You are on page 1of 17

GLOBAL

CONSTRUCTION
DISPUTES REPORT
2016
DON’T GET LEFT BEHIND

Contract Solutions
DON’T
GET LEFT
BEHIND
With uncertainty reigning in markets around
the world and projects more complicated than
ever before, disputes are taking longer to resolve
which can have far reaching consequences
CONTENTS

INTRODUCTION 6-7

THE WORLD ECONOMY IN 2015 8-9

OVERALL FINDINGS 10 - 13

NORTH AMERICA 14 - 15

ASIA 16 - 17

MIDDLE EAST 18 - 19

UK 20 - 21

CONTINENTAL EUROPE 22 - 23

AUSTRALIA 24 - 25

SUMMARY 26 - 27

METHODOLOGY 28

CONTRACT SOLUTIONS EXPERTISE 29

CONTACT 30 - 31
INTRODUCTION
Welcome to the Sixth We have taken an in-depth, data- • to maintain cash flow within the case than had been planned,
driven review of our projects and supply chain; which contributed to some of
Annual Arcadis Global disputes globally in 2015 and the issues and disputes that have
• to maintain party relationships;
focused on five key areas: the materialized. In particular the
Construction Disputes length of disputes, average value, • to keep the respective delivery natural resources markets and
Report 2016, which common causes, most popular teams focused on delivering the some of the major Engineering,
resolution methods and region- project; and Procurement and Construction
reveals key themes specific nuances. This report (EPC) contracts have run into
• to avoid a cumulative effect of
Mike Allen and insights into the also includes an overview of the
minor issues being aggregated
some substantial disputes, with
macroeconomic market position billions of US dollars in contention.
Global Leader global construction and goes on to cover all regions
into large disputes.
There has also been a rise in the
of Contract
Solutions disputes market. Any in which the Arcadis Contract These reasons are largely self- number of insolvent companies
Solutions team operates, evident, and it is aspirational to and terminated contracts, which
Arcadis dispute is case specific, including North America, UK, suggest that all disputes can or are no doubt linked to the current
so to endeavour to Continental Europe, Middle need to be settled quickly. Even economic environment.
East, Asia and a new section on so, we must continue to embrace
group causes and Australia. the many initiatives that are
In the last year we have also had
two cases which provide helpful
develop averages can It is commonly known in the
being deployed by construction
guidance on important aspects of
professionals, lawyers and the
risk omitting critical industry that a substantial
judiciary across the globe, and
construction dispute resolution.
percentage of disputes are settled The first related to the application
information related to before they become formalized.
do all we can to facilitate the
of Liquidated Damages, and the
settlement of such disputes. This
In the unlikely case a dispute is to other an important reminder to
the overall nature of materialize formally, both parties
means that effective dispute
us all that being an experienced
avoidance mechanisms need to
the dispute. However involved could see themselves
be actively deployed as early as
construction professional doesn’t
in a situation where differing necessary qualify you to be an
given our range and views and interests could prolong
possible within a project, and
expert in this field. Both of these
involvement of the right expertise
depth of the coverage, the dispute. Setting aside the
and support at the right time is
cases are discussed in more detail
different drivers and motives in the summary.
dispute trends, both of both parties involved, it is
critical.
We hope that you enjoy this
globally and regionally, generally agreed that a speedy In 2015 the construction industry
edition, and if you have any
settlement of any dispute is faced head winds in particular with
are indicative of market desired, but why? commodity and currency volatility.
feedback or insight that you wish
to share please contact me.
trends. • To use current and available
This resulted in many projects
and programs being faced with a
people and documents, which
very different economic business
are directly relevant;

6 7
THE WORLD
ECONOMY
IN 2015 led economy towards a more
sustainable path based on
consumption and services. In the
meantime, Chinese developers and
contractors have been diversifying
complete without a mention of
Brexit1. Brexit fears appear to be
having an impact on investment
decisions, but the direct impact of
either outcome of the referendum

