You are on page 1of 21

2.

3 Management of the Project

2.3.3 Cost Planning


and Control

2.3.3

Canadian
Handbook of
Practice
for
Architects
Introduction
Providing Advice on Costs
The Role of the Architect in Cost Planning and Control
Formats for Presentation of Cost Information
Liability of the Architect

Methods of Preparing Cost Estimates


General
Classes of Cost Estimates
Elemental Costs
Area
Volume
Unit Use

Factors Affecting Costs


Economic and Political
Environmental
Building Type and Design
Characteristics of the Owner/Client
Definition of Project Requirements (Functional Program)
2.3.3

Type of Construction Project Delivery


Owner’s Responsibilities and Timetable
Other Factors

Techniques
Cost Consultants
Construction Price Index
Publications
Contingencies

Professional Service for Each Phase of the Project


Phase A. Pre-agreement Phase
Phase B. Schematic Design Phase
Phase C. Design Development Phase
Phase D. Construction Documentation Phase
Phase E. Bidding and Negotiation Phase
Phase F. Contract Administration Phase

Life Cycle Costs

Value Analysis or Value Engineering

Embodied Energy Cost Analysis or Embodied Energy Consumption

Definitions

References

Appendix — Description of the Classes of Estimates used by PWGSC


for Construction Costing of Building Projects
Cost Planning and Control Chapter 2.3.3 Volume 2

Cost Planning and Control


Introduction Providing Advice on Costs
In most client-architect agreements, one
The capital cost for the construction of the project responsibility of the architect is to prepare a
is generally established by the client during the construction cost estimate. This estimate is
pre-design phase, expressed in terms of a neither a quotation nor a guarantee. Due to the
construction budget corresponding to the relative variable market conditions, the architect should
size of the building. never guarantee or warrant a construction cost
estimate. In fact, such a warranty could void any
The importance of cost planning and control in professional liability insurance policy. Nevertheless,
the delivery of professional architectural services the architect is expected to deliver the normal,
cannot be overemphasized. Clients are unlikely professional standard of care in preparing cost
to allow their architect to proceed unless estimates and providing cost advice.
the architect first estimates the cost of
a venture and then monitors the process. Cost Whenever suitably experienced personnel are not
management is more common today because available in-house, architects or owners should
of increased expertise in this field and the hire the best available cost consultants. If
availability of sophisticated analytical tools. preferred, the architect or cost consultant should
form an alliance with business associates who
are contractors or in the development industry,
or they should establish an ongoing relationship
with a quantity surveyor.

Illustration 1: Cost Planning and Control by Project Stages

Cost Planning Cost Control

Cost analysis
Final estimate
and cost check
Cost checks
Cost limit First cost
established plan

Requirements Schematics Design Contract Bid/ Construction Take-over Post-


and Pre-design Development Documents — Contract construction
Drawings and Award
Specifications

Budget Cost Estimates Contract Administration


Evaluation • evaluation of alternatives
• Certificates for Payment
• Change Orders

Canadian Handbook of Practice for Architects January 2009 1


Volume 2 Chapter 2.3.3 Cost Planning and Control

The Role of the Architect in Cost Planning • initiate and control the preparation of cost
and Control information;
• manage team members to ensure that the
To ensure that the project will be well-defined work stays within the agreed-upon budget;
and realized within a predicted cost limit, cost • set or adjust limits;
planning (also known as cost control, cost • exercise maximum influence on decisions
analysis, or cost management) requires: affecting costs.
• effective cost estimating;
Once equipped with access to reliable and
• financial analysis of various components;
current cost information available at all stages
• management of the design and construction
of a project, architects should:
documentation process.
• use this resource with confidence;
Cost planning (or the preparation of construction • express information in standard formats;
cost estimates) is done in the predesign and • be consistent and methodical;
design stages, whereas cost control (or the • avoid ambiguity;
monitoring of construction costs) is done at the • list all assumptions clearly whenever cost
later stages. Refer to Illustration 1. information is published;
• promptly confirm in writing any cost
Formats for the Presentation information provided verbally;
of Cost Information • consider providing references and comparable
projects when issuing information;
The client usually summarizes overall project
• start a cost information file for each project
costs in a “Global” or Project Budget which:
and keep it updated;
• lists all expenditures needed to complete • analyze each project on completion (refer to
every aspect of the venture; Chapter 2.3.1, Management of the Project);
• incorporates information provided by the • maintain files containing reliable historic
architect for the construction component cost data;
of the budget with a detailed breakdown. • check historic cost data in detail to ensure
comparability with the current project.
Refer to Illustration 2 which suggests some
of the “global” and “soft” costs that must Liability of the Architect
be considered.
In an architectural practice, liability for incorrect
cost estimates cannot be avoided, whether or
Prior to delivering cost advice on a regular basis,
not the architect is acting as the project
the architect should:
manager or is providing limited services with no
• make the provision of cost advice and project management responsibilities.
cost management a priority;
• make specific efforts to become Methods of Preparing
knowledgeable;
• develop in-house experience and skills;
Cost Estimates
• maintain up-to-date records of historic cost
General
data;
• emphasize to clients the importance of cost Cost forecasting is an important and rigorous
estimating and related services. activity. All cost estimates:
• work on the principle of forecasting based
To ensure effective cost management, every team on historic data;
member must be vigilant about the effect that • require that the original data be selected,
all design, detailing or specification decisions carefully and methodically, by experienced
could have on the cost of individual components personnel.
of the project, estimated during the initial
budget preparation. The project manager will:

