Professional Documents
Culture Documents
336
respondent.
Actions; Alternative Dispute Resolution (ADR); 336 SUPREME COURT REPORTS
Arbitrations; Construction Industry Arbitration Commission ANNOTATED
(CIAC); Administrative Law; Factual findings of construction Uniwide Sales Realty and Resources Corporation vs.
arbitrators are final and conclusive and not reviewable by the Titan-Ikeda Construction and Development Corporation
Supreme Court on appeal; Exceptions.—As a rule, findings of Same; Same; Same; Same; Natural Obligations; The
fact of administrative agencies and quasi-judicial bodies, Supreme Court has not been wont to give an expansive
which have acquired expertise because their jurisdiction is construction of Art. 1724 of the Civil Code, denying, for
confined to specific matters, are generally accorded not only example, claims that it applies to constructions made of ship
respect, but also finality, especially when affirmed by the vessels, or that it can deny the claim for payment of
Court of Appeals. In particular, factual findings of professional fees to the architect.—To be certain, this Court
construction arbitrators are final and conclusive and not has not been wont to give an expansive construction of Art.
reviewable by this Court on appeal. This rule, however admits 1724, denying, for example, claims that it applies to
of certain exceptions. In David v. Construction Industry and constructions made of ship vessels, or that it can validly deny
Arbitration Commission, 435 SCRA 654 (2004), we ruled that, the claim for payment of professional fees to the architect.
as exceptions, factual findings of construction arbitrators The present situation though presents a thornier problem.
may be reviewed by this Court when the petitioner proves Clearly, Art. 1724 denies, as a matter of right, payment to
affirmatively that: (1) the award was procured by corruption, the contractor for additional works which were not authorized
fraud or other undue means; (2) there was evident partiality in writing by the proprietor, and the additional price of which
or corruption of the arbitrators or of any of them; (3) the was not determined in writing by the parties. Yet the
arbitrators were guilty of misconduct in refusing to hear distinction pointed out by the Court of Appeals is material.
evidence pertinent and material to the controversy; (4) one The issue is no longer centered on the right of the contractor
or more of the arbitrators were disqualified to act as such to demand payment for additional works undertaken because
under Section nine of Republic Act No. 876 and willfully payment, whether mistaken or not, was already made by
refrained from disclosing such disqualifications or of any Uniwide. Thus, it would not anymore be incumbent on Titan
other misbehavior by which the rights of any party have been to establish that it had the right to demand or receive such
materially prejudiced; or (5) the arbitrators exceeded their payment.
powers, or so imperfectly executed them, that a mutual, final Same; Same; Same; Same; Same; Solutio Indebiti; For
and definite award upon the subject matter submitted to the provisions on solutio indebiti to apply, there has to be
them was not made. Other recognized exceptions are as evidence establishing the frame of mind of the payor at the
follows: (1) when there is a very clear showing of grave time the payment was made.—Uniwide, as the owner who did
abuse of discretion resulting in lack or loss of jurisdiction as pay the contractor for such additional works even if they had
when a party was deprived of a fair opportunity to present its not been authorized in writing, has to establish its own right
position before the Arbitral Tribunal or when an award is to reimbursement not under Art. 1724, but under a different
provision of law. Uniwide’s burden of establishing its legal Uniwide’s claim for liquidated damages was not raised as an
right to reimbursement becomes even more crucial in the issue in the TOR or in any modified or amended version of it,
light of the general presumption contained in Section 3(f), the CIAC cannot make a ruling on it. The Rules of Court
Rule 131 of the Rules of Court that “money paid by one to cannot be used to contravene the spirit of the CIAC rules,
another was due to the latter.” Uniwide undertakes such a whose policy and objective is to “provide a fair and
task before this Court, citing the provisions on solutio expeditious settlement of construction disputes through a
indebiti under Arts. 2154 and 2156 of the Civil Code. non-judicial process which ensures harmonious and friendly
However, it is not enough to prove that the payments made relations between or among the parties.”
by Uniwide to Titan were “not due” because there was no Same; Same; Same; Same; Pleadings and
prior authorization or agreement with respect to additional Practice; Amendment of Pleadings; Due Process; A party may
works. There is a further requirement that the payment by not be deprived of due process of law by an amendment of
the debtor was made either through mistake or under a cloud the complaint as provided in Section 5, Rule 10 of the Rules
of doubt. In short, for the provisions on solutio indebiti to of Court.—A party may not be deprived of due process of law
apply, there has to be evidence establishing the frame of by an amendment of the complaint as provided in Section 5,
mind of the payor at the time the payment was made. Rule 10 of the Rules of Court. In this case, as noted by the
337 Court of Appeals, Uniwide only introduced and quantified its
VOL. 511, DECEMBER 20, 2006 337 claim for liquidated damages in its memorandum submitted
Uniwide Sales Realty and Resources Corporation vs. to the CIAC at the end of the arbitration proceeding. Verily,
Titan-Ikeda Construction and Development Corporation Titan was not given a chance to present evidence to counter
Uniwide’s claim for liquidated damages.
Same; Same; Same; Same; As an arbitration body, the
338
Construction Industry Arbitration Commission (CIAC) can only
resolve issues brought before it by the parties through the
338 SUPREME COURT REPORTS
Terms of Reference (TOR) which functions similarly as a pre- ANNOTATED
trial brief.—Arbitration has been defined as “an arrangement Uniwide Sales Realty and Resources Corporation vs.
for taking and abiding by the judgment of selected persons in Titan-Ikeda Construction and Development Corporation
some disputed matter, instead of carrying it to established Same; Same; Same; Same; Same; Formal Offer of
tribunals of justice, and is intended to avoid the formalities, Evidence; Doctrine of Multiple Admissibility; The purpose for
the delay, the expense and vexation of ordinary litigation.” which evidence is offered must be specified because such
Voluntary arbitration, on the other hand, involves the evidence may be admissible for several purposes under the
reference of a dispute to an impartial body, the members of doctrine of multiple admissibility, or may be admissible for
which are chosen by the parties themselves, which parties one purpose and not for another, otherwise the adverse
freely consent in advance to abide by the arbitral award party cannot interpose the proper objection.—Uniwide
issued after proceedings where both parties had the alludes to an alleged judicial admission made by Engr. Luzon
opportunity to be heard. The basic objective is to provide a Tablante wherein he stated that Project 1 was completed on
speedy and inexpensive method of settling disputes by 10 March 1992. It now claims that by virtue of Engr.
allowing the parties to avoid the formalities, delay, expense Tablante’s statement, Titan had admitted that it was in
and aggravation which commonly accompany ordinary delay. We disagree. The testimony of Engr. Tablante was
litigation, especially litigation which goes through the entire offered only to prove that Project 1 was indeed completed. It
hierarchy of courts. As an arbitration body, the CIAC can only was not offered to prove the fact of delay. It must be
resolve issues brought before it by the parties through the remembered that the purpose for which evidence is offered
TOR which functions similarly as a pre-trial brief. Thus, if must be specified because such evidence may be admissible
for several purposes under the doctrine of multiple plans are required before payment can be claimed by Titan is
admissibility, or may be admissible for one purpose and not a mere legal conclusion which is not binding on this Court.
for another, otherwise the adverse party cannot interpose Same; Same; Same; Same; Aware of the objective of
the proper objection. Evidence submitted for one purpose voluntary arbitration in the labor field, in the construction
may not be considered for any other purpose. Furthermore, industry, and in any other area for that matter, the Court will
even assuming, for the sake of argument, that said testimony not assist one or the other or even both parties in any effort
on the date of completion of Project 1 is admitted, the to subvert or defeat that objective for their private purposes;
establishment of the mere fact of delay is not sufficient for The Court will not permit the parties to relitigate before it the
the imposition of liquidated damages. It must further be issues of facts previously presented and argued before the
shown that delay was attributable to the contractor if not Arbitral Tribunal, save only where a clear showing is made
otherwise justifiable. Contrarily, Uniwide’s belated claim that, in reaching its factual conclusions, the Arbitral Tribunal
constitutes an admission that the delay was justified and committed an error so egregious and hurtful to one party as
implies a waiver of its right to such damages. to constitute a grave abuse of discretion resulting in lack or
Same; Same; Same; Same; National Building Code (P.D. loss of jurisdiction.—It is worthy to stress our ruling in Hi-
No. 1098); The submission of “as-built” plans is not a pre- Precision Steel Center, Inc. v. Lim Kim Steel Builders, Inc.,
requisite for the contractor to be paid by the owner; The 228 SCRA 397 (1993), which was reiterated in David v.
purposes of the National Building Code is to safeguard life, Construction Industry and Arbitration Commission, 435 SCRA
health, property, and public welfare, consistent with the 654 (2004), that: x x x Executive Order No. 1008 created an
principles of sound environmental management and control, arbitration facility to which the construction industry in the
and the purposes of the “as-built” plans is necessary only in Philippines can have recourse. The Executive Order was
furtherance of the law’s purpose.—On the necessity of enacted to encourage the early and expeditious
submitting “as-built” plans, this Court rules that the settlement of disputes in the construction industry, a
submission of such plans is not a pre-requisite for Titan to be public policy the implementation of which is necessary
paid by Uniwide. The argument that said plans are required and important for the realization of national
by Section 308 of Presidential Decree No. 1098 (National development goals. Aware of the objective of voluntary
Building Code) and by Section 2.11 of its Implementing Rules arbitration in the labor field, in the construction industry, and
before payment can be made is untenable. The purpose of in any other area for that matter, the Court will not assist one
the law is “to safeguard life, health, property, and public or the other or even both parties in any effort to subvert or
welfare, consistent with the principles of sound defeat that objective for their private purposes. The Court
environmental management and control.” The submission of will not review the factual findings of an arbitral
these plans is necessary tribunal upon the artful allegation that such body had
339 “misapprehended facts” and will not pass upon issues
VOL. 511, DECEMBER 20, 2006 339 which are, at bottom, issues of fact, no matter how
Uniwide Sales Realty and Resources Corporation vs. cleverly disguised they might be as “legal questions.”
