Professional Documents
Culture Documents
2.3.3
Canadian
Handbook of
Practice
for
Architects
Introduction
Providing Advice on Costs
The Role of the Architect in Cost Planning and Control
Formats for Presentation of Cost Information
Liability of the Architect
Techniques
Cost Consultants
Construction Price Index
Publications
Contingencies
Definitions
References
Cost analysis
Final estimate
and cost check
Cost checks
Cost limit First cost
established plan
The Role of the Architect in Cost Planning • initiate and control the preparation of cost
and Control information;
• manage team members to ensure that the
To ensure that the project will be well-defined work stays within the agreed-upon budget;
and realized within a predicted cost limit, cost • set or adjust limits;
planning (also known as cost control, cost • exercise maximum influence on decisions
analysis, or cost management) requires: affecting costs.
• effective cost estimating;
Once equipped with access to reliable and
• financial analysis of various components;
current cost information available at all stages
• management of the design and construction
of a project, architects should:
documentation process.
• use this resource with confidence;
Cost planning (or the preparation of construction • express information in standard formats;
cost estimates) is done in the predesign and • be consistent and methodical;
design stages, whereas cost control (or the • avoid ambiguity;
monitoring of construction costs) is done at the • list all assumptions clearly whenever cost
later stages. Refer to Illustration 1. information is published;
• promptly confirm in writing any cost
Formats for the Presentation information provided verbally;
of Cost Information • consider providing references and comparable
projects when issuing information;
The client usually summarizes overall project
• start a cost information file for each project
costs in a “Global” or Project Budget which:
and keep it updated;
• lists all expenditures needed to complete • analyze each project on completion (refer to
every aspect of the venture; Chapter 2.3.1, Management of the Project);
• incorporates information provided by the • maintain files containing reliable historic
architect for the construction component cost data;
of the budget with a detailed breakdown. • check historic cost data in detail to ensure
comparability with the current project.
Refer to Illustration 2 which suggests some
of the “global” and “soft” costs that must Liability of the Architect
be considered.
In an architectural practice, liability for incorrect
cost estimates cannot be avoided, whether or
Prior to delivering cost advice on a regular basis,
not the architect is acting as the project
the architect should:
manager or is providing limited services with no
• make the provision of cost advice and project management responsibilities.
cost management a priority;
• make specific efforts to become Methods of Preparing
knowledgeable;
• develop in-house experience and skills;
Cost Estimates
• maintain up-to-date records of historic cost
General
data;
• emphasize to clients the importance of cost Cost forecasting is an important and rigorous
estimating and related services. activity. All cost estimates:
• work on the principle of forecasting based
To ensure effective cost management, every team on historic data;
member must be vigilant about the effect that • require that the original data be selected,
all design, detailing or specification decisions carefully and methodically, by experienced
could have on the cost of individual components personnel.
of the project, estimated during the initial
budget preparation. The project manager will:
Summary Page Schematic Contingency Variance % Design Contingency Variance % Construction Contingency
Design Developmt Documents
Level 1 Level 2 Level 3
Budget Status Budget Budget Budget
1. General requirements $ - $ - 0% $ - 0% $ -
2. Site Work $ - 0% $ - 0% $ -
3. Concrete $ 65,000 $ 15,000 115% $ 75,000 $ 7,500 107% $ 80,000 $ 4,000
4. Masonry $ - 0% $ - 0% $ -
5. Metals $ - 0% $ - 0% $ -
6. Wood and Plastics $ - 0% $ - 0% $ -
7. Thermal and
Moisture Protection $ - 0% $ - 0% $ -
8. Doors and Windows $ - 0% $ - 0% $ -
9. Finishes $ - 0% $ - 0% $ -
10. Specialties $ - 0% $ - 0% $ -
11. Equipment $ - 0% $ - 0% $ -
12. Furnishings $ - 0% $ - 0% $ -
13. Special Construction $ - 0% $ - 0% $ -
14. Conveying $ - 0% $ - 0% $ -
15. Mechanical $ - 0% $ - 0% $ -
16. Electrical $ - 0% $ - 0% $ -
Total
Construction
Contingency % $ - 0% $ - 0% $ -
Total Construction $ - 0% $ - 0% $ -
STRUCTURAL CAST-IN-
PLACE FORMWORK $ 20,000
Accessories $ 1,500 $ 75
Expansion joints $ 1,000 $ 50
Elevated slabs $ 10,000 $ 500
Footing $ 2,000 $ 100
Slab on Grade $ 2,000 $ 100
Walls $ 2,500 $ 125
Stairs $ 4,000 $ 200
CONCRETE
REINFORCEMENT $ 10,000
Reinforcing steel $ 9,000 $ 450
W.W. Fabric $ 3,000 $ 150
CAST-IN-PLACE
CONCRETE $ 35,000
Admixtures $ 1,000 $ 50
Ready Mix $ 17,000 $ 850
Elevated slabs $ 7,000 $ 350
Footings $ 2,000 $ 100
Slab on Grade $ 5,000 $ 250
Walls $ 2,000 $ 100
Stairs $ 3,000 $ 150
Elemental Costs Extensive floor area cost data are available from
a number of sources as a basis for interpolation
Quantity surveyors often use the elemental cost
and use in forecasting. These should be used
method as the standard format for presenting
when providing general cost advice and for the
cost information. This method:
calculation of overall project costs.
