Tambak Lorok Combine Cycle Power Plant: Daily HSE Observation Register
Tambak Lorok Combine Cycle Power Plant: Daily HSE Observation Register
Date tt Observation Photo Discription / Observation Location Category Risk Responsible Person Company Action Required Action Taken/Photo Status Date Closed
17/05/20 IMAM S Cable there is no S-Hook at Top HRSG Zone 1 Electrical Safety Low SPV TPE JEL inform to Spv incharge to install S-Hook Close 17/05/20
17/05/20 IMAM S scaffold at access no have protection Zone 1 Access & Egress Low SPV TPE JEL inform to SPV incharge install protection Close 17/05/20
17/05/20 IMAM S Poor Housekeeping Zone 1 Housekeeping Low SPV TPE JEL inform to SPV incharge housekeeping Close 17/05/20
17/05/20 IMAM S material Protebtial Dropped Object Zone 1 Dropped Objects Low SPV TPE JEL inform to SPV incharge tie material Close 17/05/20