT
2
AND IMPACT ON DESTRUCTIVE OVERSPEED PROBABILITY
Addendum to Report:
"Effects of Removing the Turbine Redundant Overspeed Trip System,"
Dated June 1989.
0499x:1 0/070689
17
basic unavailability calculation model in which failure probability
or
unavailability of the fault is directly proportional to
the time interval
between tests. The table contains several faults outside of the
boundary of
the component or system being tested because the test outcomes
in the
procedures are defined in terms of a turbine trip or in terms
of closure of
the turbine valves. For example, a fault such as clogging of the
autostop
oil header would be detected in the overspeed trip test of the mechanical
overspeed trip mechanism since the control and stop valves would not
close
or would close in a delayed manner if the autostop oil header did not
depressurize rapidly as soon as the overspeed trip speed was reached.
Table 9 gives the top four faults having the largest importance factors
for
each case analyzed. Only two faults related to testing of the mechanical
overspeed trip device, overspeed protection controller, and the electrical
solenoid trip appear in Table 9. These faults are failure of the emergency
trip fluid header common to the stop valves due to clogging (D12B),
and
failure of the stop valve to close promptly due to mechanical damage
(D475V*). The latter fault is included in the list because mechanical
0 4 99x:1D/070689 18
damage is assumed to be a fault that slows the
rate of closure of the valve
and is assumed to be detectable only during turbine
trip when the high
pressure oil is suddenly dumped.
0 4 9 9x:1 0/070789
19
_E 7
DETAILED LIST OF FAULTS AFFECTED BY TESTING AND BASIS FOR
EVALUATING EXTENDED TEST INTERVALS
(2) The failure rates are based on Westinghouse data as given in WCAP-11525 (Reference 5).
(3) Test procedure number followed by the procedure section number in parentheses are given below for letters
A through E. The procedure either directly tests the component or can be assumed to test the component as
a result of the component being exercised during a turbine trip or during closure of the turbine valves.
(4) The letters F through I correspond to the following test intervals that were considered in quantifications
of destructive overspeed probability:
F = I MO H = 6 MO. 12 MO. 18 MO
G = 1 MO. 3 MO. 6 MO. 12 MO I = 18 MO
0499x:10/070689 20
TABLE 8
PROBABILITY OF TURBINE DESTRUCTIVE OVERSPEED( 1 )
BASED ON VARYING THE INTERVALS OF SURVEILLANCE TESTING
NOTES:
0499x:1 0/070689 21
TABLE 9
IMPORTANCE OF TOP FOUR DOMINANT FAULTS
CONTRIBUTING TO DESTRUCTIVE OVERSPEED PROBABILITY
NOTES:
o4 99x:1 0/070689
22
PO. OT DC
STRUCTIVT C:PD.
GIVEN LOS: OF
LCAD (VAR 4)
z' 7 CONTINUED ON
27 110 SHEETS 2 &3
23
CONTINUED
FROM SHEET 1
Cialamh valv(
Sgr VSV
CVI IN [Va
I
-Ti rAILS 10I(LDE FAILS ICLOIt
C
(D
(D CONRa ALV(
vAv[ Alg A1 T.
gV [ VIEV
CONTINUED ON " 9
C) SHEET 4 *
(D
L4
I%3~~FLI Kl(ALICS
hlOLca
(1 W'ch 111(115
of110 %CI.IA S SILC K To1( 5Ck'l I1P Dj1 A l k1.C'.f
fL
"(0IloAf
-rl
CONTINUED ON I, *
r+ SHEET 5 ..
r+
(D
CD
ot105 (IF L
MENtslALA(UNI
C.1AAC IIO Ifcl IK
sIA Il"t t (IfVIAT41 mS Alpt a
W t b'uIS is kot(fl)
KDSxtD v.
vMVC ll 10.
i SAs %m.aac HINP tOj~tal
DE
DS kIK145[
(It. , to
ROess e1
(A.t M llI cI ustwa 1.