2 January 2009 Canadian Handbook of Practice for Architects


Cost Planning and Control Chapter 2.3.3 Volume 2

The success of any method depends on: Cost Estimate Class C:


Schematic Design
• the reliability of the raw historic data:
• the ability to adjust the data to suit the • prepared at an early stage in the project,
characteristics of the new project and to when drawings are preliminary in nature;
market conditions; • based on:
• the similarity of the new project in as many type of construction;
ways as possible to the examples from which quantities of materials;
data are available; • includes all assumptions or qualifications
• the extent to which the analysis is broken to the estimate;
down into a large number of small • includes a relatively large design contingency
components, instead of a few large allowance which is used to provide for
unit headings. changes in scope and because information
is more limited.
Therefore, historic data must contain as much
descriptive detail as possible, so that differences Cost Estimate Class B:
may be identified and precise adjustments made. Design Development
• the estimating process is repeated when
Classes of Cost Estimates
additional specification and drawing
Government and institutional clients commonly information becomes available, using an
use this method, and usually refer to these expanded format under the original headings;
estimates as Class “C” Estimate, Class “B” • the reduction in uncertainty made possible
Estimate, etc. Refer to “Appendix — Description by better information from the design team
of the Classes of Estimates used by PWGSC for allows for a reduced design contingency
Construction Costing of Building Projects” at allowance.
the end of this chapter. From the outset of the
project, cost information is arranged under the Cost Estimate Class A:
standard MasterFormat™ divisions, which Construction Documentation
uses the typical trade and supplier headings
• as the construction documents become more
that will eventually be used during construction.
complete, the process continues and the
This same format is usually used by contractors
contingency allowance is reduced further.
for preparing tenders and for the preparation
of applications for payment. The data in this
Advantages:
format simplify retrieval (from files or electronic
• the most reliable method if undertaken
sources) for calculating detailed budgets for the
carefully from the start;
next project.
• well-suited when cost advice is being supplied
to the architect by contractor/construction
The following is a description of each level:
managers and suppliers;
• Cost Estimate Class D: • the information stays current and relevant
• Functional Program throughout pre-construction;
• project leaders can build up a history of,
• Prepared prior to commencement of the
and the knowledge and skills for, cost
design;
estimating — especially if building projects
• based on
are similar within the architectural practice.
the functional program and historic data;
adjusted to take into account assumptions
Disadvantages:
regarding inflation, location, risk, quality,
• requires an estimator with both design and
size and project timing;
construction experience;
• a rough order of magnitude.
• requires the ability to foresee all the typical
trades needed to complete the building.

Refer to Illustration 3 for an application of this


estimating method.

Canadian Handbook of Practice for Architects January 2009 3


Volume 2 Chapter 2.3.3 Cost Planning and Control

Illustration 2: Project Budget

Typical Industrial Original Variance Last Variance Current Notes


Manufacturing Budget Budget Reporting
Building Budget
Land
Land purchase price $ - 0 $ - 0 $ -
Land transfer tax $ - 0 $ - 0 $ -
Legal fees $ - 0 $ - 0 $ -
Construction
Building $ - 0 $ - 0 $ -
Contingency $ - 0 $ - 0 $ -
Equipment $ - 0 $ - 0 $ -
Racking $ - 0 $ - 0 $ -
Permit $ - 0 $ - 0 $ -
Insurance $ - 0 $ - 0 $ -
Parkland dedication $ - 0 $ - 0 $ -
Development charges $ - 0 $ - 0 $ -
Sewer impost levy $ - 0 $ - 0 $ -
Service connections $ - 0 $ - 0 $ -
Owners FF&E $ - 0 $ - 0 $ -
General contractors bonding $ - 0 $ - 0 $ -
Design
Architect $ - 0 $ - 0 $ -
Structural Engineer $ - 0 $ - 0 $ -
Mechanical Engineer $ - 0 $ - 0 $ -
Electrical Engineer $ - 0 $ - 0 $ -
Soils Test/Environmental $ - 0 $ - 0 $ -
Landscape Consultant $ - 0 $ - 0 $ -
Equipment Engineer $ - 0 $ - 0 $ -
Cost Planning $ - 0 $ - 0 $ -
Surveyor $ - 0 $ - 0 $ -
Misc. fees $ - 0 $ - 0 $ -
Legal & Administration
Legal fees $ - 0 $ - 0 $ -
Development Management $ - 0 $ - 0 $ -
Project Management $ - 0 $ - 0 $ -
Realty Taxes $ - 0 $ - 0 $ -
Site Plan & Misc. costs $ - 0 $ - 0 $ -
Marketing/Pre-opening/
Commissions
Marketing/sales/
leasing commissions $ - 0 $ - 0 $ -
Utilities prior to opening $ - 0 $ - 0 $ -
Commissions $ - 0 $ - 0 $ -
Finance
Commitment fees $ - 0 $ - 0 $ -
L.C. fees $ - 0 $ - 0 $ -
Project Manager $ - 0 $ - 0 $ -
Interim finance $ - 0 $ - 0 $ -
Appraisal $ - 0 $ - 0 $ -
Contingency
Design contingency $ - 0 $ - 0 $ -
Construction contingency $ - 0 $ - 0 $ -
Escalation
Government Taxes
GST on monthly payments 0 0
GST monthly input credits 0 0
Project Total $ - 0 $ - 0 $ -