• divides the building into major elements
such as structure, exterior closure; Advantages:
• uses these elements to provide a cost • the concept of “floor area” is easily
framework which is useful throughout the understood and applicable to all buildings;
life of the project; • costs for an individual component or element
• is applicable to new or existing buildings; of a building, or for the entire structure, are
• uses these elements to form the basis for straightforward to calculate;
applying relevant cost information from • very simplified historic cost information,
similar projects. expressed as costs per m2/per ft2 for
completed projects, is available for many
Advantages: different building types.
• the process assumes that the approximate
size of a building is known; Disadvantages:
• the process can proceed without construction • does not account for unique conditions
drawings and specifications; or special construction;
• particularly useful for architects during • is simplistic and can be misinterpreted.
design development, when trade-offs
between elements can be considered to The architect should limit the use of this basic
improve the quality of the project without information by using it only as a general guide
compromising the total budget. at the pre-design stage.
Typical Example of
Elemental Format Elemental Elemental Elemental Cost/SF Total %
using Canadian Institute Quantity Unit Rate Amount $/SF $
of Quantity Surveyors SF $/SF
Measurement and
Pricing Method
A SHELL
A1 SUBSTRUCTURE
A11 Foundation 252,800 $ 3.75 $ 948,000 $ 3.39 $ 948,000 3.96%
A12 Basement Excavation 0 $ -
A2 STRUCTURE
A21 Lowest floor
construction 252,800 $ 10.00 $ 2,528,000 $ 9.03
A22 Upper floor
construction 27,205 $ 11.98 $ 325,916 $ 1.16
A23 Roof construction 252,800 $ 12.00 $ 3,033,600 $ 10.83 $ 5,887,516 24.61%
A3 EXTERIOR ENCLOSURE
A31 Walls below grade 0 $ - $ - $ -
A32 Walls above grade 64,800 $ 7.99 $ 517,752 $ 1.85
A33 Windows & Entrance 1,656 $ 50.12 $ 82,999 $ 0.30
A34 Roof coverings 252,800 $ 4.00 $ 1,011,200 $ 3.61
A35 Projections 64,800 $ 0.77 $ 49,896 $ 0.18 $ 1,661,847 6.95%
B INTERIORS
B1 PARTITIONS
B11 Partitions 179,915 $ 7.19 $ 1,293,589 $ 4.62 $ 1,525,589 6.38%
B12 Doors 232 no $ 1,000.00 ea $ 232,000
B2 FINISHES
B21 Floor Finishes 266,005 $ 2.00 $ 532,010 $ 1.90 $ 747,742 3.13%
B22 Ceiling Finishes 266,005 $ 0.38 $ 101,082 $ 0.36
B23 Wall Finishes 424,630 $ 0.27 $ 114,650 $ 0.41
B3 FITTING & EQUIPMENT
B31 Fitting & Fixtures 280,005 $ 0.18 $ 50,401 $ 0.18
B32 Equipment 280,005 $ 0.45 $ 126,002 $ 0.45
B33 Conveying Systems 0 $ - $ 50,000 $ 0.18 $ 226,403 0.95%
C SERVICES
C1 MECHANICAL 280,005 $ 22.50 $ 6,300,113 $ 22.50 $ 6,300,113 26.33%
C11 Plumbing & Drainage
C12 Fire Protection
C13 HVAC
C14 Controls
