You are on page 1of 33

A TE S

S TI M
ION E NG
U CT EE RI
N ST R NG IN
CO U ES E
VA L
AND
BACKGROUND & PURPOSE

Construction cost estimating is the process of forecasting the cost of


building a physical structure.
It is to determine a project’s scope and feasibility and to allocate
budgets.
Cost estimate prevents the builder from losing money and helps the
customer avoid overpaying
They are also essential for large civil projects or mega-projects
because of their sizable scope and the potential involvement of public
money.
Customers usually select the lowest bid that meets the standards and
specifications they set.
overview of the
construction estimation process

COMMISSIONING A DETERMINING FORMING A DESIGN


PROJECT REQUIREMENTS TEAM

Commissioning is The first real step in The project owner contracts


essentially a verification constructing a project is a with an architect who will
process that ensures a pre-design phase or then select other
builder designs, constructs, planning phase. specialized consultants to
and delivers a project form a design team.
according to the owner’s
requirements.
overview of the
construction estimation process

DESIGNING THE BIDDING BASED ON SIGNING THE


STRUCTURE THE SCOPE OF CONTRACT
WORK

This step deals with the Once the construction Once the contractor has
architect creating a series documents are finalized, been selected, they execute
of designs they are released to a set of contract
contractors who wish to bid documents with the owner.
on the project.
overview of the
construction estimation process

CONSTRUCTION CLOSE-OUT COMPLETION


When the builder comes If the contractor has
close to finishing a completed the structure
During the construction structure, the contractor according to construction
phase, the contractor requests the architect drawings and
oversees building in perform a substantial specifications, the architect
accordance with the completion inspection in will issue a certificate of
construction documents. which the architect verifies final completion, and the
the near-complete status contractor is entitled to
of the project. receive the full payment.
MAIN TYPES OF CONSTRUCTION
COST ESTIMATES

Level 1 : Order of Magnitude Estimate


It is created when project design has not yet begun, to assess the
overall viability of a construction project. To assess the overall
viability of a construction project.

Level 2 : Schematic Design Estimate


An estimate produced in line with schematic design

Level 3 : Design Development Estimate

An estimate made during the design development phase


MAIN TYPES OF CONSTRUCTION
COST ESTIMATES

Level 4 : Construction Document Estimate


An estimate based on the construction drawings and
specifications

Level 5: Bid Estimate


An estimate prepared by the contractor, based on construction
documents. The bid estimate is the basis of the bid price offered
to the customer.
MAIN TYPES OF CONSTRUCTION
COST ESTIMATES

DESIGN ESTIMATES
These estimates, prepared during a project’s pre-design and design
phases, start with an order of magnitude estimate, or screening
estimate, which determines which construction methods and types
are most feasible

BID ESTIMATES
Contractors prepare bid estimates when bidding to construct
the project.

CONTROL ESTIMATES
Prepared after one sign a contractor agreement and before
construction gets underway, the control estimate functions as a
baseline by which you assess and control actual construction
costs.
A Contstruction cost
estimates perspective
on building systems
A Contstruction cost estimates
perspective on building systems
For a project as complex as a skyscraper, estimating costs requires a methodical approach to enumerating
expenses. Cost estimators can use the Uniformat System which divides a structure into seven functional
sections, These are:

Substructure
Shell
Interiors
Services
Equipment and furnishings
Special construction
Building site work
When submitting a bid, contractors will draft a bill of quantities, which is a detailed inventory
of the labor and supplies needed for the project.

Taking-Off Quantities
It’s important to follow one of the standard methodologies, such as the New Rules of Measurement

Squaring Abstracting Biling


The quantity surveyor The collecting and It involves
multiplies the dimensions
ordering of the presenting item
of the component into
squared dimensions. descriptions and
square area and multiplies
this by the number of Similar tasks and quantities in a
times this work item components are structured format, the
occurs in the construction bill of quantities
grouped together
The Elements of a Construction
Cost Estimate

QUANTITY TAKE- LABOR HOUR LABOR RATE


OFF
is the amount per hour one
pays to skilled craftsmen.
·Developed during the pre- The labor hour, or man hour, This includes not just the
construction phase, a is a unit of work that basic hourly rate and
quantity take-off measures measures the output of one benefits, but the added
the materials and labor person working for one costs of overtime and
needed to complete a hour. payroll burdens, such as
project. worker compensation and
unemployment insurance
The Elements of a Construction
Cost Estimate

EQUIPMENT COST SUBCONTACTOR INDIRECT COST


Refer primarily to the cost of COST Are expenses not directly
running, and possibly renting, Most contractors will hire associated with construction
heavy machinery, such as cement multiple specialist work, like administrative
mixers and cranes. It’s important to subcontractors to complete costs, transport costs, smaller
note that the equipment in use parts of the construction. You
types of equipment,
influences how quickly you can add these subcontractors’
temporary structures, design
complete the project, so the use of quotes to the contractor’s total
equipment actually impacts many estimate. (It can be helpful to fees, legal fees, permits, and
costs outside of those directly use a tracker to collect all the any number of other costs,
associated with running the subcontractor documentation depending on the particular
equipment. in one place. project.
The Elements of a Construction
Cost Estimate