4 January 2009 Canadian Handbook of Practice for Architects


Cost Planning and Control Chapter 2.3.3 Volume 2

Illustration 3: Uniformat Estimates

Summary Page Schematic Contingency Variance % Design Contingency Variance % Construction Contingency
Design Developmt Documents
Level 1 Level 2 Level 3
Budget Status Budget Budget Budget

1. General requirements $ - $ - 0% $ - 0% $ -
2. Site Work $ - 0% $ - 0% $ -
3. Concrete $ 65,000 $ 15,000 115% $ 75,000 $ 7,500 107% $ 80,000 $ 4,000
4. Masonry $ - 0% $ - 0% $ -
5. Metals $ - 0% $ - 0% $ -
6. Wood and Plastics $ - 0% $ - 0% $ -
7. Thermal and
Moisture Protection $ - 0% $ - 0% $ -
8. Doors and Windows $ - 0% $ - 0% $ -
9. Finishes $ - 0% $ - 0% $ -
10. Specialties $ - 0% $ - 0% $ -
11. Equipment $ - 0% $ - 0% $ -
12. Furnishings $ - 0% $ - 0% $ -
13. Special Construction $ - 0% $ - 0% $ -
14. Conveying $ - 0% $ - 0% $ -
15. Mechanical $ - 0% $ - 0% $ -
16. Electrical $ - 0% $ - 0% $ -
Total
Construction
Contingency % $ - 0% $ - 0% $ -
Total Construction $ - 0% $ - 0% $ -

3 Concrete Schematic Contingency Variance % Design Contingency Variance % Construction Contingency


Design Developmt Documents
Level 1 Level 2 Level 3
Budget Status Budget Budget Budget

STRUCTURAL CAST-IN-
PLACE FORMWORK $ 20,000
Accessories $ 1,500 $ 75
Expansion joints $ 1,000 $ 50
Elevated slabs $ 10,000 $ 500
Footing $ 2,000 $ 100
Slab on Grade $ 2,000 $ 100
Walls $ 2,500 $ 125
Stairs $ 4,000 $ 200

CONCRETE
REINFORCEMENT $ 10,000
Reinforcing steel $ 9,000 $ 450
W.W. Fabric $ 3,000 $ 150

CAST-IN-PLACE
CONCRETE $ 35,000
Admixtures $ 1,000 $ 50
Ready Mix $ 17,000 $ 850
Elevated slabs $ 7,000 $ 350
Footings $ 2,000 $ 100
Slab on Grade $ 5,000 $ 250
Walls $ 2,000 $ 100
Stairs $ 3,000 $ 150

CONCRETE FINISHING $ 10,000


Floors $ 6,000 $ 300
Walls $ 2,000 $ 100
TOTAL DIVISION 3 —
CONCRETE $ 65,000 $ 15,000 $ 75,000 $ 7,500 $ 80,000 $ 4,000

Canadian Handbook of Practice for Architects January 2009 5


Volume 2 Chapter 2.3.3 Cost Planning and Control

Elemental Costs Extensive floor area cost data are available from
a number of sources as a basis for interpolation
Quantity surveyors often use the elemental cost
and use in forecasting. These should be used
method as the standard format for presenting
when providing general cost advice and for the
cost information. This method:
calculation of overall project costs.
• divides the building into major elements
such as structure, exterior closure; Advantages:
• uses these elements to provide a cost • the concept of “floor area” is easily
framework which is useful throughout the understood and applicable to all buildings;
life of the project; • costs for an individual component or element
• is applicable to new or existing buildings; of a building, or for the entire structure, are
• uses these elements to form the basis for straightforward to calculate;
applying relevant cost information from • very simplified historic cost information,
similar projects. expressed as costs per m2/per ft2 for
completed projects, is available for many
Advantages: different building types.
• the process assumes that the approximate
size of a building is known; Disadvantages:
• the process can proceed without construction • does not account for unique conditions
drawings and specifications; or special construction;
• particularly useful for architects during • is simplistic and can be misinterpreted.
design development, when trade-offs
between elements can be considered to The architect should limit the use of this basic
improve the quality of the project without information by using it only as a general guide
compromising the total budget. at the pre-design stage.