Titan-Ikeda Construction and Development Corporation The parties here had recourse to arbitration and chose
the arbitrators themselves; they must have had
only in furtherance of the law’s purpose by setting
confidence in such arbitrators. The Court will not,
minimum standards and requirements to control the
therefore, permit the parties to relitigate before it the
“location, site, design, quality of materials, construction, use,
issues of facts previously presented and argued
occupancy, and maintenance” of buildings constructed and
before the Arbitral Tribunal,
not as a requirement for payment to the contractor. The
340
testimony of Engr. Tablante to the effect that the “as-built”
340 SUPREME COURT REPORTS
ANNOTATED 1. a)The ruling holding petitioner liable directly to the BIR for the
VAT on Project 3 and exempting respondent from the said
Uniwide Sales Realty and Resources Corporation vs. obligation is hereby DELETED, and in lieu thereof, judgment
Titan-Ikeda Construction and Development Corporation is hereby rendered that the Value-Added Tax for Project 3, as
save only where a clear showing is made that, in determined by the BIR may be passed on to the petitioner,
subject to such defenses as it may raise with regard to its
reaching its factual conclusions, the Arbitral Tribunal
computation;
committed an error so egregious and hurtful to one 2. b)The denial of petitioner’s claims for liquidated damages is
party as to constitute a grave abuse of discretion hereby made without prejudice;
resulting in lack or loss of jurisdiction. Prototypical
examples would be factual conclusions of the Tribunal which 341
resulted in deprivation of one or the other party of a fair VOL. 511, DECEMBER 20, 2006 341
opportunity to present its position before the Arbitral
Tribunal, and an award obtained through fraud or the
Uniwide Sales Realty and Resources Corporation vs. Titan-
corruption of arbitrators. Any other, more relaxed rule Ikeda Construction and Development Corporation
would result in setting at naught the basic objective of Court of Appeals Fifteenth Division in CA-G.R. SP No.
a voluntary arbitration and would reduce arbitration 37957 which modified the 17 April 1995 Decision of the 2
Balgos & Perez for petitioner. arising from Uniwide’s non-payment of certain claims
Roderick R.C. Salazar III, Devi Katerina S. billed by Titan after completion of three projects
Martinez-Negre and Michelle B. Lazaro co-counsels for covered by agreements they entered into with each
petitioner. other. Upon Uniwide’s motion to dismiss/suspend
Jose Angelito B. Bulao for private respondent. proceedings and Titan’s open court manifestation
agreeing to the suspension, Civil Case No. 98-0814 was
TINGA, J.:
suspended for it to undergo arbitration. Titan’s 4
This Petition for Review on Certiorari under Rule 45 complaint was thus re-filed with the CIAC. Before the 5
seeks the partial reversal of the 21 February 1996 CIAC, Uniwide filed an answer which was later amended
Decision of the
1
and re-amended, denying the material allegations of the
complaint, with counterclaims for refund of
_______________ overpayments, actual and exemplary damages, and
attorney’s fees. The agreements between Titan and
1
Rollo, pp. 10-33, 54-77 and 155-178. The dispositive portion of the Uniwide are briefly described below.
said decision states:
“WHEREFORE, the judgment of the CIAC herein appealed from is
hereby MODIFIED in the following respects: PROJECT 1. 6
The first agreement (Project 1) was a written drawings and specifications provided by Uniwide’s
“Construction Contract” entered into by Titan and structural engineers. The parties proceeded on the basis
Uniwide sometime in of a cost estimate of P21,301,075.77 inclusive of Titan’s
20% mark-up. Titan conceded in its complaint to having
_______________ received P15,000,000.00 of this amount. This project
was completed in the latter part of October 1992 and
1. c)The interest of 12% per annum attached to the unpaid
balances for Projects 2 and 3 is hereby REDUCED to 6% per turned over to Uniwide.
annum.
PROJECT 3. 9
Uniwide claims that Titan allegedly admitted that the building was
8
Ikeda Construction and Development Corporation completed only on 12 March 1992, which date was reflected in Titan’s
May 1991 whereby Titan undertook to construct Opposition to Partial Motion for Reconsideration dated 10 May 1996.
Uniwide’s Warehouse Club and Administration Building Rollo, pp. 285-292.
9
343
in Libis, Quezon City for a fee of P120,936,591.50,
payable in monthly progress billings to be certified to by VOL. 511, DECEMBER 20, 2006 343
Uniwide’s representative. The parties stipulated that
7 Uniwide Sales Realty and Resources Corporation vs. Titan-
the building shall be completed not later than 30 Ikeda Construction and Development Corporation
November 1991. As found by the CIAC, the building was in progress billings to be certified to by Uniwide’s
eventually finished on 15 February 1992 and turned 8 representative. It was stipulated that the project shall
10
Project 2–Edsa Central: Uniwide filed a motion for reconsideration of the 17 April
1995 decision which was denied by the CIAC in its
[Uniwide] is absolved of any liability for VAT payment on Resolution dated 6 July 1995. Uniwide accordingly filed
this project, the same being for the account of the [Titan]. On
a petition for review with the Court of Appeals, which
13
and quasi-judicial bodies, which have acquired expertise Other recognized exceptions are as follows: (1) when
because their jurisdiction is confined to specific matters, there is a very clear showing of grave abuse of
are generally accorded not only respect, but also discretion resulting in lack or loss of jurisdiction as
20
finality, especially when affirmed by the Court of when a party was deprived of a fair opportunity to
Appeals. In particular, factual findings of construction
16
present its position before the Arbitral Tribunal or when
arbitrators are final and conclusive and not reviewable an award is obtained through fraud or the corruption of
by this Court on appeal. This rule, however admits of
17
arbitrators, (2) when the findings of the Court of
21
certain exceptions. Appeals are contrary to those of the CIAC, and (3) when
22
In David v. Construction Industry and Arbitration a party is deprived of administrative due process. 23
this Court when the petitioner proves affirmatively that: of the CIAC for the reason that petitioner was requiring
(1) the award was procured by corruption, fraud or other the Court to go over each individual claim and
undue means; (2) there was evident partiality or counterclaim submitted by the parties in the CIAC. A
corruption of the arbitrators or of any of them; (3) the review of the CIAC’s findings of fact would have had the
arbitrators were guilty of misconduct in refusing to hear effect of “setting at naught the basic objective of a
evidence pertinent and material to the controversy; (4) voluntary arbitration and would reduce arbitration to a
one or more of the arbitrators were disqualified to act as largely inutile institution.” Further, petitioner therein
such under Section nine of Republic Act No. 876 and failed to show any serious error of law amounting to
willfully refrained from disclosing such disqualifications grave abuse of discretion resulting in lack of jurisdiction
or of any other misbehavior by which the rights of any on the part of the Arbitral Tribunal, in either the
party have methods employed or the results reached by the
Arbitral Tribunal, in disposing of the detailed claims of
_______________
the respective parties. In
Id., at pp. 344-373. See Petitioner’s Memorandum.
15
See David
17
v. Construction Industry and Arbitration Megaworld Globus Asia, Inc. v. DSM Construction
20
and
Commission, G.R. No. 159795, 30 July 2004, 435 SCRA 654, 666. Development Corporation, supra note 15 at p. 198.
Id.
18
Hi-Precision Steel Center, Inc. v. Lim Kim Steel Builders, Inc., G.R.
21
“additional works,” and prior approval as a requirement
No. 110434, 13 December 1993, 228 SCRA 397, 405.
Metro Construction, Inc. v. Chatham Properties, Inc., 418 Phil. 176;
22
before Titan could perform “additional works.”
365 SCRA 697 (2001). Nonetheless, Uniwide cites Article (Art.) 1724 of the
Megaworld Globus Asia, Inc. v. DSM Construction and
23
New Civil Code as basis for its claim that it is not liable
Development Corporation, supra. to pay for “additional works” it did not authorize or
G.R. No. 110434, 13 December 1993, 228 SCRA 397.
24
347
agree upon in writing. The provision states:
VOL. 511, DECEMBER 20, 2006 347 _______________
Uniwide Sales Realty and Resources Corporation vs. Titan-
Ikeda Construction and Development Corporation 418 Phil. 176; 365 SCRA 697 (2001).
25
amount because the additional works were without any Code and characterized Uniwide’s payment of the said
written authorization. amount as a voluntary fulfillment of a natural obligation.
It should be noted that the contracts do not contain The situation was characterized as being akin to
stipulations on “additional works,” Uniwide’s liability for Uniwide being a debtor who paid a debt even while it
knew that it was not legally compelled to do so. As such
debtor, Uniwide could no longer demand the refund of the right of the contractor to demand payment for
the amount already paid. additional works undertaken because payment, whether
Uniwide counters that Art. 1724 makes no distinction mistaken or not, was already made by Uniwide. Thus, it
as to whether payment for the “additional works” had would not anymore be incumbent on Titan to establish
already been made. It claims that it had made the that it had the right to demand or receive such
payments, subject to reservations, upon the false payment.
representation of Titan-Ikeda that the “additional works” But, even if the Court accepts Art. 1724 as applicable
were authorized in writing. Uniwide characterizes the in this case, such recognition does not ipso facto accord
payment as a “mistake,” and not a “voluntary” Uniwide the right to be reimbursed for payments
fulfillment under Art. 1423 of the Civil Code. already made, since Art. 1724 does not effect such right
of reimbursement. It has to be understood that Art.
_______________ 1724 does not preclude the payment to the contractor
27
Art. 1423. Obligations are civil or natural. Civil obligations give a who performs additional works without any prior written
right of action to compel their performance. Natural obligations, not authorization or agreement as to the
being based on positive law but on equity and natural law, do not grant
a right of action to enforce their performance, but after voluntary _______________
fulfillment by the obligor, they authorize the retention of what has
been delivered or rendered by reason thereof. Some natural 28
Art. 2154. If something is received when there is no right to
obligations are set forth in the following articles. demand it, and it was unduly delivered through mistake, the obligation
349 to return it arises.
VOL. 511, DECEMBER 20, 2006 349 29
Art. 2156. If the payer was in doubt whether the debt was due, he
may recover if he proves that it was not due.
Uniwide Sales Realty and Resources Corporation vs. Titan- 30
See Royal Lines, Inc. v. Court of Appeals, 227 Phil. 570; 143 SCRA
Ikeda Construction and Development Corporation 608 (1986).
Hence, it urges the application, instead, of the principle
31
See Arenas v. Court of Appeals, G.R. No. 56524, 27 January
1989, 169 SCRA 558.
of solutio indebiti under Arts. 2154 and 2156 of the
28 29
350
Civil Code. 350 SUPREME COURT REPORTS ANNOTATED
To be certain, this Court has not been wont to give an
Uniwide Sales Realty and Resources Corporation vs. Titan-
expansive construction of Art. 1724, denying, for
Ikeda Construction and Development Corporation
example, claims that it applies to constructions made of
ship vessels, or that it can validly deny the claim for
30
price for such works if the owner decides anyway to
payment of professional fees to the architect. The 31
make such payment. What the provision does preclude
present situation though presents a thornier problem. is the right of the contractor to insist upon payment for
Clearly, Art. 1724 denies, as a matter of right, payment unauthorized additional works.
to the contractor for additional works which were not Accordingly, Uniwide, as the owner who did pay the
authorized in writing by the proprietor, and the contractor for such additional works even if they had not
additional price of which was not determined in writing been authorized in writing, has to establish its own right
by the parties. to reimbursement not under Art. 1724, but under a
Yet the distinction pointed out by the Court of different provision of law. Uniwide’s burden of
Appeals is material. The issue is no longer centered on establishing its legal right to reimbursement becomes
even more crucial in the light of the general that these additional works on Project 1 were either
presumption contained in Section 3(f), Rule 131 of the authorized or documented. 33
Rules of Court that “money paid by one to another was Yet even conceding that the additional works on
due to the latter.” Project 1 were not authorized or committed into writing,
Uniwide undertakes such a task before this Court, the undisputed fact remains that Uniwide paid for these
citing the provisions on solutio indebiti under Arts. 2154 additional works. Thus, to claim a refund of payments
and 2156 of the Civil Code. However, it is not enough to made under the principle of solutio indebiti, Uniwide
prove that the payments made by Uniwide to Titan were must be able to establish that these payments were
“not due” because there was no prior authorization or made through mistake. Again, this is a factual matter
agreement with respect to additional works. There is a that would have acquired a mantle of invulnerability had
further requirement that the payment by the debtor was it been determined by both the CIAC and the Court of
made either through mistake or under a cloud of doubt. Appeals. However, both bodies failed to arrive at
In short, for the provisions on solutio indebiti to apply,
there has to be evidence establishing the frame of mind _______________
of the payor at the time the payment was made. 32
wide] has not been substantiated despite Cherrie Gow’s undertaking to do so.