The economic trends that away from home markets. While


they have shown themselves to
on construction is likely to be more
limited. However, given that so

impacted disputes
be adept at operating in overseas much of the debate in connection
markets, these organizations with the referendum concerns
are challenged to adapt to the free-movement of labor, it is
business cultures and construction conceivable that any changes to
practices of mature developed labor market rules could affect
The global recovery from the 2008 Much like the aftermath of the markets. Two unexpected spill- the ability of contractors to meet
financial crash continued in 2015, financial crash of 2008, the over effects of China’s slowdown long-term project commitments.
but at an ever slowing pace. Future loss of growth momentum in in international markets could This is a long-term risk, but as
prospects are looking increasingly some markets including Russia be an increase in competition for skills shortages are such a big
fragile. The baseline projection for and Brazil is likely to impact work – resulting in lower entry issue in many markets, the ability
global growth in 2016 is a modest on construction volumes, prices – and an increase in disputes of designers and contractors
3.2% according to the International leading to disputes surrounding as new entrants to markets align to find the abilities to deliver
Monetary Fund, which is broadly the cancellation, suspension, themselves to established ways of projects to cost, time and quality
in line with 2015, but a 0.2% termination or restructuring of working. expectations, could turn out to
downward revision from January projects. Elsewhere in markets be a significant trigger for project
As previously stated, turbulence problems and possible disputes
2016. Recovery is projected to that are seeing some recovery in in commodity and currency over the next few years.
strengthen in 2017 and beyond, demand such as mainland Europe, markets over the past 12 months
driven primarily by developing persistently low background may have exposed clients and On the bright side, despite the
economies as conditions in these inflation can be expected to affect their contractors to unexpected global slowdown impacting
stressed markets gradually contractors’ ability to secure financial outcomes that could on economies worldwide, one
normalize. However, there are big expected levels of returns on potentially trigger problems on a benefit is likely to be interest
risks in the forecasts and some projects. project. Crude oil was priced at $44 rates remaining low, as countries
turbulence is expected in markets,
A major cause of the global a barrel in April 2016, down 32% continue to apply fiscal stimulus.
which could, in turn, affect the
economic slowdown has been a year on year, but up by over 50% in We are therefore unlikely to see
level of construction disputes.
fall in investment demand. This the first quarter from the low point a reduction in viability due to
The end of 2015 and beginning has been the case particularly for of the cycle. Similar movement increases in the cost of finance.
of 2016 saw renewed episodes commodity exporting countries has been seen in currencies. These
wild fluctuations are likely to affect All together these factors will
of global asset market volatility. whose terms of trade have
some parties in a supply chain if contribute to a challenging
Commodity and currency prices collapsed. If the forward pipeline
appropriate price hedging has not economic environment over the
have also fluctuated a great deal, of construction-related projects
been put in place. Currencies and next year both in emerging and
increasing the levels of uncertainty further weakens in these countries,
commodities are likely to remain developed economies.
underpinning commercial those involved in construction
arrangements. Despite an projects may focus efforts on unstable and could well trigger
improvement in market sentiment maximizing returns from existing wider problems on projects going
during the first quarter of this projects through disputes rather forwards.
year, business conditions remain than pursuing future projects. Finally, in 2016, no review which
challenging, highlighted by weak
China is navigating a complex includes the UK and Continental
financial data from China and
transition away from a high European markets would be
further loosening of fiscal policy in
Europe and Japan. growth, investment and export-

1.
The referendum vote on whether the UK will withdraw from the European Union.

8 9
OVERALL FINDINGS
We define a ‘dispute’ as a situation where two parties typically differ in
the assertion of a contractual right, resulting in a decision being given
REGION DISPUTE VALUES (US$ MILLIONS) LENGTH OF DISPUTE (MONTHS)
• The global average value of under the contract, which in turn becomes a formal dispute. 2010 2011 2012 2013 2014 2015 2010 2011 2012 2013 2014 2015
disputes was US$46million. The value of a dispute is the additional entitlement to that included in Middle East 56.3 112.5 65 40.9 76.7 82 8.3 9 14.6 13.9 15.1 15.2
the contract, for the additional work or event which is being claimed. The
• The global average length of a dispute is the period between when it becomes formalized Asia 64.5 53.1 39.7 41.9 85.6 67 11.4 12.4 14.3 14 12 19.5
length of disputes was under the contract, and the time of settlement or the conclusion of the
North America 64.5 10.5 9 34.3 29.6 25 11.4 14.4 11.9 13.7 16.2 13.5
15.5months. hearing.