Disadvantages: Refer to Illustration 5 for typical data provided


• cuts across the traditional construction for preparing a construction cost estimate based
trade areas (refer to “Classes of on area.
Cost Estimates” section above);
• can be difficult to double-check information Volume
from real project data without complex, (Cost per m3)
time-consuming analysis.
This method is not widely used, except:
The elemental cost method is best left to • for certain specialized building types such as
quantity surveyors or those experienced in warehousing (particularly freezer buildings);
the calculation of building costs, unless the • for multi-storey buildings where the floor
architect has extensive in-house records which area method might not adequately reflect
have been analyzed and are easily accessible. the true costs;
• as a double-check on the other methods
Refer to Illustration 4 for a typical elemental being used.
cost forecast.
Unit Use
Area (Cost per bed, cost per seat, etc.)
(Cost per m2/per ft2)
This method uses very simplified historic data
The terms “cost per square metre/per square as a basis for calculating cost. It is brief, to the
foot” are used throughout the development and point, and relatively reliable — provided that
construction industries, and are recognized by the historic data on projects are comparable.
public and private institutions and the public at This method is useful for preliminary budgeting
large. Both imperial and metric measurements because the result is general in nature and more
continue to be used. obviously “approximate.”

6 January 2009 Canadian Handbook of Practice for Architects


Cost Planning and Control Chapter 2.3.3 Volume 2

Illustration 4: Elemental Cost Forecast

Typical Example of
Elemental Format Elemental Elemental Elemental Cost/SF Total %
using Canadian Institute Quantity Unit Rate Amount $/SF $
of Quantity Surveyors SF $/SF
Measurement and
Pricing Method
A SHELL
A1 SUBSTRUCTURE
A11 Foundation 252,800 $ 3.75 $ 948,000 $ 3.39 $ 948,000 3.96%
A12 Basement Excavation 0 $ -
A2 STRUCTURE
A21 Lowest floor
construction 252,800 $ 10.00 $ 2,528,000 $ 9.03
A22 Upper floor
construction 27,205 $ 11.98 $ 325,916 $ 1.16
A23 Roof construction 252,800 $ 12.00 $ 3,033,600 $ 10.83 $ 5,887,516 24.61%
A3 EXTERIOR ENCLOSURE
A31 Walls below grade 0 $ - $ - $ -
A32 Walls above grade 64,800 $ 7.99 $ 517,752 $ 1.85
A33 Windows & Entrance 1,656 $ 50.12 $ 82,999 $ 0.30
A34 Roof coverings 252,800 $ 4.00 $ 1,011,200 $ 3.61
A35 Projections 64,800 $ 0.77 $ 49,896 $ 0.18 $ 1,661,847 6.95%
B INTERIORS
B1 PARTITIONS
B11 Partitions 179,915 $ 7.19 $ 1,293,589 $ 4.62 $ 1,525,589 6.38%
B12 Doors 232 no $ 1,000.00 ea $ 232,000
B2 FINISHES
B21 Floor Finishes 266,005 $ 2.00 $ 532,010 $ 1.90 $ 747,742 3.13%
B22 Ceiling Finishes 266,005 $ 0.38 $ 101,082 $ 0.36
B23 Wall Finishes 424,630 $ 0.27 $ 114,650 $ 0.41
B3 FITTING & EQUIPMENT
B31 Fitting & Fixtures 280,005 $ 0.18 $ 50,401 $ 0.18
B32 Equipment 280,005 $ 0.45 $ 126,002 $ 0.45
B33 Conveying Systems 0 $ - $ 50,000 $ 0.18 $ 226,403 0.95%
C SERVICES
C1 MECHANICAL 280,005 $ 22.50 $ 6,300,113 $ 22.50 $ 6,300,113 26.33%
C11 Plumbing & Drainage
C12 Fire Protection
C13 HVAC
C14 Controls
C2 ELECTRICAL 280,005 $ 6.00 $ 1,680,030 $ 6.00 $ 1,680,030 7.02%
C21 Service & Distribution
C22 Lighting, Devices
& Heating
C23 Systems & Ancillaries
NET BUILDING COST excluding site $ 67.78 $ 18,977,239 79.31%