But even hypothetically assuming that claim to be established, it would not
_______________ help [Uniwide] any. The presumption is that payment is made for
something that is due. Thus, [S]ection 3(f), Rule 131 of the Revised Rules of
Rollo, p. 232. On this score, the CIAC made two crucial
32 Evidence provides “that money paid by one to another was due to the latter.”
If payment was made by mistake for an obligation not due, [Uniwide] has
conclusions:
the burden of proving that claim in order to get a refund. This burden was not
The Tribunal finds that the evidence sufficiently establishes this issue in favor
discharged by [Uniwide]. Sufficient documentation surely does not establish
of the [Titan]. The fact that [Uniwide] had paid the claim for said
that payment was not due. All it establishes is carelessness on the part of
additional works implies that the additional works were actually done
[Uniwide]. Not having been contradicted and overcome[d] by any
and that they had been duly authorized. Otherwise, Jimmy Gow would not
evidence adduced by [Uniwide], the presumption enjoyed by the
have instructed his daughter-treasurer to make payments for them.
[Titan] on this issue is satisfactory in accordance with the foregoing
What [Uniwide] merely complains about is that there were no sufficient
cited procedural rule. (Emphasis supplied.)
documents that had been attached by the [Titan] in support of its billings
therefor. That claim of [Uni- See Rollo, pp. 356, 360-361.
33
351 352
VOL. 511, DECEMBER 20, 2006 351 352 SUPREME COURT REPORTS ANNOTATED
Uniwide Sales Realty and Resources Corporation vs. Titan- Uniwide Sales Realty and Resources Corporation vs. Titan-
Ikeda Construction and Development Corporation Ikeda Construction and Development Corporation
The CIAC refused to acknowledge that the additional such a conclusion. Moreover, Uniwide is unable to direct
works on Project 1 were indeed unauthorized by our attention to any pertinent part of the record that
Uniwide. Neither did the Court of Appeals arrive at a would indeed establish that the payments were made
contrary determination. There would thus be some by reason of mistake.
difficulty for this Court to agree with this most basic We note that Uniwide alleged in its petition that the
premise submitted by Uniwide that it did not authorize CIAC award in favor of Titan in the amount
the additional works on Project 1 undertaken by Titan. P5,158,364.63 as the unpaid balance in Project 3
Still, Uniwide does cite testimonial evidence from the included claims for additional works of P1,087,214.18
record alluding to a concession by employees of Titan for which no written authorization was presented.
Unfortunately, this issue was not included in its paid by Uniwide as VAT for Project 1. This conclusion
memorandum as one of the issues submitted for the was drawn from an Order of Payment dated 7 October
37
resolution of the Court. 1992 wherein Titan billed Uniwide the amount of
P2,400,000.00 as “Value Added Tax based on
Liability for the Value-Added Tax (VAT) P60,000,000.00 Contract,” computed on the basis of 4%
of P60,000,000.00. Said document which was approved
The second issue takes us into an inquiry on who, under by the President of Uniwide expressly indicated that the
the law, is liable for the payment of the VAT, in the project involved was the “UNIWIDE SALES WAREHOUSE
absence of a written stipulation on the matter. Uniwide CLUB & ADMIN BLDG.” located at “90 E. RODRIGUEZ JR.
claims that the VAT was already included in the contract AVE., LIBIS, Q.C.” The reduced base for the computation
price for Project 1. Citing Secs. 99 and 102 of the of the tax, according to the Court of Appeals, was an
National Internal Revenue Code, Uniwide asserts that indication that the parties agreed to pass the VAT for
VAT, being an indirect tax, may be shifted to the buyer Project 1 to Uniwide but based on a lower contract price.
by including it in the cash or selling price and it is Indeed, the CIAC found as follows:
entirely up to the buyer to agree or not to agree to “Without any documentary evidence than Exhibit “H” to
absorb the VAT. Thus, Uniwide concludes, if there is no
34
show the extent of tax liability assumed by [Uniwide], the
provision in the contract as to who should pay the VAT, Tribunal holds that the parties is [sic] obliged to pay only a
it is presumed that it would be the seller. 35
share of the VAT payment up to P60,000,000.00 out of the
The contract for Project 1 is silent on which party total contract price of P120,936,591.50. As explained by
should shoulder the VAT while the contract for Project 3 Jimmy Gow, VAT is paid on labor only for construction
contained a provision to the effect that Uniwide is the contracts since VAT had already been paid on the
party responsible for the payment of the VAT. Thus, 36
materials purchased. Since labor costs is [sic]
proportionately placed at 60%-40% of the contract
when Uniwide paid the amount of P2,400,000.00 as
price, simplified accounting computes VAT at 4% of
billed by Titan for VAT, it assumed that it was the VAT the contract price. Whatever is the balance for VAT that
for Project 3. However, the CIAC and the Court of remains to be paid on Project 1–Libis shall remain the
Appeals found that the same was for Project 1. obligation of [Titan]. (Emphasis supplied.)” 38
_______________
Liquidated Damages
Citing BIR Ruling No. 242, dated 6 June 1988.
34
356
can only resolve issues brought before it by the parties
356 SUPREME COURT REPORTS ANNOTATED through the TOR which functions similarly as a pre-trial
Uniwide Sales Realty and Resources Corporation vs. Titan- brief. Thus, if Uniwide’s claim for liquidated damages
Ikeda Construction and Development Corporation was not
the Rules of Court to arbitration proceedings, even in a
suppletory capacity. Hypothetically admitting that there is _______________
such a provision, suppletory application is made only if it
would not contravene a specific provision in the arbitration Black’s LAW DICTIONARY (6th Edition), p. 105.
43
rules and the spirit thereof. The Tribunal holds that such Supra note 23, at p. 405.
44
357
importation of the Rules of Court provision on
amendment to conform to evidence would contravene VOL. 511, DECEMBER 20, 2006 357
the spirit, if not the letter of the CIAC rules. This is for Uniwide Sales Realty and Resources Corporation vs. Titan-
the reason that the formulation of the Terms of Reference is Ikeda Construction and Development Corporation
done with the active participation of the parties and their raised as an issue in the TOR or in any modified or
counsel themselves. The TOR is further required to be signed amended version of it, the CIAC cannot make a ruling on
by all the parties, their respective counsel and all the it. The Rules of Court cannot be used to contravene the
members of the Arbitral Tribunal. Unless the issues thus
spirit of the CIAC rules, whose policy and objective is to
carefully formulated in the Terms of Reference were
expressly showed [sic] to be amended, issues outside thereof “provide a fair and expeditious settlement of
may not be resolved. As already noted in the Decision, “no construction disputes through a non-judicial process
attempt was ever made by the [Uniwide] to modify the TOR which ensures harmonious and friendly relations
in order to accommodate the issues related to its belated between or among the parties.” 45
counterclaim” on this issue.” (Emphasis supplied.) Further, a party may not be deprived of due process
Arbitration has been defined as “an arrangement for of law by an amendment of the complaint as provided in
taking and abiding by the judgment of selected persons Section 5, Rule 10 of the Rules of Court. In this case, as
in some disputed matter, instead of carrying it to noted by the Court of Appeals, Uniwide only introduced
established tribunals of justice, and is intended to avoid and quantified its claim for liquidated damages in its
the formalities, the delay, the expense and vexation of memorandum submitted to the CIAC at the end of the
ordinary litigation.” Voluntary arbitration, on the other
43
arbitration proceeding. Verily, Titan was not given a
hand, involves the reference of a dispute to an impartial chance to present evidence to counter Uniwide’s claim
body, the members of which are chosen by the parties for liquidated damages.
themselves, which parties freely consent in advance to Uniwide alludes to an alleged judicial admission made
abide by the arbitral award issued after proceedings by Engr. Luzon Tablante wherein he stated that Project
where both parties had the opportunity to be heard. The 1 was completed on 10 March 1992. It now claims that
basic objective is to provide a speedy and inexpensive by virtue of Engr. Tablante’s statement, Titan had
admitted that it was in delay. We disagree. The before it can be paid by Uniwide; (2) whether or not
testimony of Engr. Tablante was offered only to prove there was overpricing of the project; (3) whether or not
that Project 1 was indeed completed. It was not offered the P15,000,000.00 paid by Uniwide to Titan for Project
to prove the fact of delay. It must be remembered that 2 constitutes full payment; and (4) whether or not Titan
the purpose for which evidence is offered must be can be held liable for defective construction of Project 2.
specified because such evidence may be admissible for The CIAC, as affirmed by the Court of Appeals, held
several purposes under the doctrine of multiple Uniwide liable for deficiency relating to Project 2 in the
admissibility, or may be admissible for one purpose and amount of P6,301,075.77. It is nonetheless alleged by
not for another, otherwise the adverse party cannot Uniwide that Titan failed to submit any “as-built” plans
interpose the proper objection. Evidence submitted for for Project 2, such plans allegedly serving as a condition
one purpose may not be considered for any other precedent for payment. Uniwide further claims that
purpose. Furthermore, even assuming, for the sake of
46
Titan had substantially overcharged Uniwide for Project
argument, that said testimony on the date of 2, there being uncontradicted expert testimony that the
completion of Project 1 is admitted, the establishment total cost of Project 2 did not exceed P7,812,123.60.
of the mere fact of delay is not sufficient for the Furthermore, Uniwide alleged that the works performed
imposition of liquidated damages. It must further be were structurally defective, as evidenced by the
shown that delay was attribut- structural damage on four columns as observed on
ocular inspection by the CIAC and confirmed by Titan’s
_______________ project manager.
RULES
45
OF PROCEDURE GOVERNING CONSTRUCTION On the necessity of submitting “as-built” plans, this
ARBITRATION, Art. 1, Sec. 1. Court rules that the submission of such plans is not a
Regalado, Remedial Law Compendium (Vol. II), pp. 694-695.
