Professional Documents
Culture Documents
D. Basement Construction (Blank)
D. Basement Construction (Blank)
Basement Construction
(Provisional Lump Sum Price)
located at
-
F Contractor is responsible for temporary stability during Note -
construction and for all temporary works design
-
G All necessary steel reinforcements, treaded couplers, chairs, Note -
spacers, tying wire, accessories and all necessary cutting and
bending.
-
H All necessary, tamping, vibrating, surface treatments (power Note -
floating, trowelling etc.), curing, protection etc.
-
J All / any necessary construction joints (Transverse, Note -
Longitudinal, contraction, isolation etc.), joint filler, mastics.
-
K Integration/forming of all necessary service openings. Note -
-
L All necessary platforms for Mechanical and Electrical Note -
Equipment/Plant, incl any base hardeners or slab thickening
for plant and equipment.
-
M All necessary lifting, hoisting, cranage etc. Note -
-
N The layout for all construction joints must be submitted to the Note -
Engineer prior to commencement. Construction joints are not
measured separately and are deemed to be included within
the rates.
-
P Allow for liaising with the Steel Contractor as required; note Note -
the Cast-In Fixing Inserts for the Steel Frame are to be
installed by the Steel Contractor as part of the steel works.
The below is deemed to include all costs associated with
progress on same.
-
-
NOTES (Cont'n) -
-
A The contractor shall note the requirement for noise and Note -
vibration monitoring throughout the Excavation Works. The
Contractor is deemed to have included all costs associated
with same within their tender.
-
B The Contractor is requested to insert quantities for items of Note -
work where he thinks applicable and appropriate; hence, no
claim for additional quantities will be entertained
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
To Collection
-
Concrete Formwork
-
-
To Collection -
To Collection -
Cast-in-Place Concrete
Blinding
-
C Mat/Raft Foundation; 600 mm thick 6,935 m3 -
-
D Mat/Raft Foundation; 1200 mm thick 174 m3 -
-
E Mat/Raft Foundation; 1600 mm thick 298 m3 -
-
F Mat/Raft Foundation; 2400 mm thick 1,236 m3 -
-
G Reinforced Concrete Footing; refer to FRUP-THT-ST-00- 2,261 m3 -
DWG-1105000 Series
-
H Pits 114 m3 -
-
J Retaining Wall 4,815 m3 -
-
K Extra-over allowance for Breakout Panels to Retaining Wall 197 m3 -
-
-
Reinforced in situ concrete; 45MPA; portland cement -
American Concrete Institute (ACI 318M-2008); include for
all construction joints as required; all in accordance with
the Drawings and Specification Section FRUP-THT-ST-
1B-SPC-0033000
-
L Flat Slab 11,194 m3 -
M Drop Panel 352 m3 -
N Beam 455 m3 -
O Ramp Slab 500 m3 -
To Collection -
-
F To basement 05 1 item -
-
-
Concrete Construction Joints -
-
G Continuous Water stops at Construction Joints 2,667 m -
-
J Extra-over; for powder floated finish to receive floor finish 48,832 m2 -
To Collection -
Stair RS01-A
-
Q 1220mm wide x 1347mm High; 8 stair treads/risers 3 nr -
-
R 1220mm wide x 1853mm High;10 stair treads/risers 2 nr -
-
S 1220mm wide x 2039mm High;11 stair treads/risers 2 nr -
-
T 1220mm wide x 2236mm High;12 stair treads/risers 2 nr -
-
U 1220mm wide x 2369mm High;13 stair treads/risers 1 nr -
-
To Collection -
-
A 100mm x 200mm size 10 m -
-
B 150mm x 200mm size 61 m -
-
C 200mm x 200mm size 3 m -
-
D 250mm x 200mm size 16 m -
-
E To walls exceeding 3m height; 100mm x 200mm size 1 item -
-
-
Concrete Topping (Screed) -
-
Proprietary quick drying bonded levelling screed; basis -
of design: Flowcrete UK, Isocrete Heavy Duty "K" screed
or similar by Flowcrete or approved equal; including
fabric reinforcement and all necessary accessories; all in
accordance with the drawings and Specification Section
03 53 00
-
F To basement floors, 100mm thick 5,419 m2 -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
To Collection SAR -
-
Additional Items -
-
-
The Contractor shall describe and price below the items
necessary for the full and proper Completion of the
Works as described in the Specifications or shown on
the Drawings and for which either expressed or implied
provision is required and which are not covered by either
the items or the rates in the Bills of Quantities and
whether arising from the class of work, Conditions of
Contract or any other matter whatsoever. Anything not
so separately described shall be deemed to be covered
in the items and rates inserted in the Bills of Quantities.
-
A _______________________________________________ -
-
B _______________________________________________ -
-
C _______________________________________________ -
-
D _______________________________________________ -
-
E _______________________________________________ -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
To Collection SAR -
COLLECTION
#REF! SAR -
#REF! SAR -
#REF! SAR -
#REF! SAR -
#REF! SAR -
#REF! SAR -
#REF! SAR -
#REF! SAR -
#REF! SAR -