D SITE
D1 SITE WORK $ 1,300,000 $ 4.64 $ 1,300,000 5.43%
D11 Site Development $ 1,000,000 $ 3.57
D12 Mechanical Site services $ 200,000 $ 0.71
D13 Electrical Site services $ 100,000 $ 0.36
D2 ANCILLARY WORK $ - $ -
D21 Demolition $ - $ -
D22 Alterations $ - $ -
NET BUILDING COST including site $ 72.42 $ 20,277,239 84.75%

Z MARK UPS
Z1 GENERAL REQUIREMENTS
Z11 General requirements 7% $ 1,419,406.74 5.06930978 $ 1,419,407 5.93%
TOTAL CONSTRUCTION ESTIMATE excluding contingency
Z2 CONTINGENCIES 11% 2,230,496.303 $7.97 $ 2,230,496 9.32%
Z21 Design contingency 0%
Z22 Escalation contingency 6% 1,216,634.347 $ 4.35
Z23 Construction contingency 5% 1,013,861.956 $ 3.62
GOODS AND SERVICES TAX EXCLUDED $ -

TOTAL CONSTRUCTION ESTIMATE including Allowances $ 85.45 $ 23,927,142 100.00%


Gross Floor Area
280 000 sf

Canadian Handbook of Practice for Architects January 2009 7


Volume 2 Chapter 2.3.3 Cost Planning and Control

Advantages: Architects should:


• provides a quick reference or check at
• use this method with caution, for preliminary
the early design stages.
advice only, and as a convenient double-check
for comparison purposes;
Disadvantages:
• spell out clearly all qualifications and
• projects are rarely identical, so careful
assumptions when the information is
adjustment must be made for differences;
released.
• the circumstances, location, and date of
construction may render the historic
Do not confuse unit use with the term unit cost
information of questionable value, even
which can be expressed in a number of different
though the projects may be very similar
numerical unit forms and is a technique used for
in physical form;
calculating building and component costs:
• the calculation of differences may require
extensive analysis of the information using Unit Cost e.g., Concrete curbs: $13 lf (linear foot)
some of the other methods referred to above Lavatory — wall hung $1,090 ea (each)
(sometimes, this is best done by quantity
Unit Use e.g., 2,000 seat cinema @ $1,500 per seat
surveyors).
60-room motel @ $125,000 per room

Illustration 5: Typical Data used in the Area Method Cost Forecast

Typical Page From Jan-97 Jan-96 Jan-95 Jan-94


Toronto Real Estate Board per/SF per/SM per/SF per/SM per/SF per/SM per/SF per/SM
Schedule of Unit Costs’
price $ 10.00

1 INDUSTRIAL BUILDING
16 ft clear height Under 10 000 sf $ 55.51 $ 597.29 $ 55.01 $ 591.91 $ 53.93 $ 580.29 $ 51.03 $ 549.08
10 000 - 20 000 sf $ 46.11 $ 496.14 $ 45.70 $ 491.73 $ 44.80 $ 482.05 $ 42.39 $ 456.12
20 000 - 50 000 sf $ 38.31 $ 412.22 $ 37.96 $ 408.45 $ 37.22 $ 400.49 $ 35.22 $ 378.97
50 000 - 150 000 sf $ 33.24 $ 357.66 $ 32.94 $ 354.43 $ 32.29 $ 347.44 $ 30.56 $ 328.83
Over 150 000 sf $ 31.31 $ 336.90 $ 31.03 $ 333.88 $ 30.42 $ 327.32 $ 28.78 $ 309.67
18 ft clear height Under 10 000 sf $ 57.49 $ 618.59 $ 56.97 $ 613.00 $ 55.85 $ 600.95 $ 52.85 $ 568.67
10 000 - 20 000 sf $ 47.55 $ 511.64 $ 47.12 $ 507.01 $ 46.20 $ 497.11 $ 43.72 $ 470.43
20 000 - 50 000 sf $ 39.27 $ 422.55 $ 38.91 $ 418.67 $ 38.15 $ 410.49 $ 36.10 $ 388.44
50 000 - 150 000 sf $ 33.84 $ 364.12 $ 33.54 $ 360.89 $ 32.88 $ 353.79 $ 31.11 $ 334.74
Over 150 000 sf $ 31.62 $ 340.23 $ 31.33 $ 337.11 $ 30.72 $ 330.55 $ 29.07 $ 312.79
22 ft clear height Under 10 000 sf $ 58.45 $ 628.92 $ 57.92 $ 623.22 $ 56.78 $ 610.95 $ 53.73 $ 587.13
10 000 - 20 000 sf $ 48.22 $ 518.85 $ 47.79 $ 514.22 $ 46.85 $ 504.11 $ 44.33 $ 476.99
20 000 - 50 000 sf $ 40.80 $ 439.01 $ 40.43 $ 435.03 $ 39.64 $ 426.53 $ 37.51 $ 403.61
50 000 - 150 000 sf $ 34.46 $ 370.79 $ 34.15 $ 367.45 $ 33.48 $ 360.24 $ 31.68 $ 340.88
Over 150 000 sf $ 32.94 $ 354.43 $ 32.64 $ 351.21 $ 32.00 $ 344.32 $ 30.28 $ 325.81
25 ft clear height Under 10 000 sf $ 59.00 $ 634.84 $ 58.47 $ 629.14 $ 57.32 $ 616.76 $ 54.24 $ 583.62
10 000 - 20 000 sf $ 49.67 $ 534.45 $ 49.23 $ 529.71 $ 48.26 $ 519.28 $ 45.67 $ 491.41
20 000 - 50 000 sf $ 41.11 $ 442.34 $ 50.74 $ 545.96 $ 39.94 $ 429.75 $ 37.79 $ 406.62
50 000 - 150 000 sf $ 34.48 $ 371.00 $ 34.17 $ 367.67 $ 33.50 $ 360.46 $ 31.70 $ 341.09
Over 150 000 sf $ 33.22 $ 357.45 $ 32.92 $ 354.22 $ 32.27 $ 347.23 $ 30.54 $ 328.61