The results below show that disputes globally have marginally reduced,
UK 7.5 10.2 27 27.9 27 25 6.8 8.7 12.9 7.9 10 10.7
• The highest value dispute but the durations have markedly increased. The increased length of Continental Europe 33.3 35.1 25 27.5 38.3 25 10 11.7 6 6.5 18 18.5
handled by the team in disputes will have multiple effects for both parties and are likely to,
2015 was worth US$2.5bn. ultimately, have a negative impact on the construction industry. GLOBAL AVERAGE 35.1 32.2 31.7 32.1 51 46 9.1 10.6 12.8 11.8 13.2 15.5

10 11
Dispute causes – poor contract Resolving disputes – let’s talk
administration most common
2015 RANK METHOD OF ALTERNATIVE DISPUTE RESOLUTION 2014 RANK

2015 RANK CAUSE 2014 RANK 1 Party to party negotiation 1

1 Failure to properly administer the contract 1 2 Mediation 2

2 Poorly drafted or incomplete and unsubstantiated claims 2 3 Arbitration 3

3 Errors and/or omissions in the contract document 3


The most important activities in helping to avoid a We have found that these trends are symptomatic
4 Incomplete design information or employer requirements New dispute were considered the following: of the work that we have undertaken, and provides a
(for Design and Build) helpful insight into global trends.
1 Proper contract administration
5 Employer/contractor/subcontractor failing to understand and/or 4 2 Fair and appropriate risk and balances in contract Programs of work are being aggregated into various
comply with its contractual obligations delivery models, at a time when key features are
3 Accurate contract documents evident in the global market, and may well be of
a direct contributory relevance to the disputes
In addition to this, one feature that was also discussed
themselves, including:
A new cause in the rankings is related to incomplete within the key inputs to avoiding a dispute was the
design information, which is considered to be linked
generally to the poor quality of design information,
25.5% of Joint role (and perhaps return) of the need for a truly
independent certifier.
• Commodity and currency volatility;

Ventures (JVs)
• legacy effects of tenders priced in the immediate
and a proportionate increase globally in the use
In reviewing the overall findings we find that, when aftermath of the financial crisis and the ensuing
of design and construct forms of contract. The

