Professional Documents
Culture Documents
CONSTRUCTION PLANNING
AND SCHEDULING
G R O U P 3
Planning and Scheduling
CONSTRUCTION
PLANNING
Preconstruction Planning
>> Must be viewed as an opportunity to design and build the project on
paper before actual construction.
>> Allows all entities involved to visualize the process and make necessary
provisions to coordinate it .
>> Provides an estimate of the time required for each portion of the project
as well as the total project.
>> Forms the basis for managers to issue instructions to the subordinates .
>> Establishes the planned sequence for the use of personnel, materials,
equipment, and money.
Planning and Scheduling
Object of Planning
>>To execute work in an organized and structured manner.
>>To know the cost associated with each activity.
>>To reduce rework.
Principles of Planning
control.
Project planning is a logical process to ensure that the work of project is carried out:
• The first step of project planning is to clearly define the problem to be solved by the
project.
• Once the problem is clearly defined, the next step is to define the project objectives or
goals.
• After identifying the deliverables, these are subdivided into smaller activities to enable
• Step to estimate cost and develop budget based on project deliverable and schedule.
• Supporting plans such as quality management, human resources, communication, risk
Types of Plans
DIFFERENT TYPES OF PLANS
1. Project Conceptual Plan
4. Time Plan
5. Manpower Plan
6. Material Plan
8. Finance Plan
Planning and Scheduling
SCHEDULING
• Materials
• Man
• Machinery
• Money
activities in order by fixing the starting and finishing date of each activity
of the work .
Planning and Scheduling
Uses of Scheduling
each work.
• The actual progress of the work can be checked.
scheduling.
Planning and Scheduling
Advantages of Scheduling
Types of Schedule
>> Construction Schedule
>> Material Schedule
>> Labor Schedule
Example of WBS
Methods Of Scheduling
Scheduling can be done by different methods depending on the size of the
project. The methods used are:
01 02 03
along the horizontal axis. Activities are arranged along the vertical axis.
March.
1. Gantt Charts
2. Milestone Charts
milestone.
2. Milestone Charts
3. Network Analysis
• Both CPM and PERT describe the work plan of project where arrows and
PERT is primarily concerned with time only CPM places dual emphasis on project time as
well cost.
PERT is generally used for projects where time CPM is used for projects which are repetitive in
required to complete the activities is not known nature and comparatively small in size.
a priority. Thus PERT is used for large of
projects
Two types of notations used in the network diagram. They are as under,
1. Activity-on-Arrow (AOA),
2. Activity-on-Node (AON).
• Networks should be continuous (i.e., each activity except the first and the
last has both preceding and succeeding activities).
3. Network Analysis
Activity-on-Arrow (AOA)
In this method, the arrows represent activities while the nodes
represent the start and the end of an activity (usually named as events).The
length of the arrow connecting the nodes has no significance. When one
activity depends upon another, both appear on the diagram as two arrows
Activity-on-Node (AON).
In this method, a box (or node) is used to show the task itself and the
network diagram) that indicates that any activity following the dummy
cannot be started until the activity or activities preceding the dummy are
completed.
3. Network Analysis
REPRESENTATION OF ACTIVITY
E. S = Early start time an activity can start with
T LS LF
L.S = Latest start time that an activity can be start (DAYS)
Total float time (T.F). The float for an activity is the amount that its duration can slip
without causing the project to be delayed. T.F= L.F - E.F or L.S – E.S
3. Network Analysis
– Earliest Start Time (ES) - This is the earliest time an activity can begin without
violation of immediate predecessor requirements.
– Earliest Finish Time (EF) - This represent the earliest time at which an activity
can end. The project completion time is the maximum of the Earliest Finish Times
A critical path is a path of activities, from the Start node to the Finish node,
with 0 slack times.
3. Network Analysis
Planning and Scheduling
THANK YOU