46
pre-requisite for Titan to be paid by Uniwide. The
358 argument that said plans are required by Section 308 of
358 SUPREME COURT REPORTS ANNOTATED Presidential Decree No. 1098 (National Building Code)
Uniwide Sales Realty and Resources Corporation vs. Titan- and by Section 2.11 of its Implementing Rules before
Ikeda Construction and Development Corporation payment can be made is untenable. The purpose of the
able to the contractor if not otherwise justifiable. law is “to safeguard life, health, property, and public
Contrarily, Uniwide’s belated claim constitutes an welfare, consistent with the principles of sound
admission that the delay was justified and implies a 359
waiver of its right to such damages. VOL. 511, DECEMBER 20, 2006 359
Uniwide Sales Realty and Resources Corporation vs. Titan-
Project 2: “as-built” plans, overpricing, defective Ikeda Construction and Development Corporation
construction environmental management and control.” The
submission of these plans is necessary only in
To determine whether or not Uniwide is liable for the furtherance of the law’s purpose by setting minimum
unpaid balance of P6,301,075.77 for Project 2, we need standards and requirements to control the “location,
to resolve four sub-issues, namely: (1) whether or not it site, design, quality of materials, construction, use,
was necessary for Titan to submit “as-built” plans occupancy, and maintenance” of buildings constructed
and not as a requirement for payment to the conspiracy. As a matter of fact, [Uniwide]’s own principal
contractor. The testimony of Engr. Tablante to the
47 witness, Jimmy Gow, admitted on cross-examination that
effect that the “as-built” plans are required before he does not have any direct evidence to prove his
payment can be claimed by Titan is a mere legal charge of connivance or complicity between the
[Titan] and his own representatives. He only made that
conclusion which is not binding on this Court.
conclusion by the process of his own “logical reasoning”
Uniwide claims that, according to one of its arising from his consultation with other contractors who gave
consultants, the true price for Project 2 is only him a much lower estimate for the construction of the Dau
P7,812,123.60. The CIAC and the Court of Appeals, Project. There is thus no reason to invalidate the
however, found the testimony of this consultant suspect binding character of Exhibit “2-A” which, it is
and ruled that the total contract price for Project 2 is significant to point out, is [Uniwide]’s own
P21,301,075.77. The CIAC held: evidence.” (Emphasis supplied.)
49
“The Cost Estimate for Architectural and Site Accordingly, deducting the P15,000,000.00 already paid
Development Works for the EDSA Central, Dau Branch by Uniwide from the total contract price of
Project (Exhibit “2-A” for [Uniwide] and made as a common P21,301,075.77, the unpaid balance due for Project 2 is
exhibit by [Titan] who had it marked at [sic] its own Exhibit P6,301,075.77. This is the same amount reflected in the
“U”), which was admittedly prepared by Fermindoza and Order of Payment prepared by Uniwide’s representative,
Associates, [Uniwide]’s own architects, shows that the
Le Consultech, Inc. and signed by no less than four top
amount of P17,750,896.48 was arrived at. Together with
the agreed upon mark-up of 20% on said amount, the officers and architects of Le Consultech, Inc. endorsing
total project cost was P21,301,075.77. for payment by Uniwide to Titan the amount of
The Tribunal holds that the foregoing document is binding P6,301,075.77. 50
upon the [Uniwide], it being the mode agreed upon by which Uniwide asserts that Titan should not have been
its liability for the project cost was to be allowed to recover on Project 2 because the said project
determined.” (Emphasis supplied.)
48
was defective and would require repairs in the amount
Indeed, Uniwide is bound by the amount indicated in the of P800,000.00. It claims that the CIAC and the Court of
above document. Claims of connivance or fraudulent Appeals should have applied Nakpil and Sons v. Court of
conspiracy between Titan and Uniwide’s representatives Appeals and Art. 1723 of the New Civil Code holding a
51
which, it is alleged, grossly exaggerated the price may contractor responsible for damages if the edifice
properly be dismissed. As held by the CIAC: constructed falls within fifteen years from completion on
account of defects in the construction or the use of
_______________
materials of inferior quality furnished by him or due to
NATIONAL BUILDING CODE OF THE PHILIPPINES, Sec. 102.
47 any violation of the terms of the contract.
Rollo, p. 238.
48
On this matter, the CIAC conducted an ocular
360 inspection of the premises on 30 January 1995. What
360 SUPREME COURT REPORTS ANNOTATED transpired in the said ocular inspection is described
Uniwide Sales Realty and Resources Corporation vs. Titan- thus:
Ikeda Construction and Development Corporation
_______________
“The Tribunal holds that [Uniwide] has not introduced
any evidence to sustain its charge of fraudulent Id., at p. 239.
49
Rollo, p. 443.
50
to the old columns where cracks were discovered. The
G.R. No. L-47851, 3 October 1986, 144 SCRA 596.
51
Id., at p. 242.
53
_______________ 364
364 SUPREME COURT REPORTS ANNOTATED
Supra note 23, at pp. 405-406.
54
Camitan vs. Court of Appeals
Supra note 16, at pp. 666-667.
55
363 © Copyright 2020 Central Book Supply, Inc. All rights reserved.
VOL. 511, DECEMBER 20, 2006 363
Uniwide Sales Realty and Resources Corporation vs. Titan-
Ikeda Construction and Development Corporation
relaxed rule would result in setting at naught the
basic objective of a voluntary arbitration and would
reduce arbitration to a largely inutile institution.”
(Emphasis supplied.)
WHEREFORE, premises considered, the petition is
DENIED and the Decision of the Court of Appeals dated
21 February 1996 in CA-G.R. SP No. 37957 is hereby
AFFIRMED.
SO ORDERED.
Quisumbing (Chairperson), Carpio, Carpio-
Morales and Velasco, Jr., JJ., concur.
Petition denied, judgment affirmed.
Notes.—Arbitration agreements are valid, binding,
enforceable and not contrary to public policy such that
when there obtains a written provision for arbitration
which is not complied with, the trial court should
suspend the proceedings and order the parties to
proceed to arbitration in accordance with the terms of
their agreement. (European Resources and
196 SUPREME COURT REPORTS ANNOTATED promoted by the State. Thus, petitioner correctly cites
Benguet Corporation vs. Department of Environment and several cases whereby arbitration clauses have been upheld
by this Court.
Natural Resources-Mines Adjudication Board Same; Same; Distinction between Voluntary and
G.R. No. 163101. February 13, 2008. *
Compulsory Arbitration.—J.G. Realty’s contention, that prior
BENGUET CORPORATION, petitioner, vs. DEPARTMENT resort to arbitration is unavailing in the instant case because
OF ENVIRONMENT AND NATURAL RESOURCES-MINES the POA’s mandate is to arbitrate disputes involving mineral
ADJUDICATION BOARD and J.G. REALTY AND MINING agreements, is misplaced. A distinction must be made
CORPORATION, respondents. between voluntary and compulsory arbitration. In Ludo and
Arbitration; Mines Adjudication Board; Appeals; A Luym Corporation v. Saordino, 395 SCRA 451 (2003), the
decision of the Mines Adjudication Board (MAB) must first be Court had the occasion to distinguish between the two types
appealed to the Court of Appeals (CA) under Rule 43 of the of arbitrations: Comparatively, in Reformist Union of R.B.
Rules of Court before recourse to the Court may be had.— Liner, Inc. vs. NLRC, 266 SCRA 713 (1997), compulsory
The last paragraph of Section 79 of Republic Act No. (RA) arbitration has been defined both as “the process of
7942 or the “Philippine Mining Act of 1995” states, “A settlement of labor disputes by a government agency
petition for review by certiorari and question of law may which has the authority to investigate and to make an
award which is binding on all the parties, and as a mode of
_______________ arbitration where the parties are compelled to accept the
resolution of their dispute through arbitration by a third
SECOND DIVISION.
*
party.” While a voluntary arbitrator is not part of the
197
governmental unit or labor department’s personnel,
VOL. 545, FEBRUARY 13, 2008 197 said arbitrator renders arbitration services provided for under
Benguet Corporation vs. Department of Environment and labor laws. (Emphasis supplied.)
Natural Resources-Mines Adjudication Board Civil Law; Unjust Enrichment; Definition of Unjust
be filed by the aggrieved party with the Supreme Court Enrichment; There is no unjust enrichment when the person
within thirty (30) days from receipt of the order or decision of who will benefit has a valid claim to such benefit.—In Car
the [MAB].” However, this Court has already invalidated such Cool Philippines, Inc. v.
provision in Carpio v. Sulu Resources Development Corp., 198
387 SCRA 128 (2002) ruling that a decision of the MAB must 198 SUPREME COURT REPORTS
first be appealed to the Court of Appeals (CA) under Rule 43 ANNOTATED
of the Rules of Court, before recourse to this Court may be Benguet Corporation vs. Department of Environment and
had.
Natural Resources-Mines Adjudication Board
Same; Same; A contractual stipulation that requires
Ushio Realty and Development Corporation, 479 SCRA
prior resort to voluntary arbitration before the parties can go
404 (2006), we defined unjust enrichment, as follows: We
directly to court is not illegal and is in fact promoted by the
have held that “[t]here is unjust enrichment when a
State.—In RA 9285 or the “Alternative Dispute Resolution Act
person unjustly retains a benefit to the loss of another, or
of 2004,” the Congress reiterated the efficacy of arbitration
when a person retains money or property of another against
as an alternative mode of dispute resolution by stating in
the fundamental principles of justice, equity and good
Sec. 32 thereof that domestic arbitration shall still be
conscience.” Article 22 of the Civil Code provides that
governed by RA 876. Clearly, a contractual stipulation that
“[e]very person who through an act of performance by
requires prior resort to voluntary arbitration before the
another, or any other means, acquires or comes into
parties can go directly to court is not illegal and is in fact
possession of something at the expense of the latter without Benguet and J.G. Realty, and excluded Benguet from the
just or legal ground, shall return the same to him.” The joint Mineral Production Sharing Agreement (MPSA)
principle of unjust enrichment under Article 22 requires two application over four mining claims. The March 17, 2004
conditions: (1) that a person is benefited without a valid basis Resolution denied Benguet’s Motion for Reconsideration.
or justification, and (2) that such benefit is derived at
The Facts
another’s expense or damage. There is no unjust
enrichment when the person who will benefit has a On June 1, 1987, Benguet and J.G. Realty entered into a
valid claim to such benefit. (Emphasis supplied.) RAWOP, wherein J.G. Realty was acknowledged as the
owner of four mining claims respectively named as
SPECIAL CIVIL ACTION in the Supreme Court. Certiorari. Bonito-I, BonitoII, Bonito-III, and Bonito-IV, with a total
area of 288.8656 hectares, situated in Barangay
The facts are stated in the opinion of the Court. Luklukam, Sitio Bagong Bayan, Municipality of Jose
Reynaldo P. Mendoza for petitioner. Panganiban, Camarines Norte. The parties also
Cortina, Buted & Coloma Law Offices for J.G. executed a Supplemental Agreement dated June 1,
5
Realty & Mining Corporation. 1987. The mining claims were covered by MPSA
Application No. APSA-V-0009 jointly filed by J.G. Realty
VELASCO, JR., J.: as claimowner and Benguet as operator.
In the RAWOP, Benguet obligated itself to perfect the
The instant petition under Rule 65 of the Rules of Court rights to the mining claims and/or otherwise acquire the
seeks the annulment of the December 2, 2002 mining rights to the mineral claims. Within 24 months
Decision and March 17, 2004 Resolution of the
1 2
from the execution of the RAWOP, Benguet should also
Department of Environment and Natural Resources- cause the examination of the mining claims for the
Mines Adjudication Board (DENR-MAB) in MAB Case No. purpose of determining whether or not they are worth
0124-01 (Mines Administrative Case No. R-M-2000-01) developing with reasonable probability of profitable
entitled Benguet Corporation (Benguet) v. J.G. Realty production. Benguet undertook also to furnish J.G.
and Mining Corporation (J.G. Realty). The December 2, Realty with a report on the examination, within a
2002 Decision upheld the March 19, 2001 Decision of 3
reasonable time after the completion of the
the MAB Panel of Arbitrators (POA) which examination. Moreover, also within the examination
_______________
period, Benguet shall conduct all necessary exploration
in accordance with a prepared exploration program. If it
Rollo, pp. 25-38.