ended in dispute. compared to previous years, we gain the following economic recession;
implementation of EPC forms of contract have been
particularly problematic in certain industries. headline insights into global disputes: • rising global cost base and strain upon the supply
chain;
The property/real estate sector had the most • They have decreased marginally in value;
disputes. This was closely followed by the social • scarcity of labor and professional staff;
• they have increased in duration;
infrastructure/public sector, albeit the natural • significant reduction in the oil and natural resources
resources sector has some of the largest disputes. • the most common cause is still a failure to
price that has caused a radical rethink of strategy
administer the contract;
and delivery across the major programs.
• 1 in 4 JV’s still end up in dispute; and
Beneath the headline data of our research, many of
• party to party negotiation is still the most common these factors have also proved to be a contributory
form of resolving disputes. feature within the dispute environment and are
considered to be key factors in ensuring that you
“Don’t get left behind”.
12 13
NORTH AMERICA
In North America, JVs tended to result in a dispute in disputed issues grow beyond adolescence and into
DISPUTE VALUES (US$ MILLIONS) LENGTH OF DISPUTE (MONTHS)
just over a fifth of all cases (20.45%), a slight increase a full “blown” dispute with consultants and counsel
2010 2011 2012 2013 2014 2015 2010 2011 2012 2013 2014 2015 on 2014. involved. It is no secret that US courts are reluctant
to try construction cases. They are complex and
North 64.5 10.5 9 34.3 29.6 25 11.4 14.4 11.9 13.7 16.2 13.5 The three most common methods of Alternative contain large volumes of documents. These factors
America Dispute Resolution that were used during 2015 in actually extend durations of disputes as parties are
North America were: encouraged to settle and the courts will give them the
time do so.
1 Party to party negotiation
Both the time taken to resolve disputes and the values value will continue into 2016 as the industry continues
involved in North America actually dipped slightly to recognize the importance of addressing disputes 2 Mediation There is an alternate effect on the project participants
between 2014 and 2015. Dispute values have seen a early in their lifecycle, and contracts are written addressing and coming to an early agreement on
3 Arbitration many disputed issues. Disputed issues that remain
moderate incremental decline since 2013 when they with provisions giving strict instruction on how and
were the highest since 2010. The duration of disputes when to address disputes. This early intervention and grow into full disputes are complicated and have
The global pattern is that dispute durations are
in 2015 also fell from 2014 levels and has moderated allows disputes to be evaluated more quickly before large damages and will take a long time to resolve.
up and the same is true in North America. While
closer to the five-year average, at approximately 12 damages and emotions swell impeding settlement. durations are up, dispute values and the quantity It would be a surprise to see durations of disputes
months. We expect that the decline in duration and of disputes have declined. Less and less disputes ever decrease to lower than several months. While
progress through the stages of initial assessment the industry is getting better at proactively addressing
to evaluation to negotiation and then all the way disputed issues, as long as people are building, there
through litigation. will be complicated disputes that will take time
2015 RANK CAUSE 2014 RANK
to resolve.
There are several reasons for this change in behavior.
1 Errors and/or omissions in the contract document 1 Both owners and contractors in North America
have come to appreciate how expensive and time
2 Failure to properly administer the contract New consuming the formal dispute resolution process
can be. Legal fees, consultant fees and business
3 Differing site conditions 2 distraction have prompted the construction industry
to consider quicker and less costly ways of addressing
disputed issues. In recent years, provisions have been
For the second year running, the most common cause and a failure to properly administer the contract – the included in many major construction contracts that
for disputes in North America during 2015 was errors top cause globally – came in second position. outline a specific procedure for addressing disputed
and/or omissions in the contract documentation. issues. The result, which is evident in the survey
Differing site conditions dropped down a place to third responses, is that the field staff of active projects
are resolving most disputed issues and less and less

14 15
ASIA
Where a dispute occurred, JVs were more likely to be Singapore meanwhile is currently in consultation
DISPUTE VALUES (US$ MILLIONS) LENGTH OF DISPUTE (MONTHS)
behind the cause in Asia, with a JV–related difference on a Mediation Bill, which looks to strengthen the
2010 2011 2012 2013 2014 2015 2010 2011 2012 2013 2014 2015 the cause in 41.4% of all cases overall framework for the use of Mediation. It is
also interesting to note that both the Hong Kong
Asia 64.5 53.1 39.7 41.9 85.6 67 11.4 12.4 14.3 14 12 19.5 The three most common methods of Alternative International Arbitration Center and Singapore
Dispute Resolution that were used during 2015 in Asia International Arbitration Center remain very active
were: in the number of both institutional and ad hoc
Dispute values in Asia actually dropped significantly during 2015, hitting an average of US$67m. arbitrations in the region.
1 Party to party negotiation
Meanwhile, the amount of time taken to resolve Asian disputes rose substantially.
2 Arbitration We are predicting an increase in the number of
disputes that we will be dealing with in the coming
3 Mediation year. With this in mind, combined with project
2015 RANK CAUSE 2014 RANK status and lack of desire by parties to have long and
In 2015 we have seen an overall reduction in the value,
but an increase in the duration of the disputes in the protracted disputes, we are likely to see a further
1 A failure to properly administer the contract 2
region. While the overall value has reduced, the Asian increase in the use of ad hoc forms of Alternative
2 Failure to make interim awards on extensions of time and compensation 1 based disputes are still approximately 45% higher Dispute Resolution, which we are currently
than the global average. From a market perspective, experiencing in the region. Some of the leading
3 Poorly drafted or incomplete and unsubstantiated claims New we find that although there is a construction institutions in the region have actively embraced and
slowdown in China, the Hong Kong and Singapore deployed such mechanisms to good effect in 2015,
markets are now facing challenges that are presented and this may be part of a recipe to reduce the regional
There were some changes in the reasons behind global and/or total cost claims. Common causes by large scale infrastructure projects nearing statistics.
disputes in 2015. A failure to properly administer the of this approach to claims is either an individual or completion.
contract was the most common cause, moving up combination of the desire for a speedy submission, Finally, with a hardening economy in the region and
from second in last year’s report. lack of substantiation, lack of capability to prepare a To address both historic and current issues regulatory the stakes so high for both parties, it’s perhaps not a
robust and credible claim, or the complexity of issues changes have been implemented. Hong Kong time to be passive in looking at how to address issues
Poorly drafted claims has kept its place in the to be claimed. introduced the Rights of Third Parties Ordinance on 1 that arise on the projects, but to actively seek to
rankings, where we have seen a growing trend for Jan 2016 and the Security of Payment is due in 2017. resolve issues before they become a formal dispute.