Reprinted with permission from: Schedule of Unit Costs, Toronto Real Estate Board.
Additional information contained in Schedule of Unit Costs can be obtained through the Toronto Real Estate Board.

8 January 2009 Canadian Handbook of Practice for Architects


Cost Planning and Control Chapter 2.3.3 Volume 2

Factors Affecting Costs Abroad, in countries where democracy and


respected institutions are stable, commercial
Economic and Political activity can flourish, and competition and true
supply and demand will occur. In certain areas
Several factors influence the construction industry of the world — where some or all of these
and affect building costs. These factors include: factors may be missing — stability is often
• inflation; lacking and construction prices will tend to be
• market conditions; erratic and unpredictable.
• other economic factors;
• political and social climate. Prior to using any raw cost data for estimates,
architects and cost consultants should consider all
Inflation the above factors and make suitable corrections.
Due to economic cycles, inflation and the
consequent escalation of construction costs can Environmental
vary depending on the era and the economic Construction costs are affected by several
factors affecting Canada and the world. Because environmental factors:
inflation is a factor of the cyclical economic
system, especially for construction, architects • site characteristics;
should: • weather, and season of the year;
• location.
• always include an allowance for escalation
as a line item in the project budget; Site Characteristics
• be aware of the trend during the past • challenging topography;
12 months as well as predictions for • natural or built features;
the future; • unusual soil or sub-surface conditions;
• indicate a reference date on all estimates • existence of hazardous wastes, including
• seek input from the client. asbestos, PCBs;
• contaminated soils requiring removal
Market Conditions and/or environmental certification;
Periodically, there is so much demand for • disposal costs of contaminated soils;
construction that it can become almost impossible • adjacent buildings.
to obtain competitive tenders for a project. This
situation results in inflated costs. At the other Weather and Season
extreme, construction costs during recessions — • cost and construction procedures in Canada
particularly for non-union labour rates — may are significantly influenced by the weather
decrease significantly. Such decreases can be and season;
followed by a rapid rise in costs shortly after the • construction activities are cyclical over each
end of the recession. 12-month period (reduced activity from
December through March for exterior
Other Economic Factors construction and excavation);
• the use of union or non-union labour; • winter protection and provision of temporary
• interest rates on financing costs; heating adds to cost.
• large demand for certain building materials;
• exchange rates between nations, for projects Location
with a significant proportion of imported • site characteristics (for example, a project in
materials and equipment. a suburban location will cost less compared
to one in a constricted downtown core —
Political and Social Climate where overhead can be much higher because
In Canada, the political climate (local, provincial, of parking charges, traffic congestion causing
and federal) can affect the timing of a project loss of time and delivery delays, and the
approval, especially around election time. likelihood of more stringent regulatory
requirements);
• construction in remote areas where skilled
labour is unavailable;

Canadian Handbook of Practice for Architects January 2009 9


Volume 2 Chapter 2.3.3 Cost Planning and Control

• distance to sources of supply for materials These factors include:


and trades;
• design requiring high standards of quality or
• use of components that are manufactured
rigorous quality control procedures
at some distance from the site;
(especially long life cycle, redundancies in
• travel distance to dump/disposal sites
spaces);
or recycling depots.
• complex bidding procedures;
• insurance requirements above the norm;
Building Type and Design
• extensive bonding requirements;
Building types range from simple wood-framed • poorly written, sometimes inequitable,
structures to complex, technically sophisticated non-standard contract wording;
buildings such as hospitals and laboratories. • long delays in issuing payments to contractors.
Some costing handbooks classify building
costs under as many as several dozen different The architect should consider adjusting the
types. Construction costs vary considerably estimate based on the type of organization the
($575-$3,700 per m2/$55-$350 per ft2 in client represents.
Canadian dollars).
Definition of Project Requirements
Features affecting cost include: (Functional Program)
Refer to Chapter 2.3.4, Pre-design.
• compliance with building codes;
• method of construction (for example, wood,
The functional program defines the project.
reinforced concrete or steel frame);
To minimize the possibility of cost overruns
• building height and number of storeys;
resulting from changes in the program, review
• building form (a compact building is
the functional intent or objectives. Ask the owner
less expensive than one with the same
to clarify any incomplete or unclear requirements
area that is long and narrow);
prior to providing any architectural service.
• type and range of finishes;
• choice and arrangement of structural,
Changes in the scope of a project can occur
mechanical, and electrical systems;
for many reasons, including:
• the planned life of the structure;
• selection of components (standard or • the development of more specific detailed
off-the-shelf vs. custom-manufactured); requirements by the owner;
• sustainable design requirements such as • external factors such as new technological
material selection and requirements for developments, new legislation or a change
certification. in market conditions;
• lack of sufficient detailed information;
Characteristics of the Owner/Client • a change in client personnel, building users
or stakeholders;
Architects need to recognize the impact that the
• inadequate research prior to developing
type of owner can have on the cost of a project.
the program;
• the addition of new partners or stakeholders.
Sophisticated clients, such as commercial
and industrial corporations or developers
Cost increases due to changes in the program can
who regularly procure design services and
be significant for the owner and the architect at
construction, frequently expect the delivery of
any time, but especially in the construction
completed projects at or below target costs.
documentation stage, when re-design costs and
additional consulting fees arise. Refer to
Other owners, such as certain institutions
Illustration 7.
and government agencies, have entrenched
bureaucratic procedures that effectively preclude
The architect should always keep the owner fully
taking advantage of a competitive system. Some
advised of the potential cost implications of any
owners are unable or unwilling to avoid certain
changes.
factors which can contribute significantly to
project costs.

10 January 2009 Canadian Handbook of Practice for Architects


Cost Planning and Control Chapter 2.3.3 Volume 2

Type of Construction Project Delivery • additional protection and clean-up


expenditures beyond normal requirements;
Contractual relationships between the owner and
• work adjacent to or within certain building
the contractor can have an impact on the cost
types may be subject to limitations on
of a project. Refer to Chapter 2.3.2, Types of
scheduling and on the times when
Construction Project Delivery.
equipment, such as cranes, may be used;
Owner’s Responsibilities and Timetable • demolition and shoring of existing structures;
• abnormal construction phasing.
The owner frequently has requirements which
can affect the construction budget. In all cases, When developing the cost plan of a project,
these should be discussed and approval establish the basic cost of the building. Identify
subsequently sought from the owner. Some of and pull out unusual or site-specific costs and
these circumstances include: justify the overall project budget during the
• a project schedule that is accelerated to suit forecasting process.
an owner’s critical date, such as a school
opening or the timing of an event due to Techniques
market forces;
• late commencement due to reasons beyond Cost Consultants
the owner’s control, for example, winter
Unless the architect has developed the
conditions, resulting in additional
knowledge and systems in-house, expert advice
construction costs;
should be obtained either from:
• delayed commencement of a project during
a time of inflation and currency fluctuations; • independent professional experts
• owners approval process. (quantity surveyors); or
• those intimately involved in everyday
Architects are advised to: construction (development/construction
experts).
• ensure that assumptions attached to any
forecasts include reference to specific timing;
Quantity Surveyors
• check and make adjustments for specific
Quantity surveyors provide professional service at
issues that may influence the cost of the
hourly rates, or at a fixed or percentage
project when using historic cost data.
fee of the construction budget.
Other Factors
Advantages:
Regulations: • independent professional status;
• onerous bureaucratic requirements, such as • their success is based upon their track record
planning regulations or site development of reliability in forecasting;
agreement conditions; • up-to-date archival material that is very
• numerous building code occupancy extensive for many different building projects
classifications within one building; and is easily accessible;
• hazardous demolition, such as removal • quantity surveyors will usually supply
of asbestos; information on comparable projects as a
• recycling regulations and dumping charges double-check to establish credibility;
(tipping fees) for demolition or construction • some larger companies publish their own
debris. updated forecast information yearly.

Inconvenient or unusual work arrangements: Disadvantages:


• construction must be scheduled around the • unit costs are usually historical and often not
ongoing activities of occupants in buildings connected to real-time costs making them
such as hospitals, court houses, shopping less current than costs available from
malls or restaurants; because these activities contractors or construction managers;
bear little relationship to the logic of • detailed cost information may not be
construction, overtime labour costs often available because cost breakdowns are
result; limited to major trade divisions.