1 chooses to do so and before the expiration of the
Id., at pp. 39-41.
2
examination period, Benguet may undertake to develop
Id., at pp. 42-47.
3
In response, Benguet’s Manager for Legal Services, the Legaspi City POA, Region V, docketed as DENR Case
Reynaldo P. Mendoza, wrote J.G. Realty a letter dated No. 2000-01 and entitled J.G. Realty v. Benguet.
March 8, 1999, therein alleging that Benguet complied
8
On March 19, 2001, the POA issued a
with its obligations under the RAWOP by investing Decision, dwelling upon the issues of (1) whether the
10
PhP42.4 million to rehabilitate the mines, and that the arbitrators had jurisdiction over the case; and (2)
commercial operation was hampered by the non- whether Benguet violated the RAWOP justifying the
issuance of a Mines Temporary Permit by the Mines and
unilateral cancellation of the RAWOP by J.G. Realty. The substantial rights of Benguet under the contract
dispositive portion stated: to the unjust enrichment of JG Realty.
12
when it sustained the cancellation of the Royalty appealed to the Court of Appeals (CA) under Rule 43 of
Agreement for alleged breach of contract despite the Rules of Court, before recourse to this Court may be
the absence of evidence. had. We held, thus:
“To summarize, there are sufficient legal footings authorizing
3. 3.The Questioned Decision of the Honorable Board a review of the MAB Decision under Rule 43 of the Rules of
in cancelling the RAWOP prejudice[d] the Court. First, Section 30 of Article VI of the 1987 Constitution,
mandates that “[n]o law shall be passed increasing the
appellate jurisdiction of the Supreme Court as provided in Fourth, the Court realizes that under Batas
this Constitution without its advice and consent.” On the Pambansa (BP) Blg. 129 as amended by RA No. 7902, factual
other hand, Section 79 of RA No. 7942 provides that controversies are usually involved in decisions of quasi-
decisions of the MAB may be reviewed by this Court on a judicial bodies; and the CA, which is likewise tasked to
“petition for review by certiorari.” This provision is obviously resolve questions of fact, has more elbow room to resolve
an expansion of the Court’s appellate jurisdiction, an them. By including questions of fact among the issues that
expansion to which this Court has not consented. may be raised in an appeal from quasi-judicial agencies to
Indiscriminate enactment of legislation enlarging the the CA, Section 3 of Revised Administrative Circular No. 1-95
appellate jurisdiction of this Court would unnecessarily and Section 3 of Rule 43 explicitly expanded the list of such
burden it. issues.
Second, when the Supreme Court, in the exercise of its According to Section 3 of Rule 43, “[a]n appeal under this
rulemaking power, transfers to the CA pending cases Rule may be taken to the Court of Appeals within the period
involving a review of a quasi-judicial body’s decisions, such and in the manner herein provided whether the appeal
transfer relates only to procedure; hence, it does not impair involves questions of fact, of law, or mixed questions of fact
the substantive and vested rights of the parties. The and law.” Hence, appeals from quasi-judicial agencies even
aggrieved party’s right to appeal is preserved; what is only on questions of law may be brought to the CA.
changed is only the procedure by which the appeal is to be Fifth, the judicial policy of observing the hierarchy of
made or decided. The parties still have a remedy and a courts dictates that direct resort from administrative
competent tribunal to grant this remedy. agencies to this Court will not be entertained, unless the
Third, the Revised Rules of Civil Procedure included Rule redress desired cannot be obtained from the appropriate
43 to provide a uniform rule on appeals from quasi-judicial lower tribunals, or unless exceptional and compelling
agencies. Under the rule, appeals from their judgments and circumstances justify availment of a remedy falling within
final orders are now required to be brought to the CA on a and calling for the exercise of our primary jurisdiction.” 14
verified petition for review. A quasi-judicial agency or body The above principle was reiterated in Asaphil
has been defined as an organ of government, other than a Construction and Development Corporation v. Tuason,
court or legislature, which affects the rights of private parties Jr. (Asaphil). However, the Carpio ruling was not applied
15
through either adjudication or rule-making. MAB falls under to Asaphil as the petition in the latter case was filed in
this definition; hence, it is no different from the other quasi-
1999 or three years before the promulgation
judicial bodies enumerated under Rule 43. Besides, the
of Carpio in 2002. Here, the petition was filed on April
_______________ 28, 2004 when the Carpio decision was already
applicable, thus Benguet should have filed the appeal
G.R. No. 148267, August 8, 2002, 387 SCRA 128.
13
with the CA.
204
204 SUPREME COURT REPORTS ANNOTATED _______________
Benguet Corporation vs. Department of Environment and
Id., at pp. 138-141.
14
Natural Resources-Mines Adjudication Board G.R. No. 134030, April 25, 2006, 488 SCRA 126, 133.
15
11.02 Court Action
No action shall be instituted in court as to any matter in Moreover, the MAB ruled that the contractual provision
dispute as hereinabove stated, except to enforce the decision on arbitration merely provides for an additional forum or
of the majority of the Arbitrators.
16 venue and does not divest the POA of the jurisdiction to
Thus, Benguet argues that the POA should have first hear the case. 19
referred the case to voluntary arbitration before taking In its July 20, 2004 Comment, J.G. Realty reiterated
20
cognizance of the case, citing Sec. 2 of RA 876 on the above rulings of the POA and MAB. It argued that RA
persons and matters subject to arbitration. 7942 or the “Philippine Mining Act of 1995” is a special
On the other hand, in denying such argument, the law which should prevail over the stipulations of the
POA ruled that: parties and over a general law, such as RA 876. It also
argued that the POA cannot be considered as a “court”
_______________ under the contemplation of RA 876 and that
jurisprudence saying that there must be
Rollo, p. 90.
16
206
_______________
206 SUPREME COURT REPORTS ANNOTATED
Id.,
17
at p. 44. BF Corporation v. Court of Appeals, G.R. No. 120105, March 27,
21
Id.,
18
at p. 31. 1998, 288 SCRA 267; Puromines v. Court of Appeals, G.R. No. 91228,
Id.,
19
at p. 32. March 22, 1993, 220 SCRA 281; General Insurance and Surety
Id.,
20
at pp. 150-273. Corporation v. Union Insurance Society of Canton, et al., G.R. Nos.
207 30475-76, November 22, 1989, 179 SCRA 530; Gascon v. Arroyo, G.R.
VOL. 545, FEBRUARY 13, 2008 207 No. 78389, October 16, 1989, 178 SCRA 582; Bengson v. Chan, No. L-
27283, July 29, 1977, 78 SCRA 113; Mindanao Portland Ce
Benguet Corporation vs. Department of Environment and 208
Natural Resources-Mines Adjudication Board 208 SUPREME COURT REPORTS ANNOTATED
prior resort to arbitration before filing a case with the Benguet Corporation vs. Department of Environment and
courts is inapplicable to the instant case as the POA is Natural Resources-Mines Adjudication Board
itself already engaged in arbitration. Moreover, the contention that RA 7942 prevails over RA
On this issue, we rule for Benguet. 876 presupposes a conflict between the two laws. Such
Sec. 2 of RA 876 elucidates the scope of arbitration: is not the case here. To reiterate, availment of voluntary
“Section 2. Persons and matters subject to arbitration.——
arbitration before resort is made to the courts or quasi-
Two or more persons or parties may submit to the
arbitration of one or more arbitrators any controversy judicial agencies of the government is a valid
existing between them at the time of the submission contractual stipulation that must be adhered to by the
and which may be the subject of an action, or the parties. As stated in Secs. 6 and 7 of RA 876:
parties to any contract may in such contract agree to “Section 6. Hearing by court.——A party aggrieved by the
settle by arbitration a controversy thereafter arising failure, neglect or refusal of another to perform under
between them. Such submission or contract shall be an agreement in writing providing for arbitration may
valid, enforceable and irrevocable, save upon such petition the court for an order directing that such
grounds as exist at law for the revocation of any arbitration proceed in the manner provided for in such
contract. agreement. Five days notice in writing of the hearing of
Such submission or contract may include question[s] such application shall be served either personally or by
arising out of valuations, appraisals or other controversies registered mail upon the party in default. The court shall
which may be collateral, incidental, precedent or subsequent hear the parties, and upon being satisfied that the
to any issue between the parties.” (Emphasis supplied.) making of the agreement or such failure to comply
In RA 9285 or the “Alternative Dispute Resolution Act of therewith is not in issue, shall make an order directing
2004,” the Congress reiterated the efficacy of the parties to proceed to arbitration in accordance
with the terms of the agreement. If the making of the
arbitration as an alternative mode of dispute resolution
agreement or default be in issue the court shall
by stating in Sec. 32 thereof that domestic arbitration proceed to summarily hear such issue. If the finding
shall still be governed by RA 876. Clearly, a contractual be that no agreement in writing providing for
stipulation that requires prior resort to voluntary arbitration was made, or that there is no default in
arbitration before the parties can go directly to court is the proceeding thereunder, the proceeding shall be
not illegal and is in fact promoted by the State. Thus, dismissed. If the finding be that a written provision for
petitioner correctly cites several cases whereby arbitration was made and there is a default in
arbitration clauses have been upheld by this Court. 21 proceeding thereunder, an order shall be made
summarily directing the parties to proceed with the
_______________ arbitration in accordance with the terms thereof.
xxxx and Luym Corporation v. Saordino, the Court had the
Section 7. Stay of civil action.——If any suit or proceeding occasion to distinguish between the two types of
be brought upon an issue arising out of an agreement arbitrations:
providing for the arbitration thereof, the court in which such “Comparatively, in Reformist Union of R.B. Liner, Inc. vs.
suit or proceeding is pending, upon being satisfied that the NLRC, compulsory arbitration has been defined both as “the
issue involved in such suit or proceeding is referable to process of settlement of labor disputes by a government
arbitration, shall stay the action or proceeding until an agency which has the authority to investigate and to
arbitration has been had in accordance with the make an award which is binding on all the parties, and as a
mode of arbitration where the parties are compelled to
_______________
accept the resolution of their dispute through arbitration by a
ment Corporation v. McDonough Construction Company of Florida, third party.” While a voluntary arbitrator is not part of the
No. L-23390, April 24, 1967, 19 SCRA 808. governmental unit or labor department’s per
209
_______________
VOL. 545, FEBRUARY 13, 2008 209
Benguet Corporation vs. Department of Environment and Supra at p. 285.
22
filed with the courts or quasi-judicial agencies, on There is a clear distinction between compulsory and
motion of the defendant, the court or quasi-judicial voluntary arbitration. The arbitration provided by the
agency shall determine whether such contractual POA is compulsory, while the nature of the arbitration
provision for arbitration is sufficient and effective. If in provision in the RAWOP is voluntary, not involving any
affirmative, the court or quasijudicial agency shall then government agency. Thus, J.G. Realty’s argument on
order the enforcement of said provision. Besides, in BF this matter must fail.