16 17
MIDDLE EAST
The three most common methods of Alternative Mediation and Adjudication instead of the traditionally
DISPUTE VALUES (US$ MILLIONS) LENGTH OF DISPUTE (MONTHS)
Dispute Resolution that were used during 2015 in ME contracted Litigation/Arbitration methods. All
2010 2011 2012 2013 2014 2015 2010 2011 2012 2013 2014 2015 were: parties embrace the added value that an impartial
professional judgement/recommendation brings
Middle 56.3 112.5 65 40.9 76.7 82 8.3 9 14.6 13.9 15.1 15.2 1 Party to party negotiation to the settlement of disputes, which is not only
East 2 Arbitration cheaper and more expeditious, but also transfers
decision-making to external agents, thereby assisting
3 Mediation with state audit compliance. The market is further
The Middle East region saw its dispute values increase, once more, to their highest value since 2011. In an economic environment impacted by the oil increasingly utilizing design and build contracting
However, the amount of time taken to resolve disputes remained more-or-less static. price, the market continues to see a restriction in models and has even experimented with the New
decision-making within the industry. This drives a lack Engineering Contract (NEC) suite. Public-private
of appropriate delegation to project management partnerships are also growing in popularity as
2015 RANK CAUSE 2014 RANK
consultants and client representatives, thereby inward investment is coveted to mitigate budget
1 A failure to properly administer the contract 1 prolonging critical commercial decisions and deficits generated by low oil prices. This shift in
generating cash flow issues related to instructed strategic procurement can only be beneficial to
2 Poorly drafted or incomplete and unsubstantiated claims 2 variations. Some clients are looking to spread cash the continued growth of construction in the Middle
obligations by prolonging commercial payments and East and maintain its attractiveness to international
3 Incomplete design information or employer requirements New negotiations. Additionally, the tendency to utilize a contractors and consultants.
(for Design and Build) traditional contracting strategy is ill-suited to the
While the region is experiencing a challenging
continuing size and complexity of the programs. This
period, the opportunities and potential rewards
A failure to properly administer the contract In the Middle East, where a JV is in place, the is exacerbated by the propensity of clients to transfer
for contractors and consultants remain. As better
remained the most common cause of dispute in the proportion of disputes caused by a JV-related issue the majority of project risk to contractors.
compliance and cost optimization initiatives are
region, followed by poorly drafted or incomplete dropped in 2015, moving down almost ten percent to However, there is a desire from all parties to better introduced by private operators and governmental
and unsubstantiated claims which, once again, 32.3% streamline formal dispute processes, reduce entities, the market will improve as an environment
demonstrates the need to get the basics right from administrative burden and create a fairer contracting within which both domestic and international
the very start. model. There is a noticeable shift in the use of organizations can thrive.

