Sub- Total -
C. FUEL, OIL & SPAREPARTS
(Exclude acquisition & delivery of materials)
DESCRIPTION UNIT QUANTITY UNIT COST AMOUNT
Sub- Total -
B. MATERIALS:
(Include acquisition of equipment, fuel, etc. for materials)
KIND UNIT QTY UNIT COST AMOUNT
Fence
Epoxy Primer (Gray) gal 12.00 800.00 9,600.00
Lacquer Thinner gal 24.00 250.00 6,000.00
QDE gal 12.00 700.00 8,400.00
Paint Brush #2 pcs 5.00 35.00 175.00
Paint Roller #7 pcs 2.00 75.00 150.00
Tennis Court
Rubberized Paint (green) gal 70.00 1,400.00 98,000.00
Rubberized Paint (blue) gal 58.00 1,350.00 78,300.00
Rubberized Paint (white) gal 1.00 1,450.00 1,450.00
Paint Roller #8 pcs 6.00 95.00 570.00
Sub- Total -
D. MATERIALS:
(Include acquisition of equipment, fuel, etc. for materials)
KIND UNIT QTY UNIT COST AMOUNT
Sub- Total -
D. MATERIALS:
(Include acquisition of equipment, fuel, etc. for materials)
KIND UNIT QTY UNIT COST AMOUNT
SUMMARY
Item DESCRIPTION OF WORK QTY. UNIT UNIT COST TOTAL COST
Concrete Works 1.00 lumpsum 36,933.98 36,933.98
Steel Works 1.00 lumpsum 562,464.00 562,464.00
Painting Works 1.00 lumpsum 357,290.00 357,290.00
I. CONCRETE WORKS
a . 3/4" Marine plywood 7 pcs 1,500.00 10,500.00
b . Coco Lumber 2" x 2" x 12' 9 pcs 100.00 900.00
c . Coco Lumber 2" x 3" x 12' 5 pcs 150.00 750.00
d . CWN 3" 3 kgs 85.00 255.00
e . CWN 4" 3 kgs 85.00 255.00
f . Cement 36 bags 265.00 9,540.00
g . Sand 0.53 cu. m. 650.00 344.50
h . Gravel 1.42 cu. m. 800.00 1,136.00
i . RSB 12mm 15 pcs 190.00 2,850.00
j . RSB 10mm 6 pcs 138.00 828.00