Corporation v. Court of Appeals, we already ruled: As to J.G. Realty’s contention that the provisions of
“In this connection, it bears stressing that the lower court has RA 876 cannot apply to the instant case which involves
not lost its jurisdiction over the case. Section 7 of Republic an administrative agency, it must be pointed out that
Act No. 876 provides that proceedings therein have only
Section 11.01 of the RAWOP states that:
been stayed. After the special proceeding of arbitration has
“[Any controversy with regard to the contract] shall not be
been pursued and completed, then the lower court may
cause of any action of any kind whatsoever in any court
confirm the award made by the arbitrator.” 22
release to [sic] BENGUET from any further liability to In the instant case, the obligation of Benguet to pay
the OWNER of the amounts represented by such royalties to J.G. Realty has been admitted and supported
deposits.” (Emphasis supplied.)
by the provisions of the RAWOP. Thus, the burden to
Evidently, the RAWOP itself provides for the mode of prove such obligation rests on Benguet.
royalty payment by Benguet. The fact that there was It should also be borne in mind that MPSA Application
the previous practice whereby J.G. Realty picked-up the No. APSA-V-0009 has been pending with the MGB for a
checks from Benguet is unavailing. The mode of considerable length of time. Benguet, in the RAWOP,
payment is embodied in a contract between the parties. obligated itself to perfect the rights to the mining claims
As such, the contract must be considered as the law and/or otherwise acquire the mining rights to the
between the parties and binding on both. Thus, after
26
215
case
Based on the foregoing discussion, the cancellation of VOL. 545, FEBRUARY 13, 2008 215
the RAWOP was based on valid grounds and is, TSPIC Corporation vs. TSPIC Employees Union (FFW)
therefore, justified. The necessary implication of the SO ORDERED.
cancellation is the cessation of Benguet’s right to Quisumbing (Chairperson), Carpio and Carpio-
prosecute MPSA Application No. APSA-V-0009 and to Morales, JJ., concur.
further develop such mining claims. Tinga, J., In the result.
In Car Cool Philippines, Inc. v. Ushio Realty and Petition dismissed, judgment and resolution affirmed.
Development Corporation, we defined unjust Note.—Findings of the Arbitration Board affirmed by
enrichment, as follows: the trial court and the Court of Appeals and supported
“We have held that “[t]here is unjust enrichment when a by substantial evidence should be accorded not only
person unjustly retains a benefit to the loss of another, or respect but finality. (National Power Corporation vs.
when a person retains money or property of another against Alonzo-Legasto, 443 SCRA 342 [2004])
the fundamental principles of justice, equity and good
conscience.” Article 22 of the Civil Code provides that ——o0o——
“[e]very person who through an act of performance by
another, or any other means, acquires or comes into © Copyright 2020 Central Book Supply, Inc. All rights reserved.
possession of something at the expense of the latter without
just or legal ground, shall return the same to him.” The
principle of unjust enrichment under Article 22 requires two
conditions: (1) that a person is benefited without a valid basis
or justification, and (2) that such benefit is derived at
another’s expense or damage.
There is no unjust enrichment when the person who
will benefit has a valid claim to such
benefit.” (Emphasis supplied.)
28
VELASCO, JR., J.: 8
8 SUPREME COURT REPORTS ANNOTATED
In our jurisdiction, the policy is to favor alternative
methods of resolving disputes, particularly in civil and
Korea Technologies Co., Ltd. vs. Lerma
commercial disputes. Arbitration along with mediation, On October 14, 1997, PGSMC entered into a Contract of
conciliation, and negotiation, being inexpensive, speedy Lease with Worth Properties, Inc. (Worth) for use of
3
and less hostile methods have long been favored by this Worth’s 5,079-square meter property with a 4,032-
Court. The petition before us puts at issue an arbitration square meter warehouse building to house the LPG
clause in a contract mutually agreed upon by the parties manufacturing plant. The monthly rental was PhP
stipulating that they would submit themselves to 322,560 commencing on January 1, 1998 with a 10%
arbitration in a foreign country. Regrettably, instead of annual increment clause. Subsequently, the
hastening the resolution of their dispute, the parties machineries, equipment, and facilities for the
wittingly or unwittingly prolonged the controversy. manufacture of LPG cylinders were shipped, delivered,
Petitioner Korea Technologies Co., Ltd. (KOGIES) is a and installed in the Carmona plant. PGSMC paid KOGIES
Ko-rean corporation which is engaged in the supply and USD 1,224,000.
installation of Liquefied Petroleum Gas (LPG) Cylinder However, gleaned from the Certificate executed by
4
manufacturing plants, while private respondent Pacific the parties on January 22, 1998, after the installation of
General Steel Manufacturing Corp. (PGSMC) is a the plant, the initial operation could not be conducted
domestic corporation. as PGSMC encountered financial difficulties affecting the
On March 5, 1997, PGSMC and KOGIES executed a supply of materials, thus forcing the parties to agree
Con-tract whereby KOGIES would set up an LPG
1
that KOGIES would be deemed to have completely
Cylinder Manufacturing Plant in Carmona, Cavite. The complied with the terms and conditions of the March 5,
contract was executed in the Philippines. On April 7, 1997 contract.
1997, the parties executed, in Korea, an Amendment for
For the remaining balance of USD306,000 for the plant. Five days later, PGSMC filed before the Office of
installation and initial operation of the plant, PGSMC the Public Prosecutor an Affidavit-Complaint
issued two postdated checks: (1) BPI Check No. for Estafa dock-eted as I.S. No. 98-03813 against Mr.
0316412 dated January 30, 1998 for PhP 4,500,000; and Dae Hyun Kang, President of KOGIES.
(2) BPI Check No. 0316413 dated March 30, 1998 for On June 15, 1998, KOGIES wrote PGSMC informing
PhP 4,500,000. 5
the latter that PGSMC could not unilaterally rescind their
When KOGIES deposited the checks, these were contract nor dismantle and transfer the machineries and
dishonored for the reason “PAYMENT STOPPED.” Thus, equipment on mere imagined violations by KOGIES. It
on May 8, 1998, KOGIES sent a demand letter to PGSMC 6
also insisted that their disputes should be settled by
threatening criminal action for violation of Batas arbitration as agreed upon in Article 15, the arbitration
Pambansa Blg. 22 in case of nonpayment. On the same clause of their contract.
date, the wife of PGSMC’s President faxed a letter dated On June 23, 1998, PGSMC again wrote KOGIES
May 7, 1998 to KOGIES’ President who was then staying reiterating the contents of its June 1, 1998 letter
at a Makati City hotel. She complained that not only did threatening that the machineries, equipment, and
KOGIES deliver a different brand of facilities installed in the plant would be dismantled and
transferred on July 4, 1998. Thus, on July 1, 1998,
_______________ KOGIES instituted an Application for Arbitration before
Id., at pp. 208-218; signed by PGSMC President Honorio Santiago
3
the Korean Commercial Arbitration Board (KCAB) in
and Worth President Wilson L. Chua. Seoul, Korea pursuant to Art. 15 of the Contract as
Id., at p. 95; signed by KOGIES’ President Dae Hyun Kang and
4
amended.
PGSMC President Honorio Santiago. On July 3, 1998, KOGIES filed a Complaint for Specific
Id., at p. 207.
5
Id., at p. 221.
6 Performance, docketed as Civil Case No. 98-
9 117 against PGSMC before the Muntinlupa City
8
On May 14, 1998, PGSMC replied that the two checks Id., at pp. 47-51; dated July 1, 1998.
8
10
it issued KOGIES were fully funded but the payments
were stopped for reasons previously made known to 10 SUPREME COURT REPORTS ANNOTATED
KOGIES. 7 Korea Technologies Co., Ltd. vs. Lerma
On June 1, 1998, PGSMC informed KOGIES that (RTC). The RTC granted a temporary restraining order
PGSMC was canceling their Contract dated March 5, (TRO) on July 4, 1998, which was subsequently
1997 on the ground that KOGIES had altered the extended until July 22, 1998. In its complaint, KOGIES
quantity and lowered the quality of the machineries and alleged that PGSMC had initially admitted that the
equipment it delivered to PGSMC, and that PGSMC checks that were stopped were not funded but later on
would dismantle and transfer the machineries, claimed that it stopped payment of the checks for the
equipment, and facilities installed in the Car-mona reason that “their value was not received” as the former
allegedly breached their contract by “altering the After the parties submitted their Memoranda, on July
quantity and lowering the quality of the machinery and 23, 1998, the RTC issued an Order denying the
equipment” installed in the plant and failed to make the application for a writ of preliminary injunction, reasoning
plant operational although it earlier certified to the that PGSMC had paid KOGIES USD 1,224,000, the value
contrary as shown in a January 22, 1998 Certificate. of the machineries and equipment as shown in the
Likewise, KOGIES averred that PGSMC violated Art. 15 of contract such that KOGIES no longer had proprietary
their Contract, as amended, by unilaterally rescinding rights over them. And finally, the RTC held that Art. 15
the contract without resorting to arbitration. KOGIES of the Contract as amended was invalid as it tended to
also asked that PGSMC be restrained from dismantling oust the trial court or any other court jurisdiction over
and transferring the machinery and equipment installed any dispute that may arise between the parties.
in the plant which the latter threatened to do on July 4, KOGIES’ prayer for an injunctive writ was denied. The 10
stipulated in the contract; that KOGIES was not entitled the quantity and lowered the quality of the machinery,
to the PhP 9,000,000 covered by the checks for failing equipment, and facilities it delivered to the plant. It
to completely install and make the plant operational; claimed that it had performed all the undertakings
and that KOGIES was liable for damages amounting to under the contract and had already produced certified
PhP 4,500,000 for altering the quantity and lowering the samples of LPG cylinders. It averred that whatever was
quality of the machineries and equipment. Moreover, unfinished was PGSMC’s fault since it failed to procure
PGSMC averred that it has already paid PhP 2,257,920 raw materials due to lack of funds. KOGIES, relying
in rent (covering January to July 1998) to Worth and it on Chung Fu Industries (Phils.), Inc. v. Court of
was not willing to further shoulder the cost of renting Appeals, insisted that the arbitration clause was
12
_______________
without question valid.
Korea Technologies Co., Ltd. vs. Lerma G.R. No. 96283, February 25, 1992, 206 SCRA 545.
12
Supra note 12.