18 19
UK
The UK judiciary has sought to reduce the costs of form, substance or intent of payment applications.
DISPUTE VALUES (US$ MILLIONS) LENGTH OF DISPUTE (MONTHS)
litigation to a proportionate level with the Jackson Furthermore, Grove Developments Ltd v Balfour
2010 2011 2012 2013 2014 2015 2010 2011 2012 2013 2014 2015 Report recommendations incorporated into amended Beatty [2016] EWHC 168 (TCC) stands as a warning
2013 Civil Procedure Rules. Although stopping short of to contractors of including payment schedules in
UK 7.5 10.2 27 27.9 27 25 6.8 8.7 12.9 7.9 10 10.7 compelling parties to use mediation, judicial pressure contracts without expressly stating the procedure
to limit costs has exposed an increasing number of should there be an extension of time. The practical
Construction disputes in the UK dipped for the second consecutive year. However, in keeping with most parties to its potential benefits. Combined with the implications of losing the right to interim payments
areas of the world, the time taken to resolve disputes continued to rise. In spite of this, the length of time continuing commercial pressure on construction disadvantages small and medium-sized enterprizes
taken in the UK is the lowest globally. executives to minimize the cost of disputes, this has with limited cash reserves, who account for the vast
resulted in more mediations and increased party to majority of the industry and is therefore contrary to
party negotiation. This trend is expected to accelerate the spirit of recent construction law reform.
2015 RANK CAUSE 2014 RANK over coming years as mediation continues to gain
traction, albeit adjudication will continue to dominate The increased prevalence of disputes relating to
1 Failure to properly administer the contract 1 Alternative Dispute Resolution in the UK. This is incomplete design information or employer was found
especially due to the repeal of s.107 of the Housing to be a hangover from pre-construction cost saving
2 Incomplete design information or employer requirements 5 Grants, Construction & Regeneration Act 1996, practices during the economic crisis. As the impact
(for Design and Build) providing the opportunity for parties to refer disputes from such practices recedes it is anticipated that
arising out of oral contracts to adjudication. poorly drafted claims will again feature strongly.
3 Employer, contractor or subcontractor failing to understand and/ or 2
comply with its contractual obligations Practitioners continue to underestimate the The UK – London in particular – remains a dispute
paramount importance of payment terms resolution powerhouse with the legal instruments,
within construction contracts and the financial institutions and expertise necessary to timeously
The causes of disputes in the UK followed a similar Three most common methods of Alternative Dispute consequences of failing to abide by them. This was resolve major international disputes.
pattern to previous years. A failure to properly Resolution used during 2015 in the UK: manifested in an increased number of payment
administer the contract remained the most common disputes, be that employer failure to issue Pay Less
cause in 2015, as it did in most areas of the world. 1 Party to party negotiation
Notices or contractors failing in respect of the timing,
2 Adjudication
Where a JV was in place, a JV-related issue was the
root cause in 12.5% of cases, half that of 2014. 3 Mediation

20 21
CONTINENTAL
EUROPE Conflicting party interests were the most common
cause of disputes during the year, while a failure to
properly administer the contract dropped down to
third place.

Across Continental Europe, where a JV was in place, a


In Central and Eastern Europe, the number of out-
of-court settlements is still insignificant. Disputes
are usually resolved by court proceedings and, on
a smaller scale, by arbitration. This situation results
from the lack of decisiveness of public employers in
terms of accountability for out-of-court settlement
DISPUTE VALUES (US$ MILLIONS) LENGTH OF DISPUTE (MONTHS) JV-related issue was the cause in 17.7% of cases. of disputes. Initiatives which aim to change the
2010 2011 2012 2013 2014 2015 2010 2011 2012 2013 2014 2015 most popular dispute resolution method, such as
The three most common methods of Alternative
promotion of alternative dispute resolution methods,
Continental 33.3 35.1 25 27.5 38.3 25 10 11.7 6 6.5 18 18.5 Dispute Resolution used during 2015 in Continental
still do not bring noticeable changes. However, this
Europe Europe:
seems to be a positive approach where the economic
1 Party to party negotiation growth forecast of countries like Poland, Czech
Republic, Romania and Turkey, indicate a growing
2 Arbitration market for large infrastructure projects.
The value of disputes remained high in Continental Europe, despite a significant drop from 2014.
Meanwhile, the length of time taken to resolve disputes edged up to 18.5 months. 3 Mediation
All of the above circumstances have led to an
Although party to party negotiation is still the environment where Continental Europe is still a region
2015 RANK CAUSE 2014 RANK most common form of dispute resolution, we are in which resolving a dispute is a time-consuming
observing some changes in the market, with this process, with the second longest-lasting disputes after
1 Conflicting party interests New change becoming most evident in some of the largest Asia. This fact is even more puzzling when we consider
Continental European markets. Investments located the relatively low value of disputes (over two times
2 Incomplete design information or employer requirements 5 in Southern Europe (Spain, Italy and France) are more lower than in Asia). Also worthy of note is the fact
(for Design and Build) frequently resolved through court or arbitration that the disputes in the UK, which have a comparable
proceedings rather than through negotiations value, are resolved on average in half the duration of
3 A failure to properly administer the contract 3
between the parties during the realization stage. This disputes in Continental Europe.
trend seems to be increasing and therefore proper
preparation of documents in order to effectively
conduct legal proceedings is becoming a fundamental
requirement.