C2 ELECTRICAL 280,005 $ 6.00 $ 1,680,030 $ 6.00 $ 1,680,030 7.02%
C21 Service & Distribution
C22 Lighting, Devices
& Heating
C23 Systems & Ancillaries
NET BUILDING COST excluding site $ 67.78 $ 18,977,239 79.31%
D SITE
D1 SITE WORK $ 1,300,000 $ 4.64 $ 1,300,000 5.43%
D11 Site Development $ 1,000,000 $ 3.57
D12 Mechanical Site services $ 200,000 $ 0.71
D13 Electrical Site services $ 100,000 $ 0.36
D2 ANCILLARY WORK $ - $ -
D21 Demolition $ - $ -
D22 Alterations $ - $ -
NET BUILDING COST including site $ 72.42 $ 20,277,239 84.75%
Z MARK UPS
Z1 GENERAL REQUIREMENTS
Z11 General requirements 7% $ 1,419,406.74 5.06930978 $ 1,419,407 5.93%
TOTAL CONSTRUCTION ESTIMATE excluding contingency
Z2 CONTINGENCIES 11% 2,230,496.303 $7.97 $ 2,230,496 9.32%
Z21 Design contingency 0%
Z22 Escalation contingency 6% 1,216,634.347 $ 4.35
Z23 Construction contingency 5% 1,013,861.956 $ 3.62
GOODS AND SERVICES TAX EXCLUDED $ -
1 INDUSTRIAL BUILDING
16 ft clear height Under 10 000 sf $ 55.51 $ 597.29 $ 55.01 $ 591.91 $ 53.93 $ 580.29 $ 51.03 $ 549.08
10 000 - 20 000 sf $ 46.11 $ 496.14 $ 45.70 $ 491.73 $ 44.80 $ 482.05 $ 42.39 $ 456.12
20 000 - 50 000 sf $ 38.31 $ 412.22 $ 37.96 $ 408.45 $ 37.22 $ 400.49 $ 35.22 $ 378.97
50 000 - 150 000 sf $ 33.24 $ 357.66 $ 32.94 $ 354.43 $ 32.29 $ 347.44 $ 30.56 $ 328.83
Over 150 000 sf $ 31.31 $ 336.90 $ 31.03 $ 333.88 $ 30.42 $ 327.32 $ 28.78 $ 309.67
18 ft clear height Under 10 000 sf $ 57.49 $ 618.59 $ 56.97 $ 613.00 $ 55.85 $ 600.95 $ 52.85 $ 568.67
10 000 - 20 000 sf $ 47.55 $ 511.64 $ 47.12 $ 507.01 $ 46.20 $ 497.11 $ 43.72 $ 470.43
20 000 - 50 000 sf $ 39.27 $ 422.55 $ 38.91 $ 418.67 $ 38.15 $ 410.49 $ 36.10 $ 388.44
50 000 - 150 000 sf $ 33.84 $ 364.12 $ 33.54 $ 360.89 $ 32.88 $ 353.79 $ 31.11 $ 334.74
Over 150 000 sf $ 31.62 $ 340.23 $ 31.33 $ 337.11 $ 30.72 $ 330.55 $ 29.07 $ 312.79
22 ft clear height Under 10 000 sf $ 58.45 $ 628.92 $ 57.92 $ 623.22 $ 56.78 $ 610.95 $ 53.73 $ 587.13
10 000 - 20 000 sf $ 48.22 $ 518.85 $ 47.79 $ 514.22 $ 46.85 $ 504.11 $ 44.33 $ 476.99
20 000 - 50 000 sf $ 40.80 $ 439.01 $ 40.43 $ 435.03 $ 39.64 $ 426.53 $ 37.51 $ 403.61
50 000 - 150 000 sf $ 34.46 $ 370.79 $ 34.15 $ 367.45 $ 33.48 $ 360.24 $ 31.68 $ 340.88
Over 150 000 sf $ 32.94 $ 354.43 $ 32.64 $ 351.21 $ 32.00 $ 344.32 $ 30.28 $ 325.81
25 ft clear height Under 10 000 sf $ 59.00 $ 634.84 $ 58.47 $ 629.14 $ 57.32 $ 616.76 $ 54.24 $ 583.62
10 000 - 20 000 sf $ 49.67 $ 534.45 $ 49.23 $ 529.71 $ 48.26 $ 519.28 $ 45.67 $ 491.41
20 000 - 50 000 sf $ 41.11 $ 442.34 $ 50.74 $ 545.96 $ 39.94 $ 429.75 $ 37.79 $ 406.62
50 000 - 150 000 sf $ 34.48 $ 371.00 $ 34.17 $ 367.67 $ 33.50 $ 360.46 $ 31.70 $ 341.09
Over 150 000 sf $ 33.22 $ 357.45 $ 32.92 $ 354.22 $ 32.27 $ 347.23 $ 30.54 $ 328.61
Reprinted with permission from: Schedule of Unit Costs, Toronto Real Estate Board.