E
D
CD
* Is
FROM
H.-MFROM .9
S. 8
it LAilt (K414 'AAC c IA. SAI WI
-v[,1
31MVFAL
-- TO -f
IV
ISI" " I Il [L-IIfIV -[L
AL14 WI. I"IA
FROM
SF1.4
CONTINUED
FROM SHEET 1
Ill
I+
TO
.16)
CD
IN).J
MCI1
116 T3 8f65L2 5v pl11 I-ck Del
10
Mf
r+
CONTINUE
ON V AL VEa IE s ic 1 D IS - : C S LI K FA 1.1sE.0D . C . .. . i s
DI I wV u1
CM F
CDcWL I i I CM (fnlo H cloc- 1 f ~ .I (C, W .11 H
CONDINUED
Ol
I-IL
on . on~S . V2 S H bk
on c FROM
SAL 8I
FROM FROM
SH. 2 SH. 4
AILS Cv CLO:E
5 CONTINUED
FROM SHEET 2
V4Ly1HIGH4 PREC:UPt
PONE
FCONTELD
5 e PI TON
CPEPA TING
OT RELEA:CD
TR V E ANMPED FLUID OT
rDUMP
IEN VALVE
6
7 26 CONTINUED ON
D1CV D3ZvV 9oc SHEET 8
AtFROM 29
CY Sc
SH. 8
so FROM
34 SH. 9
26
C ~FLU
10
DPERATING PISTON
IOT I.LE TED
CONTINUED
FROM SHEET 2
70
FALREO
TH FLUID NTDL PED
DUM VALVE
884
CADAINP
CI LN E C L E S C VF E
S . 8Cc1 DDO F O
OCALPT
DRAI CRAINH L
SO SE V ED CC VALVE 7"87 AE BLvKED CHECKO VALvE ECyTRL INC o
DMP T V LV DLR A CES R IR RE N G EIS L C ED TO A COTPO LA D C
. SH. 4 SH.9
S LOGCK D
BLOCKED
LCKAIL TOVE FICYTLIINDETRVLE) gy IS g
CLOEDO ENICCO
78 SH. 8 8nevR GEED L GG D
27
FLUID LtDER
DtRATi4 PiSTON
NOT PCLEASED
3 CONTINUED
FROM SHEET 3
117 129
LVR aE s T C E
V A L V E C L O S R E C OS UR CL OER C V/ V E
A30
FROM FROMUREROM
SAEC 3 VALVE P ARE LE SH. 4 ev.H4
C7OURI
CVI
E
28
ri > PISTON
NmRTLErA-ED
CONTINUED
FROM SHEET 3
141
FAILUPEOF
THEFLUIDD T DLppED
14213
FROM
5 M"
14 15815 5
1160
rA
AI UR
LU E F E D AI P TH E F INFROM0 M FROM
REED c SERve Accx mass
Av B E F SH. 4NH
D TE
An ~~~LOCGED
. CNRLV CS
LOCALDRAI
COMF0N29PATH
IMILLE ET T
. SERVO srE
CONTINUEO
FROM SHEET 4
it
017CVI
Al
D ETEC O R SA RT E B LL I S B I O r S O C A D . R T A L V T
D18CVI
ETORD
AL DRA LINE EURN LINS TO BOH Cm E
19 23
025 D5C1 D4~5
D0 PRIYDRI
30
OC AND EVERVCN
CY TRIPS rAIL TO
? . DRAIN ETr rLUID
34
OPC TAIL: TO
CLOcE CV OAT LOL L OVERSPEED
103% OVERPEED TRIP' FAIL TO
CLOSE CV S
3i
FAILURE Or BOTH
OLENIOD S~CNIOO
VtLVE:
VALVE SIGNAL TO OPEN
SOLENIOD
CHECK vaVE ETT NOTDRAINED
VALVES BETAEEN CV AND AINEAC
(2P) (20/Opt)~~S I2/C
(PC> (T IsNO
TF HEADERS VIA INT FC
VALVE AND SOL~
-----TRANSmITTED FAILS TO OPEN VALVE 20/VT
36 41 45
46
D41I
37 4
3 61
022 23 a CONTINUED ON
7 4 SHEET 10
39 62
363
D24A D24 9 DO
64
D09
65
FROM
SH. 10
31
ET FLUID Nor
rACEI0 VALVE
DR.~
INrE
0
CONTINUED
FROM SHEET 9
47
49
006
so1
St
013
MECHANICAL TRIP
FAILS TO ACTUATE ELECTRICAL TRIP
FALLS TO ACTUATE
VITH LOS, OF
LEAD
52
53
001
D1o
D2 n 04 DO3
EXTENSION
FAILS
7Swarr
DISABLING
(CHAN[CAL
NOTACTIVATED BY
TRIP
MAIN SPEED EXTENSION SHAFT
SENSING FUN4CTION rAI unt
FROM
SH. 8 5
O 5
32