Project Management

CONSTRUCTION OF HOUSE

The purpose of this project is to analyse project in the light of terms of


managing project explained by lectures and PMBOK (project management
body of knowledge).

Submitted to:
Submitted by:
Mr Sumit Kumar,
Aarushi Susovita
Asst professor,
Bft/16/597
NIFT Bhubaneswar
Project Description
Recently our company signed a contract of construction of house in Bahria town phase 8 with
Mr Ali. Mr Ali Hamza. He floats a tender about the new house construction with specify the
requirements. And choose our company for this project because we provide a reliable house
at reasonable cost. The duration decided for this project is one year with basement, ground
floor and first floor. And the cost for this project is 14,365,047.All this description is written
in the contract and both of the parties signed this agreement.

Initiation of the project


The Initiation Process consists of those processes performed to define a new project or a new
phase of an existing project by obtaining agreement to start the project or phase. Within the
initiating processes, the initial scope is defined and initial financial resources are committed.
Internal and external stakeholders who will interact and influence the overall outcome of the
project are identified. Or in simple word we can say that in this first phase of the project the
project charter and the stakeholders are identified.
Developing Project Charter
Develop Project Charter is the process of developing a document that formally authorizes a
project or a phase and documenting initial requirements that satisfy the stakeholder’s needs
and expectations.

 Duration

Start date 1st January 2020

End date 31 December 2020

 Estimated Budget
In this project keeping all expenses in mind I can say that the estimated budget require
for this project is 15,254,350.
 Procurement plan
All the material mentioned in the cost plan is going to procure from different suppliers
at given cost. And this material will purchase before 1st May.
2. Enterprise environmental factors:
Environmental factors which may influence this project are
 Organization Culture
 Work hour
 Holidays
 Internal factors like labour strike, shortage of material, unavailability of man
power, etc.
 External factors like load shedding, public strike against any event, political
factors, inflation etc.

1
.
 Triple constraint
The triple constraint consists of time, scope and cost. The objective of this project is
to achieve the triple constraint.
Our 1st focus in this project is to complete the construction within one year as
mentioned in the contract. For this purpose we construct a table and distribute our
project phases in different months.

Initiation 1st Jan- 31 Jan (1month)


Planning 1nd Feb- 30 Mar (2months)
Execution 1st Apr - 25 Nov (8months)
Monitoring and control M&C for whole execution
Closing 1st Dec- 31 Dec (1month)

The 2nd focus is to achieve the target with in given budget and for this purpose the
cost for different material is already estimated so that we would not exceed from the
given budget. The estimated budget is 14,365,047 and in these 14,365,047 all
procurement will done in future for the 1 canal house with basement, ground and 1 st
floor.
The 3rd important factor in this project is scope identification. Scope of this
project is to construct house with in given time and budget. Scope tells about the
requirement of the project. Like in our project different dimensions is mention in
scope statement for example,

Number of rooms 15
Number of kitchens 3
Number of bath rooms 12
Loan 1
Terrace 1
Garage 1

Other than this information the time taken to complete these is also mention in the
scope statement. We will try to not exceed from our scope and finishing the project
within the time and costing limit.
Estimate Activity Resource
Estimate Activity Resources is the process of estimating the type and quantities of
material, people, equipment, or supplies required to perform each activity.
Outputs

 Activity resource requirement plan

Type of resource Requirement


Human resource For all activities human resources are required to make the
project team and utilize labour for project.

2
Software resources Software resources are required to make the design of house.
Organizational process asset Organizational process assets contains organization’s
policies, templates, standards and help data for the guidance
of team members so that they can perform the project
processes more efficiently and with better utilization of time
and monetary resources.

Transportation resources Transportation is required for delivery of material.


Materials Different type of material is needed for this project like
cement, steel, sand etc.
Equipment Equipment’s are also required this project.

Resource breakdown structure:

1.Human Resource
Project team Labour

2.Transportation
Labour Material Transportation

3.Material and equipment


Cement, concrete, steel,sand etc woodcutter machine, motor, driller, etc

Estimate Activity Duration (CPM)


Estimate Activity Durations is the process of approximating the number of work periods
needed to complete individual activities with estimated resource.
Outputs

 Activity Duration Estimate

Activity Duration
Estimate(days)

project initial proposal writing 2

Defining team members and group 1


leader.

Gathering required information. 1

3
Performing feasibility analysis. 1

Defining customer requirements. 1

Develop project charter. 2

Identifying stakeholders. 1

Collecting requirements. 1

Project Costing. 2

Project Budgeting. 1

Scheduling. 1

Project procurement management 2


planning.
Whole construction 240

Work Cost
Develop Schedule (By Gantt
chart method)
Develop Schedule is the process
Pluming material  "Rs794,000.00" of analysing activity sequences,
durations, resource requirements,
Concrete rods  "Rs316,000.00" and schedule constraints to create
the project schedule.
Paint  "Rs420,000.00"
Output
Flooring material  "Rs3,030,500.00"
 Project schedule
Electrical equipment  "Rs2,328,892.00"
Main tasks Deadlines
Foundation
Glass windows  "Rs32,500.00"30 April
Ground 30 June
Basement
Wood  30 July
"Rs2,086,288.00"
Ground floor 25 Sep
1st floor
Cement  25 Nov
"Rs1,086,200.00"

Bricks  "Rs1,673,500.00"

Labor  "Rs2,310,147.00" Estimate Cost

Total Cost  14,078,027

Human  187,020

4
Reserve  100,000

Total Price  14,365,047


Determine Budget
Total budget is 15,254,350 for this project

 Procurement management Plan:


This procurement plan sets the procurement frame work for this project. It will serve as the
guideline for managing procurement throughout the life of the project and will be updated
when required.
The procurement plan of the project is given below:

Procurement Process:
By using CPM AND PERT:-
The whole procurement process is under the authority of the Project manager and also he has
the responsibility for the sales and the material selection.

Items Justification Needed


Cement, bricks Needed because important tool April - August
for construction
Concrete Rods Needed to provide the base of April – August
the house
Wood & granite Needed for the purpose of July – September
building windows, doors
Tilling& For the decoration of the house, May - July
flooring For the decoration purpose
material like
marbles and

5
tiles

Plumbing For the purpose of the piping August - October


sewerage work
material like
Pipes
Electrical When the frame of the house is October – November
material like completed then the electrical
equipment’s work should be started
Bath fixtures & Bath work will start after October-November
accessories completion of frame of house

Material for Paint house after whole October-November


Steel work construction
Aluminium
work
Paint work

Make or buy decisions:


We are outsourcing some of the project materials and also this step is important in because
the decision for buying or not buying is totally based upon the fact that the project manager
give the green signal to the supplier. Then the process of the procurement is started.