Additional information contained in Schedule of Unit Costs can be obtained through the Toronto Real Estate Board.
B. SHELL
B10 Superstructure
1010 Floor Construction N/A — — —
6.0%
1020 Roof Construction Metal deck on open web steel joists S.F. Roof 8.90 8.90
B20 Exterior Enclosure
2010 Exterior Walls Face brick with concrete block backup 70% of wall S.F. Wall 30.86 14.04
2020 Exterior Windows Window wall 30% of wall Each 45.75 8.92 20.2%
2030 Exterior Doors Aluminum and glass Each 3478 6.96
B30 Roofing
3010 Roof Coverings Built-up tar and gravel with flashing;
perlite/EPS composite insulation S.F. Roof 6.10 6.10 4.4%
3020 Rood Openings Roof hatches S.F. Roof .47 .47
C. INTERIORS
1010 Partitions Gypsum board on metal studs 25 S.F. Floor/L.F. Partition S.F. Partition 5.78 2.08
1020 Interior Doors Hollow core wood 1000 S.F. Floor/Door Each 488 .49
1030 Fittings N/A — — —
2010 Stair Construction N/A — — — 17.6%
3010 Wall Finishes Paint S.F. Surface 2.47 1.78
3020 Floor Finishes Quarry tile S.F. Floor 15.36 15.36
3030 Ceiling Finishes Mineral fiber tile on concealed zee bars S.F. Ceiling 6.38 6.38
D. SERVICES
D10 Conveying
1010 Elavators & Lifts N/A — — —
1020 Escalators & Moving Walls N/A — — — 0.0%
D20 Plumbing
2010 Plumbing Fixtures Kitchen, bathroom and service fixtures, supply and
drainage 1 Fixture/400 S.F. Floor Each 3092 7.73
2020 Domestic Water Distribution Gas fired water heater S.F. Floor 4.52 4.52 9.4%
2040 Rain Water Drainage Roof drains S.F. Roof 1.65 1.65
D30 HVAC
3010 Energy Supply N/A — — —
3020 Heat Generating Systems Incuded in D3050 — — —
3030 Cooling Generating Systems N/A — — — 12.2%
3050 Terminal & Package Units Multizone unit, gas heating, electric cooling;
kitchen ventilation S.F. Floor 18.15 18.15
3090 Other HVAC Sys. & Equipment N/A — — —
D40 Fire Protection
4010 Sprinklers Sprinklers, light hazard S.F. Floor 6.12 6.12
5.2%
4020 Standpipes Standpipe S.F. Floor 1.66 1.66
D50 Electrical
5010 Electrical Service/Distribution 400 ampere service, panel board and feeders S.F. Floor 4.30 4.30
5020 Lighting & Branch Wiring T-8 fluorescent fixtures, receptacles, switches, A.C.
and misc power S.F. Floor 9.89 9.89 12.2%
5030 Communications & Security Addressable alarm systems and emergency lighting S.F. FLoor 3.44 3.44
5090 Other Electrical Systems Emergency generator, 7.5 kW S.F. Floor .38 .38
F. SPECIAL CONSTRUCTION
1020 Integrated Construction N/A — — —
0.0%
1040 Special Facilities N/A — — —
• provide excellent, comprehensive, and full extent of the contingency allowance, can
reliable data if used with appropriate be plainly seen. However, some project managers
qualifications or multipliers; prefer the contingency to be apportioned for
• are assembled from real project data supplied each line item in addition to showing a general
by owners and contractors from the previous contingency at the end.
year;
• are available for Canada only, or for all of Professional Service for
North America (amounts can be adjusted to
the individual cities or regions).