PROFITS CONTINGENCIES ESCALATION


Since even the most Refers to the natural
In order to make a profit, accurate estimate is likely
the contractor adds a inflation of costs over time,
to be affected by and it’s especially vital to
margin on to the cost of unforeseeable factors, such take into account for long-
completing the work. as materials wastage, an running projects. Some
Subcontractors do the estimate will usually have a projects have escalation
same when preparing their predetermined sum of clauses that address how
own quotes. money built in to account to handle this inflation.
for such added costs.
The Elements of a Construction
Cost Estimate

BONDS CAPITAL COSTS OPERATIONS AND


An owner will usually require a
·Are simply the costs associated with
establishing a facility. These include the
MAINTNACE COSTS
contractor to arrange for the following: the cost of acquiring land; the More a concern for the owner than the
issuance of a performance bond in cost of conducting feasibility studies and contractor, one accounts for
favor of the project owner. The the pre-design phase; paying the operations and maintenance costs
architect, engineer, and specialist during the design phase. Making
bond functions as a kind of members of the design team; the total
guarantee of delivery. Should the choices that lower the total lifetime
cost of construction, which covers not just
contractor fail to complete the materials, equipment, and labor, but also cost of a building may result in higher
administrative, permitting, and supervision construction costs. Operating costs
project according to the terms of
costs, as well as any insurance fees or include land rent, the salaries of
the contract, the owner is entitled taxes; the cost of any temporary permanent operations staff,
to compensation for monetary equipment or structures that are not part maintenance costs, renovation
losses up to the amount covered of the final construction; the cost of hiring a
expenses (as needed), utilities, and
by the performance bond. commissioner; and the cost of inspecting
the structure when it’s near completion. insurance.
The Elements of a Construction
Cost Estimate

MATERIAL PRICES VARIANCES


·Since the cost of materials Owners will often allocate
is prone to fluctuation construction budgets that
based on market conditions are larger than cost
and such factors as estimates because even
seasonal variations, cost good, thorough cost
estimators may look at estimates have a tendency
historical cost data and the to underestimate actual
various phases of the construction costs. This can
buying cycle when happen for a number of
calculating expected reasons.
material prices.
Influences on Construction Costs

Building Site Location of the Regulatory


Construction Site Requirements
Influences on Construction Costs

Certain construction sites


Time related Size and complexity
require the completion of
feasibility or impact studies aspects
Influences on Construction Costs

Quality of plans and Government or quasi- All cost estimates add


governmental agency
specifications at least a tenth
commissions or funds the
project ( CONTINGENCIES )
Using Historical Data in
Construction Cost Estimates
Historical data comes from several sources, including catalogs of vendor data,
databases, periodicals, commercial references, and digests of actual project costs.
Contractors may also look at successful past bids, assuming these proved accurate.

You’ll have to adjust most costs for inflation, depending on how old the data is. ,
you’ll have to adjust almost all standardized cost data to local economies, and
there’s likely to be a considerable degree of cost fluctuation even between cities
in the same region or country.

Labor costs are especially variable. Based on the demand for labor, the required level of skill,
and the condition of the construction site, which in turn hinge on such factors as the time of
year, economic and market conditions, and the location of the construction site, an estimator
will usually have to adjust historical labor data when creating a new estimate.
Using Historical Data in
Construction Cost Estimates
For contractors with successfully completed projects under their belts, comparing
their actual cost data to their cost data reference can help gauge the accuracy of the
data reference

Good cost estimators will tend toward caution since cost estimates generally
underestimate the actual cost of construction. Even with contingencies built
into the estimate, factors such as design changes and unforeseeable economic
conditions can quickly increase costs

Both the contractor and the owner bear substantial risks when constructing large projects. Contractors don’t just
stand to have their profit margins cut and their reputations hit. Many end up declaring bankruptcy when it simply
becomes too expensive to complete a project. And while owners shield themselves somewhat from financial losses
through performance bonds and similar protections, the failure to complete a project on time may result in financia
damage due to lost potential profits or an inability to pursue a strategic plan.
The Effects of Scale on Construction
Cost Estimates

“Costs are not always directly proportional to the size of a


facility or the number of units one’s building. If plotted on a
graph, this phenomenon, known as an economy or
diseconomy of scale depending on which way the cost varies,
would appear as a non-linear relationship between facility size
and costs. “
The Effects of Scale on Construction
Cost Estimates
If the average cost per unit falls as the number of units increases, we have an economy of scale. If the
average cost rises as the number of units increases, we have a diseconomy of scale.