15
contract was not merely for machinery and facilities granting inspection of the plant and denying dismissal
worth USD 1,224,000 but was for the sale of an “LPG of PGSMC’s compulsory counterclaims.
manufacturing plant” consisting of “supply of all the Ten days after, on October 12, 1998, without waiting
machinery and facilities” and “transfer of technology” for the resolution of its October 2, 1998 urgent motion
for a total contract price of USD 1,530,000 such that the for reconsideration, KOGIES filed before the Court of
dismantling and transfer of the machinery and facilities Appeals (CA) a petition for certiorari docketed as CA-
18
would result in the dismantling and transfer of the very G.R. SP No. 49249, seeking annulment of the July 23,
plant itself to the great prejudice of KOGIES as the still 1998 and September 21, 1998 RTC Orders and praying
unpaid owner/seller of the plant. Moreover, KOGIES for the issuance of writs of prohibition, mandamus, and
points out that the arbitration clause under Art. 15 of preliminary injunction to enjoin the RTC and PGSMC
the Contract as amended was a valid arbitration from inspecting, dismantling, and transferring the
stipulation under Art. 2044 of the Civil Code and as held machineries and equipment in the Carmona plant, and
by this Court in Chung Fu Industries (Phils.), Inc. 15
to direct the RTC to enforce the specific agreement on
In the meantime, PGSMC filed a Motion for Inspection arbitration to resolve the dispute.
of Things to determine whether there was indeed
16
In the meantime, on October 19, 1998, the RTC
alteration of the quantity and lowering of quality of the denied KOGIES’ urgent motion for reconsideration and
machineries and equipment, and whether these were directed the Branch Sheriff to proceed with the
properly installed. KO-GIES opposed the motion positing inspection of the machineries and equipment in the
that the queries and issues raised in the motion for plant on October 28, 1998. 19
inspection fell under the coverage of the arbitration Thereafter, KOGIES filed a Supplement to the
clause in their contract. Petition in CA-G.R. SP No. 49249 informing the CA
20
On September 21, 1998, the trial court issued an about the October 19, 1998 RTC Order. It also reiterated
Order (1) granting PGSMC’s motion for inspection; (2) its prayer for the issuance of the writs of prohibition,
denying KO-GIES’ motion for reconsideration of the July mandamus and preliminary injunction which was not
23, 1998 RTC Order; and (3) denying KOGIES’ motion to acted upon by the CA. KOGIES asserted that the Branch
dismiss PGSMC’s compulsory counterclaims as these Sheriff did not have the technical expertise to ascertain
counterclaims fell within the requisites of compulsory whether or not the machineries and equipment
counterclaims. conformed to the specifications in the contract and were
properly installed.
_______________
_______________
Rollo, pp. 108-111.
13
Id.,
17
at pp. 113-115. _______________
Id.,
18
at pp. 120-146; dated October 9, 1998.
Id.,
19
at p. 119. Id., at pp. 266-268.
21
Id.,
20
at pp. 116-118. Id., at p. 40. Penned by Associate Justice Elvi John S. Asuncion and
22
Before we delve into the substantive issues, we shall Procedure. It is a responsive pleading, hence, the
first tackle the procedural issues. courts a quo did not commit reversible error in denying
The rules on the payment of docket fees for counter- KOGIES’ motion to dismiss PGSMC’s compulsory
claims and cross claims were amended effective August counterclaims.
16, 2004
KOGIES strongly argues that when PGSMC filed the _______________
counterclaims, it should have paid docket fees and filed 24
SEC. 5. Certification against forum shopping.—The plaintiff or
a certificate of non-forum shopping, and that its failure principal party shall certify under oath in the complaint or other
to do so was a fatal defect. initiatory pleading asserting a claim for relief, or in a sworn
certification annexed thereto and simultaneously filed therewith: (a) Allowing appeals from interlocutory orders would result in the
that he has not theretofore commenced any action or filed any claim ‘sorry spectacle’ of a case being subject of a
involving the same issues in any court, tribunal or quasi-judicial agency
counterproductive ping-pong to and from the appellate court
and, to the best of his knowledge, no such other action or claim is
pending therein; (b) if there is such other pending action or claim, a as often as a trial court is perceived to have made an error in
complete statement of the present status thereof; and (c) if he should any of its interlocutory rulings. However, where the assailed
thereafter learn that the same or similar action or claim has been filed interlocutory order was issued with grave abuse of discretion
or is pending, he shall report that fact within five (5) days therefrom to or patently erroneous and the remedy of appeal would not
the court where his aforesaid complaint or initiatory pleading has been afford ade-
filed. (Emphasis supplied.)
Failure to comply with the foregoing requirements shall not be _______________
curable by mere amendment of the complaint or other initiatory
pleading but shall be cause for the dismissal of the case without
G.R. No. L-56291, June 27, 1988, 162 SCRA 642.
25
criminal case which was not assailable in an action for The alleged grave abuse of discretion of the
certiorari since the denial of a motion to quash required respondent court equivalent to lack of jurisdiction in the
the accused to plead and to continue with the trial, and issuance of the two assailed orders coupled with the
whatever objections the accused had in his motion to fact that there is no plain, speedy, and adequate
quash can then be used as part of his defense and remedy in the ordinary course of law amply provides the
subsequently can be raised as errors on his appeal if the basis for allowing the resort to a petition for certiorari
judgment of the trial court is adverse to him. The under Rule 65.
general rule is that interlocutory orders cannot be Prematurity of the petition before the CA
challenged by an appeal. Thus, in Yamaoka v.
27
20
20 SUPREME COURT REPORTS ANNOTATED _______________
Korea Technologies Co., Ltd. vs. Lerma
Id., at p. 721 (8th rev. ed.).
“to enable the lower court, in the first instance, to pass
30
21
upon and correct its mistakes without the intervention
VOL. 542, JANUARY 7, 2008 21
of the higher court.” 30
The September 21, 1998 RTC Order directing the Korea Technologies Co., Ltd. vs. Lerma
branch sheriff to inspect the plant, equipment, and Philippines. Therefore, our laws ought to govern.
facilities when he is not competent and knowledgeable Nonetheless, Art. 2044 of the Civil Code sanctions the
on said matters is evidently flawed and devoid of any validity of mutually agreed arbitral clause or the finality
legal support. Moreover, there is an urgent necessity to and binding effect of an arbitral award. Art. 2044
resolve the issue on the dismantling of the facilities and provides, “Any stipulation that the arbitrators’
any further delay would prejudice the interests of award or decision shall be final, is valid, without
KOGIES. Indeed, there is real and imminent threat of prejudice to Articles 2038, 2039 and 2040.” (Emphasis
irreparable destruction or substantial damage to supplied.)
KOGIES’ equipment and machineries. We find the resort Arts. 2038, 2039, and 2040 abovecited refer to
31 32 33
to certiorari based on the gravely abusive orders of the instances where a compromise or an arbitral award, as
trial court sans the ruling on the October 2, 1998 motion applied to Art. 2044 pursuant to Art. 2043, may be 34
for reconsideration to be proper. voided, rescinded, or annulled, but these would not
denigrate the finality of the arbitral award.
The arbitration clause was mutually and voluntarily submit to arbitration any dispute arising therefrom and
agreed upon by the parties. It has not been shown to be the relationship of the parties is part of that contract
con- and is itself a contract.” 37
that submission to arbitration is a contract and that a Capitol Industrial Construction Groups, Inc., we declared
clause in a contract providing that all matters in dispute that:
“Being an inexpensive, speedy and amicable method of
between the parties shall be referred to arbitration is a
settling disputes, arbitration—along with mediation,
contract. Again in Del Monte Corporation-USA v. Court
36
deemed retroactive in that sense and to that extent. As stipulates the requirement for the arbitral award to be
a general rule, the retroactive application of procedural recognized by a competent court for enforcement,
laws does not violate any personal rights because no which court under Sec. 36 of the UNCITRAL Model Law
vested right has yet attached nor arisen from them. 42
may refuse recognition or enforcement on the grounds
Among the pertinent features of RA 9285 applying provided for. RA 9285 incorporated these provisos to
and incorporating the UNCITRAL Model Law are the Secs. 42, 43, and 44 relative to Secs. 47 and 48, thus:
following: “SEC. 42. Application of the New York Convention.––The New
York Convention shall govern the recognition and
1.(1)The RTC must refer to arbitration in enforcement of arbitral awards covered by said Convention.
proper cases The recognition and enforcement of such arbitral awards
shall be filed with the Regional Trial Court in accordance
with the rules of procedure to be promulgated by the
Under Sec. 24, the RTC does not have jurisdiction over Supreme Court. Said procedural rules shall provide that the
disputes that are properly the subject of arbitration party relying on the award or applying for its enforcement
pursuant to an arbitration clause, and mandates the shall file with the court the original or authenticated copy of
referral to arbitration in such cases, thus: the award and the arbitration agreement. If the award or
“SEC. 24. Referral to Arbitration.—A court before which an agreement is not made in any of the official languages, the
action is brought in a matter which is the subject matter of party shall supply a duly certified translation thereof into any
an arbitration agreement shall, if at least one party so of such languages.
requests not later than the pre-trial conference, or upon the The applicant shall establish that the country in which
request of both parties thereafter, refer the parties to foreign arbitration award was made in party to the New York
arbitration unless it finds that the arbitration agreement is Convention.
null and void, inoperative or incapable of being performed. xxxx
SEC. 43. Recognition and Enforcement of Foreign Arbitral
1.(2)Foreign arbitral awards must be Awards Not Covered by the New York Convention.––The
confirmed by the RTC recognition and enforcement of foreign arbitral awards not
covered by the New York Convention shall be done in
Foreign arbitral awards while mutually stipulated by the accordance with procedural rules to be promulgated by the
parties in the arbitration clause to be final and binding Supreme Court. The Court may, on grounds of comity and
reciprocity, recognize and enforce a non-convention award as
are
a convention award.
_______________
_______________ confirmed, are enforced as final and executory decisions
of our courts of law.
43
Id., Art. 35(1) provides:
Article 35. Recognition and enforcement Thus, it can be gleaned that the concept of a final
(1) An arbitral award, irrespective of the country in which it was and binding arbitral award is similar to judgments or
made, shall be recognized as binding and, upon application in writing awards given by some of our quasi-judicial bodies, like
to the competent court, shall be enforced subject to the provisions of
this article and of article 36.
the National Labor Relations Commission and Mines
27 Adjudication Board, whose final judgments are
VOL. 542, JANUARY 7, 2008 27 stipulated to be final and binding, but not immediately
Korea Technologies Co., Ltd. vs. Lerma executory in the sense that they may still be judicially
SEC. 44. Foreign Arbitral Award Not Foreign Judgment.—A reviewed, upon the instance of any party. Therefore,
28
foreign arbitral award when confirmed by a court of a foreign
country, shall be recognized and enforced as a foreign 28 SUPREME COURT REPORTS ANNOTATED
arbitral award and not as a judgment of a foreign court. Korea Technologies Co., Ltd. vs. Lerma
A foreign arbitral award, when confirmed by the Regional the final foreign arbitral awards are similarly situated in
Trial Court, shall be enforced in the same manner as final and that they need first to be confirmed by the RTC.
executory decisions of courts of law of the Philippines
xxxx 1.(3)The RTC has jurisdiction to review foreign
SEC. 47. Venue and Jurisdiction.—Proceedings for arbitral awards
recognition and enforcement of an arbitration agreement or
for vacations, setting aside, correction or modification of an
arbitral award, and any application with a court for Sec. 42 in relation to Sec. 45 of RA 9285 designated and
arbitration assistance and supervision shall be deemed as vested the RTC with specific authority and jurisdiction to
special proceedings and shall be filed with the Regional Trial set aside, reject, or vacate a foreign arbitral award on
Court (i) where arbitration proceedings are conducted; (ii) grounds provided under Art. 34(2) of the UNCITRAL
where the asset to be attached or levied upon, or the act to Model Law. Secs. 42 and 45 provide:
be enjoined is located; (iii) where any of the parties to the “SEC. 42. Application of the New York Convention.––The New
dispute resides or has his place of business; or (iv) in the York Convention shall govern the recognition and
National Judicial Capital Region, at the option of the enforcement of arbitral awards covered by said Convention.
applicant. The recognition and enforcement of such arbitral awards
SEC. 48. Notice of Proceeding to Parties.—In a special shall be filed with the Regional Trial Court in
proceeding for recognition and enforcement of an arbitral accordance with the rules of procedure to be promulgated
award, the Court shall send notice to the parties at their by the Supreme Court. Said procedural rules shall provide
address of record in the arbitration, or if any part cannot be that the party relying on the award or applying for its
served notice at such address, at such party’s last known enforcement shall file with the court the original or
address. The notice shall be sent at least fifteen (15) days authenticated copy of the award and the arbitration
before the date set for the initial hearing of the application.” agreement. If the award or agreement is not made in any of
It is now clear that foreign arbitral awards when the official languages, the party shall supply a duly certified
confirmed by the RTC are deemed not as a judgment of translation thereof into any of such languages.
a foreign court but as a foreign arbitral award, and when
The applicant shall establish that the country in which given by a local arbitral tribunal are the specific grounds
foreign arbitration award was made is party to the New York or conditions that vest jurisdiction over our courts to
Convention. review the awards.