22 23
AUSTRALIA
As Arcadis expands its geographical footprint, we The mining sector is likely to continue to see decline Residential and commercial developments have sums involved. Commodity prices continue to remain
find ourselves able to draw upon new market insights in the number and value of new projects, on the posted solid growth recently, supported by low flat, new investment in capital projects has wound
from our 2014 Hyder Consulting acquisition and back of continued weakness in commodity prices, interest rates, and the outlook for the commercial back and the slump in resources investment and
our growing presence and activity in the Australian with reduced activity in mining related construction sector is a period of strong growth with a number of commodity prices sharpens appetites to minimize or
market. Next year’s report will provide a more activity. This sector continues to explore and major developments in the pipeline. maximize respective positions.
in-depth review and context, based on findings and implement cost-cutting and production efficiency
viewpoints from 2016. In the meantime, below is a programs. Australia has recently seen a huge surge in the Current typical reasons for disputes include:
general insight into the Australian construction and construction of extremely large natural resources
There is a significant increase in the number of road projects, particularly in Western Australia and • Haste to get product to market;
dispute market.
and rail projects planned for Victoria and New South Queensland, with many of these projects now nearing • inadequate risk allocation between contracting
The outlook for Australia’s construction sector Wales. State governments are increasingly using completion. We believe that this sector is potentially parties; and
remains subdued, particularly as its mining sector public-private partnership contract mechanisms to going to be exposed to a wave of multibillion-dollar
declines and the oil and gas sector is nearing privately fund the infrastructure concessions, with disputes between producers and contractors over • incomplete contract documentation.
completion of its capital expenditure stage. However, the government bodies retaining patronage risk, liability for cost increases and project delays. What
the commercial and residential sectors continue to while continuing to develop innovative availability makes the natural resources sector unique is the
show solid growth and the transport infrastructure abatements and Key Performance Indicators. size and sheer magnitude of the supply chain and
sectors continue to recover, being forecast to show
steady growth with an upswing in new projects.

24 25
SUMMARY
Our regional commentaries have given some insight into the common causes and features
of disputes in each region. We consider that these themes provide a helpful reference point
to typical trends both regionally and globally. It is evident that the natural resources market
is now operating against a very different economic backdrop. The business case assumptions
that were likely used to endorse projects and programs have therefore changed, presenting
a huge challenge to the project and entity risk profiles. The disputes in this sector have been
a material feature in the last 12 months and will continue to be evident in the coming year.