Each Phase of the Project
Use a checklist such as the “Checklist for the
The data may be used for entire buildings or
Management of the Architectural Project” (refer
individual components. Note that the data are
to Chapter 2.3.1, Management of the Project)
more reliable for estimating in Canada when
to ensure that all cost estimating tasks are
obtained from Canadian publications or sources.
attended to at the appropriate time.
Data from non-Canadian sources may not be
reliable for estimating purposes when the value
The sections below are a commentary on the
of the dollar is fluctuating.
lists of tasks.
Architects should:
Phase A. Pre-agreement Phase
• build forecasts using this data carefully and
By listing all cost-related tasks, the architect:
methodically;
• carefully read the descriptions of the • ensures that every aspect of spending on
scope and cost allowances to ensure that the project will be reviewed by either the
the proposed building estimate is based architect, the client or another party;
on a comprehensive list of items which • can prepare a complete proposal for services.
apply exactly;
• become familiar with the format and methods The purpose is to:
employed prior to using any information.
• make the client aware that this service will
be required to complete the entire project;
Contingencies
• identify who will be responsible for
Theoretically, every budget estimate should investigating and supplying the forecasting
predict the actual (final) cost of the completed information.
project. In practice, this means that contingency
allowances of decreasing size must be applied Phase B. Schematic Design Phase
to project and construction budgets as relevant
In this phase, the architect establishes
information develops during the design process.
a preliminary design and a construction cost
There are two contingencies and it is important
estimate for the project, based on the most
to distinguish between design contingencies and
reliable information available at the time from
construction contingencies and identify both in
consultants and other specialists. The architect
any estimate in addition to any escalation
may either:
amount. Contingencies, which may be as high as
25% at the early stages of a project, will • instruct the design team to continue with
decrease to 2%-5% as the degree of uncertainty conceptual work that will meet or satisfy
is reduced. Construction contingencies for the agreed-upon budget; or
renovation work are higher. • review the scope, quality and cost for some
or all of the building elements to re-define
Most government agencies involved in the project to fit within a pre-determined
construction, as well as private companies, cost limit;
banks, and other financial institutions, expect • revise the budget and redefine the scope of
a single contingency amount to be shown at the project.
the bottom of a budget. This figure, giving the
Definitions
Construction Budget: The client’s budget for the construction cost, including contingencies for cost
increases.
Element: Term used in cost estimating to describe a component of a building, such as sub-structure
(footings, foundations) or envelope (walls and roof).
Estimate: To form and state a general idea of; an opinion or judgement (as to such factors as value,
time, size).
Indexing: Applying an index or factor to adjust costs for one geographic region to another. (A typical
index might be expressed as a percentage such as 102.7%.)
Project Budget: The client’s estimated total expenditure for the entire project. It includes, but is not
limited to, the construction budget, professional fees, costs of land, rights of way, and all other costs
to the client for the project.
Quantity Survey: A bill of quantities or a detailed listing and quantities of all items of material and
equipment necessary to construct a project.
References
American Society for Testing Materials (ASTM). publishes 24 various standards on from the Committee
E06.81 on Building Economics.
www.astm.org/COMMIT/SUBCOMMIT/E0681.htm
Derman, Asher, Ph.D. “Embodied Energy, Air Pollution, and Materials, Part 1.” AIA Environmental Guide.
Washington, D.C.: The American Institute of Architects Press, January 1993.
Foster, Norman et al. Construction Estimates From Take-Off to Bid. Third Edition. New York, NY: Hill, 1961.
Kirk, Stephen J. and Alphonse Dell’Isola. Life Cycle Costing for Design Professionals. Second Edition.
New York, NY: McGraw-Hill, 1995.
REED Construction Data publishes a range statistics and economic information on the construction
industry, as well as cost estimating tools and books.
www.canadata.com
www.rsmeans.com
Toronto Real Estate Board. Schedule of Unit Costs. Published annually. Toronto, Ont.