If the application for rejection or suspension of For foreign or international arbitral awards which
enforcement of an award has been made, the Regional Trial
must first be confirmed by the RTC, the grounds for
Court may, if it considers it proper, vacate its decision and
may also, on the application of the party claiming recognition
setting aside, rejecting or vacating the award by the
or enforcement of the award, order the party to provide RTC are provided under Art. 34(2) of the UNCITRAL
appropriate security. Model Law.
xxxx For final domestic arbitral awards, which also need
SEC. 45. Rejection of a Foreign Arbitral Award.—A party to confirmation by the RTC pursuant to Sec. 23 of RA
a foreign arbitration proceeding may oppose an application 876 and shall be recognized as final and executory
44
for recognition and enforcement of the arbitral award in decisions of the RTC, they may only be assailed before
45
accordance with the procedures and rules to be promulgated the RTC and vacated on the grounds provided under
by the Supreme Court only on those grounds enumerated Sec. 25 of RA 876. 46
VOL. 542, JANUARY 7, 2008 29 Agreements, to Provide for the Appointment of Arbitrators and the
Procedure for Arbitration in Civil Controversies, and for Other
Korea Technologies Co., Ltd. vs. Lerma Purposes” (1953).
Thus, while the RTC does not have jurisdiction over RA 9285, Sec. 40.
45
30
by the parties, still the foreign arbitral award is subject
to judicial review by the RTC which can set aside, reject, 30 SUPREME COURT REPORTS ANNOTATED
or vacate it. In this sense, what this Court held in Chung Korea Technologies Co., Ltd. vs. Lerma
Fu Industries (Phils.), Inc. relied upon by KOGIES is
applicable insofar as the foreign arbitral awards, while 1.(5)RTC decision of assailed foreign arbitral
final and binding, do not oust courts of jurisdiction since award appealable
these arbitral awards are not absolute and without
exceptions as they are still judicially reviewable. Sec. 46 of RA 9285 provides for an appeal before the CA
Chapter 7 of RA 9285 has made it clear that all arbitral as the remedy of an aggrieved party in cases where the
awards, whether domestic or foreign, are subject to RTC sets aside, rejects, vacates, modifies, or corrects an
judicial review on specific grounds provided for. arbitral award, thus:
“SEC. 46. Appeal from Court Decision or Arbitral Awards.—A
1.(4)Grounds for judicial review different in decision of the Regional Trial Court confirming, vacating,
setting aside, modifying or correcting an arbitral award may
domestic and foreign arbitral awards
be appealed to the Court of Appeals in accordance with the
rules and procedure to be promulgated by the Supreme
The differences between a final arbitral award from an Court.
international or foreign arbitral tribunal and an award
The losing party who appeals from the judgment of the the contract of arbitration, a party may not unilaterally
court confirming an arbitral award shall be required by the rescind or terminate the contract for whatever cause
appellate court to post a counterbond executed in favor of without first resorting to arbitration.
the prevailing party equal to the amount of the award in What this Court held in University of the Philippines v.
accordance with the rules to be promulgated by the Supreme
De Los Angeles and reiterated in succeeding
47
Court.”
cases, that the act of treating a contract as rescinded
48
can be enforced. No. 145483. November 19, 2004, 443 SCRA 163; Subic Bay
With our disquisition above, petitioner is correct in its Metropolitan Authority v. Universal International Group of Taiwan, G.R.
contention that an arbitration clause, stipulating that No. 131680, September 14, 2000, 340 SCRA 359; Philippine National
the arbitral award is final and binding, does not oust our Construction Corp. v. Mars Construction Enterprises, Inc., G.R. No.
133909, February 15, 2000, 325 SCRA 624; Cheng v. Genato, G.R. No.
courts of jurisdiction as the international arbitral award, 129760, December 29, 1998, 300 SCRA 722; Gold-enrod, Inc. v. Court
the award of which is not absolute and without of Appeals, G.R. No. 126812, November 24, 1998, 299 SCRA
exceptions, is still judicially 141; Adelfa Properties, Inc. v. Court of Appeals, G.R. No. 111238,
31 January 25, 1995; 240 SCRA 565; Bowe v. Court of Appeals, G.R. No.
95771, March 19, 1993, 220 SCRA 158; Lim v. Court of Appeals, G.R.
VOL. 542, JANUARY 7, 2008 31 No. 85733, February 23, 1990, 182 SCRA 564.
Korea Technologies Co., Ltd. vs. Lerma 32
reviewable under certain conditions provided for by the 32 SUPREME COURT REPORTS ANNOTATED
UNCITRAL Model Law on ICA as applied and Korea Technologies Co., Ltd. vs. Lerma
incorporated in RA 9285. from the contract must be brought first and resolved by
Finally, it must be noted that there is nothing in the arbitration, and not through an extrajudicial rescission
subject Contract which provides that the parties may or judicial action.
dispense with the arbitration clause. The issues arising from the contract between PGSMC
Unilateral rescission improper and illegal and KOGIES on whether the equipment and machineries
Having ruled that the arbitration clause of the subject delivered and installed were properly installed and
contract is valid and binding on the parties, and not operational in the plant in Carmona, Cavite; the
contrary to public policy; consequently, being bound to ownership of equipment and payment of the contract
price; and whether there was substantial compliance by and installation is indeed a factual issue prohibited by
KOGIES in the production of the samples, given the Rule 65.
alleged fact that PGSMC could not supply the raw However, what appears to constitute a grave abuse
materials required to produce the sample LPG cylinders, of discretion is the order of the RTC in resolving the
are matters proper for arbitration. Indeed, we note that issue on the ownership of the plant when it is the
on July 1, 1998, KOGIES instituted an Application for arbitral body (KCAB) and not the RTC which has
Arbitration before the KCAB in Seoul, Korea pursuant to jurisdiction and authority over the said issue. The RTC’s
Art. 15 of the Contract as amended. Thus, it is determination of such factual issue constitutes grave
incumbent upon PGSMC to abide by its commitment to abuse of discretion and must be reversed and set aside.
arbitrate. RTC has interim jurisdiction to protect the rights of the
Corollarily, the trial court gravely abused its parties
discretion in granting PGSMC’s Motion for Inspection of Anent the July 23, 1998 Order denying the issuance of
Things on September 21, 1998, as the subject matter of the injunctive writ paving the way for PGSMC to
the motion is under the primary jurisdiction of the dismantle and transfer the equipment and machineries,
mutually agreed arbitral body, the KCAB in Korea. we find it to be in order considering the factual milieu of
In addition, whatever findings and conclusions made the instant case.
by the RTC Branch Sheriff from the inspection made on Firstly, while the issue of the proper installation of the
October 28, 1998, as ordered by the trial court on equipment and machineries might well be under the
October 19, 1998, is of no worth as said Sheriff is not primary jurisdiction of the arbitral body to decide, yet
technically competent to ascertain the actual status of the RTC under Sec. 28 of RA 9285 has jurisdiction to
the equipment and machineries as installed in the plant. hear and grant interim measures to protect vested
For these reasons, the September 21, 1998 and rights of the parties. Sec. 28 pertinently provides:
October 19, 1998 RTC Orders pertaining to the grant of “SEC. 28. Grant of interim Measure of Protection.—(a) It is
the inspection of the equipment and machineries have not incompatible with an arbitration agreement for a
to be recalled and nullified. party to request, before constitution of the tribunal,
Issue on ownership of plant proper for arbitration from a Court to grant such measure. After constitution of
Petitioner assails the CA ruling that the issue petitioner the arbitral tribunal and during arbitral proceedings, a
request for an interim measure of
raised on whether the total contract price of USD
1,530,000 _______________
33
VOL. 542, JANUARY 7, 2008 33 Suarez v. National Labor Relations Commission, G.R. No. 124723,
49
property is not to the best interest of PGSMC due to the arbitral proceedings and enforcement of the award, if
prohibitive rent while the LPG plant as set-up is not any.
operational. PGSMC was losing PhP322,560 as monthly WHEREFORE, this petition is PARTLY GRANTED, in
rentals or PhP3.87M for 1998 alone without considering that:
the 10% annual rent increment in maintaining the plant.
Fourthly, and corollarily, while the KCAB can rule on 1.(1)The May 30, 2000 CA Decision in CA-G.R. SP
motions or petitions relating to the preservation or No. 49249 is REVERSED and SET ASIDE;
transfer of the equipment and machineries as an interim 2.(2)The September 21, 1998 and October 19, 1998
measure, yet on hindsight, the July 23, 1998 Order of RTC Orders in Civil Case No. 98-117 are
the RTC allowing the transfer of the equipment and REVERSED and SET ASIDE;
machineries given the nonrecognition by the lower 3.(3)The parties are hereby ORDERED to submit
courts of the arbitral clause, has accorded an interim themselves to the arbitration of their dispute and
differences arising from the subject Contract 39
before the KCAB; and © Copyright 2020 Central Book Supply, Inc. All rights reserved.
4.(4)PGSMC is hereby ALLOWED to dismantle and
transfer the equipment and machineries, if it had
not done so, and
_______________
38
38 SUPREME COURT REPORTS ANNOTATED
Korea Technologies Co., Ltd. vs. Lerma
No pronouncement as to costs.
SO ORDERED.
Quisumbing (Chairperson), Carpio, Carpio-
Morales and Tinga, JJ., concur.
Petition partly granted.
Notes.—E.O. No. 1008 which vests jurisdiction to the
Construction Industry Arbitration Commission (CIAC)
over construction disputes is a special law—hence, it
takes precedence over Batas Pambansa Blg. 129 or the
Judiciary Reorganization Act of 1980, a general law
which vests jurisdiction to the Regional Trial Courts over
civil actions in which the subject of the litigation is
incapable of pecuniary estimation. (Reyes vs. Balde
II, 498 SCRA 186 [2006])
The parties, in incorporating an arbitration clause in
their contract with regard to energy fees, expressly
intended that the said matter in dispute must first be
resolved by an arbitration panel before it reaches the
courts. (Fiesta World Mall Corporation vs. Linberg
Philippines, Inc., 499 SCRA 332 [2006])
——o0o——