ACTIVITY DESCRIPTION QUANTITY OF WORK UNIT TIME

EARTHWORK IN EXCAVATION 31.35 cu.m 8


EARTWORK IN FILLING 25.61 cu.m 6
LIME CONCRETE IN FOUNDATION 10.74 cu.m 5
FIRST CLASS BRICK WORK IN FOUNDATION 22.32 cu.m 9
DAMP PROOF COURSE 10.52 sq.m 4
FIRST CLASS BRICK WORK IN SUPERSTRUCTURE 30.1 cu.m 20
RCC WORK IN SLAB 10.1 cu.m 8
LIME CONCRETE IN ROOF TERRACING 53.6 sq.m 5
WOOD WORK IN CHAUKHAT 0.735 cu.m 8
WOOD PANALLED DOOR AND SHUTTER 16.27 sq.m 8
PLASTERING IN WALL 285.6 sq.m 12
WHITE WASHING 203.64 sq.m 14
COLOUR WASHING 171.58 sq.m 15
PAINTING DOOR AND WINDOW 65.77 sq.m 8