We have established that globally resolve issues as they materialize. • adjudication or some forms This year, consistent with last the actual loss. The Court made it considered in the context of the
the following key dispute themes Furthermore, if a claim then does of ADR in some regions is not year, we have noted the following clear that delay damages will only widely referenced ‘Ikarian Reefer’
have prevailed: progress into a formalized dispute, providing a solution that is additional features, which include: be considered to be penal, and so case and guidelines.
actively deploying key support acceptable to the parties. unenforceable, if the damages are
• The average value has and expertise, effective strategies • Mega disputes, with the largest extravagant to the point of being Thank you and I hope that you
marginally reduced to US$46m. Some interesting features of dispute we have been engaged have enjoyed this year’s edition.
and the active use of Alternative unconscionable.
the regional overviews have in this year exceeding US$2.5bn;
• The average length has Dispute Resolution (ADR) will
highlighted the following trends in and The second case is worthy of note
increased to 15.5 months. assist in reducing the time it takes
some or all of the markets: on two fronts, because it provides a Mike Allen
to resolve the dispute. • a notable increase in the volume
• The most common cause is very helpful reminder and checklist Global Leader
• The effect of the global of arbitrations. of Contract
still the failure to properly Considering why the length of of what is required of an Expert
commodity and currency Solutions
administer the contract. disputes has increased is likely to The majority of construction Witness, and also because the
volatility;
be a mix of the following factors: disputes are resolved privately other expert in this case who was Arcadis
A continuing trend over the last
• the earlier deployment of and so we tend to have very few used as a reference point of what
six years is that, on average, • An increase in the size of dispute avoidance mechanisms; reported cases, however in 2016 should have been undertaken was
disputes have increased in value disputes that Arcadis has been there were amongst others two Gary Kitt (UK Leader of Arcadis
and duration, with the notable instructed to act; • the increasing use of mediation,
cases which merit a mention. The Contract Solutions). The case
increase this year in the length and refinement of other forms of
• an increase in the number of first is Cavendish Square Holdings was Van Oord UK Limited & Sicim
of time taken to resolve disputes. ADR; and
large and complex EPC disputes; BV –v- El Makdessi and Parking Roadbridge Limited –v- Allseas UK
Therefore our theme this year
• a reliance from public or quasi- Eye Ltd –v- Beavis [2015] UKSC67, Limited [2015] EWHC 3074 (TCC),
of “Don’t get left behind” is • the disputes that are formalized public bodies to require third in which the notion of a liability in which the Court clearly set out
focused around making sure are including multiple or whole party decisions, to assist in for delay damages might be 12 rules of what is required of an
that in recognizing what causes contract issues, rather than retaining complete ‘arm’s length’ challenged if the rate of damages expert, and it is suggested that the
disputes, avoidance mechanisms referring discrete claims; and decision making. is not a genuine pre-estimate of full judgement should be read and
can be actively deployed to

26 27
METHODOLOGY CONTRACT
SOLUTIONS
This research was conducted by the
Arcadis Contract Solutions experts EXPERTISE
and is based on construction
disputes handled by the team in
2015. Arcadis’ Contract Solutions teams
help clients avoid, mitigate and
Arcadis is the leading global Design resolve disputes. The team is based
& Consultancy firm for natural around the globe and encompasses
and built assets. Applying our one of the industry’s largest pool
deep market sector insights and of procurement, contract, risk
collective design, consultancy, management and also quantum,
engineering, project and delay, project management,
management services we work engineering defects and building
in partnership with our clients to surveying experts.
deliver exceptional and sustainable
outcomes throughout the lifecycle The team provides procurement,
of their natural and built assets. contract and dispute avoidance
We are 27,000 people active in over and management strategies,
70 countries that generate €3.4 management expertise as well
billion in revenues. We support as dispute resolution and expert
UN-Habitat with knowledge witness services. This is delivered
and expertise to improve the through a blend of technical
quality of life in rapidly growing expertise, commercialism, sector
cities around the world insight and the use of live project
www.arcadis.com.  data, combined with a multi-
disciplined and professional focus.
Arcadis
Improving quality of life.

28 29
CONTACTS:
Mike Allen
Global Leader of Contract Solutions
T: +852 2263 7301
Email: mike.allen@arcadis.com

Gary Kitt
Head of Contract Solutions, UK
T: +44 20 7812 2310
Email: gary.kitt@arcadis.com

Maciej Kajrukszto
Head of Contract Solutions,
Continental Europe
T: +48 222 032 294
Email: maciej.kajrukszto@arcadis.com

Philip Moss
Head of Contract Solutions, Asia
T: +852 2263 7300
Email: philip.moss@arcadis.com

Craig Beeson
Head of Contract Solutions,
Middle East
T: +974 4424 5000
Email: craig.beeson@arcadis.com

Roy Cooper
Head of Contract Solutions,
North America
T: +1 860 503 1500
Email: roy.cooper@arcadis.com

Paul Tracey
Head of Contract Solutions, Australia
T: + 61 7 3337 0000
Email: paul.tracey@arcadis.com

30 31
Arcadis

@arcadisglobal

www.arcadis.com Contract Solutions

You might also like