The cost exponent is an indicator of whether a scale economy or


diseconomy exists. For a discussion of how to calculate cost exponents in
construction, consult Project Management for Construction. If the exponent
is greater than zero but less than one, an economy of scale exists. If it is
greater than one, a diseconomy of scale exists. If it is equal to one, the cost-
capacity relationship is unaffected by scale.
The Major Approaches to Construction
Cost Estimation

Production Function Stick Estimating Empirical Cost Inference


Production functions can be
Highly accurate, but incredibly
quite accurate for forecasting
time consuming, stick estimating This statistical method uses
input-output relationships for
is the practice of determining regression analyses to relate
projects of a particular type,
total costs by listing, in order, the the cost of construction to a
and there is extensive data to
costs for every single component model of predictors
draw from for certain project
of a job
types
The Major Approaches to Construction
Cost Estimation

UNIT COST ESTIMATING ALLOCATION OF JOINT


·Unit cost estimating simply
associates unit costs with each
COSTS
assembly involved in a construction You allocate costs that are
process. It’s fairly quick and
difficult to assign to individual
accurate, especially if one has used
project elements by using
the assemblies previously, and there
is evidence to justify the unit costs different mathematical formulas.
for each assembly.
THE CONSTRUCTION COST ESTIMATOR’S JOB

the cost estimator is central to the cost estimation process. Typically a


professional who is familiar with both design and construction and skilled at
navigating the myriad costs associated with construction projects, the cost
estimator must have both skill and training.
Essential skills for cost estimators include the ability to work quickly with
numbers, an in-depth knowledge of construction, and familiarity with
construction documents. On large projects, multiple specialist cost estimators
may be responsible for estimating different aspects of the project, so a
specialization or first-hand experience in constructing certain types of
structures can also be valuable.
THE CONSTRUCTION COST ESTIMATOR’S JOB

Although tertiary education is typically a requirement for cost estimators, first-


hand experience with construction and a knowledge of the contracting
landscape are perhaps more essential skills. Some estimators are individuals
who have risen through the ranks as construction workers. These experienced
construction professionals also know how to negotiate with subcontractors
and may be better able to appreciate the factors that impact estimated
amounts.
THE CONSTRUCTION COST ESTIMATOR’S JOB

Dedication to continued learning is necessary for all cost estimators, whether


certified or not. It’s key to keep abreast of the construction industry and also to
be able to learn and implement evolving cost estimation methods and
software, which we’ll talk about shortly.
In addition, cost estimators must be highly organized and highly attentive to
detail. They should know how to communicate cost information with accuracy
and integrity.
BEST PRACTICES IN CONSTRUCTION
COST ESTIMATING AND WHAT NOT TO DO

The cost estimator must Identifying indirect costs is


follow industry norms and another key part of the cost
Today, software applications standards for measurement estimator’s job, and it’s to
make cost estimation easier, units. He must also some extent a skill developed
but the cost estimator’s role consistently fill out costing- through experience. The
remains as crucial as ever. related documents, such as estimator examines
Some best practices can lead quantity surveys, and follow contractual terms to see which
to more accurate estimates cost-recording procedures in of them may impact indirect
and more successful bids. a way that makes their work costs. They’re also responsible
verifiable and easy to handoff for calculating indirect costs
to another cost estimator if and for coming up with a way
necessary. to record these.
BEST PRACTICES IN CONSTRUCTION
COST ESTIMATING AND WHAT NOT TO DO

The estimator is responsible Ultimately, the cost estimator


for evaluating The cost estimator also helps may have to exercise
subcontractors’ bids, track costs in the field so as specialized skills, such as value
particularly taking into to allow the comparison of engineering, which usually
account the subcontractors’ actual costs with cost refers to increasing the
performance on past estimates. The idea is to see function-to-cost ratio. Value
projects. They will review which areas of the estimate engineering is usually a
construction drawings for were accurate, which weren’t, separate study, and it’s critical
constructability and and why. to structure an estimate so you
accuracy in representing the can swap out costs and assess
project scope. the effect of value engineering.
COMMON PITFALLS FOR CONSTRUCTION
COST ESTIMATORS

Finally, some cost estimators


One common source of Other oversights include the
who draw from cost data
problems is the failure to failure to visit the site and the
repositories will fail to adjust
read the project documents inability to fully understand
costs based on local
carefully, which frequently the site conditions. As we
conditions or will make
leads to a poor talked about earlier, a site’s
arbitrary adjustments without
understanding of the project natural conditions and
considering prior experience or
scope and certain associated location can impact costs in
quantitative comparisons.
costs. These issue can be a number of ways, and a cost
Either of these can throw
compounded by neglecting estimator will develop an eye
estimates off and make it more
to thoroughly check the for spotting and asking about
difficult for another cost
completed estimate. these.
estimator to verify an estimate.
NEW ASPECTS OF Construction Cost
EstimatING
Construction cost estimating continues to evolve as design, building methods, and
materials change. Some trends that impact cost estimating today include:

Building Information Modeling (BIM): A building information model is a


digital model of a structure and all its characteristics and dimensions.
Sustainability and LEED (Leadership in Energy and Environmental
Design) Certification: LEED certification is a point system for rating
buildings based on their environmental performance.
Lean Construction and Cost Control: Lean construction, a fairly new
approach, draws from the principles of lean management, which is the
systematic effort to reduce waste without affecting productivity.
an k
th
yo u!

You might also like