Canadian Handbook of Practice for Architects January 2009 11


Volume 2 Chapter 2.3.3 Cost Planning and Control

Cost estimating is as much an art as a science Disadvantages:


and architects are advised to: • unlike a quantity surveyor, who is an
independent consultant, the builder may
• use the services of a quantity surveyor,
not always find it easy to achieve a
whenever appropriate, to increase the
comprehensive overview;
quality and depth of the architectural
• this knowledge is sometimes very specialized
service available within the practice;
and “narrow,” and may not always be
• monitor every aspect of their work to ensure
applicable to new situations;
that the information being prepared is
• certain sources may be less reliable due to
entirely applicable to the current project and
possible self-interest or commercial motives.
that any qualifications or assumptions
Architects should consider:
accompanying the cost information supplied
are precisely in accordance with the client’s • developing an alliance with individuals or
expectations; companies by working together on common
• be satisfied that every item of information is projects before using this source for cost
relevant before passing on this advice to the information;
client; • checking the relevance of all data supplied,
• ensure there are sufficient fees: even if they have confidence in the
for coordination when Construction Manager information source;
is involved, or value analysis or value • paying a fee for all cost information from
engineering is undertaken; construction industry sources.
• to include the quantity surveyor’s fees or
cost estimating. [Note: some clients prefer to It should be noted that when there may be a
engage a quantity surveyor directly; in these conflict of interest, information from a “free”
situations, the architect should allow for fees source may not be reliable.
for coordination.]
Construction Price Index
Construction Managers and other Development/
Construction price index data are usually
Construction Experts
published by government agencies and private
Other sources of expertise directly from the
companies. These publications are:
construction industry include construction
managers, contractors, design-builders, and • useful only as a guide to show trends;
developers. • usually some months out-of-date;
• often presented in graph form for ease of
Advantages: communication.
• results are likely to be reliable for calculating
costs for various classes of Cost Estimates Publications
using unit costs assigned to area
Construction cost data are available from
measurements for spot-checking individual
government agencies, private interest groups,
elements of a project where the proposed
private companies, and quantity surveyors. The
building is very similar to recently completed
information comes in printed or electronic form,
projects;
and the cost varies considerably depending on
• information will be very current because
the amount of detail, completeness, and ease of
these sources are involved with construction
use. Data from government agencies are more
spending every day and because they have
useful for identifying trends and differences in
access to trades and suppliers who are also
national, regional, and local costs than for
specialists;
calculating the cost of a specific building.
• these sources monitor trends and are
generally aware of the dynamics affecting
Refer to Illustration 6 for an example of cost
construction costs.
information from a typical publication.
Extensive detailed information for most building
types can be purchased in hard copy or
electronic form. Such publications:

12 January 2009 Canadian Handbook of Practice for Architects


Cost Planning and Control Chapter 2.3.3 Volume 2

Illustration 6: Typical Cost Information


Model costs calculated for a 1-storey building with Restaurant, Fast Food
10’ storey height and 4,000 square feet of floor area
Unit Unit Cost % Of
Cost Per S.F. Sub-Total
A. SUBSTRUCTURE
1010 Standard Foundations Poured concrete; strip and spread footings S.F. Ground 2.57 2.57
1020 Special Foundations N/A — — —
1030 Slab on Grade 4" reinforced concrete with vapor barrier and granular base S.F. Slab 4.74 4.74 8.7%
2010 Basement Excavation Site preparation for slab and trench for foundation
and footing S.F. Ground .46 .46
2020 Basement Walls 4' foundation wall L.F. Wall 78 5.07

B. SHELL
B10 Superstructure
1010 Floor Construction N/A — — —
6.0%
1020 Roof Construction Metal deck on open web steel joists S.F. Roof 8.90 8.90
B20 Exterior Enclosure
2010 Exterior Walls Face brick with concrete block backup 70% of wall S.F. Wall 30.86 14.04
2020 Exterior Windows Window wall 30% of wall Each 45.75 8.92 20.2%
2030 Exterior Doors Aluminum and glass Each 3478 6.96
B30 Roofing
3010 Roof Coverings Built-up tar and gravel with flashing;
perlite/EPS composite insulation S.F. Roof 6.10 6.10 4.4%
3020 Rood Openings Roof hatches S.F. Roof .47 .47

C. INTERIORS
1010 Partitions Gypsum board on metal studs 25 S.F. Floor/L.F. Partition S.F. Partition 5.78 2.08
1020 Interior Doors Hollow core wood 1000 S.F. Floor/Door Each 488 .49
1030 Fittings N/A — — —
2010 Stair Construction N/A — — — 17.6%
3010 Wall Finishes Paint S.F. Surface 2.47 1.78
3020 Floor Finishes Quarry tile S.F. Floor 15.36 15.36
3030 Ceiling Finishes Mineral fiber tile on concealed zee bars S.F. Ceiling 6.38 6.38

D. SERVICES
D10 Conveying
1010 Elavators & Lifts N/A — — —
1020 Escalators & Moving Walls N/A — — — 0.0%

D20 Plumbing
2010 Plumbing Fixtures Kitchen, bathroom and service fixtures, supply and
drainage 1 Fixture/400 S.F. Floor Each 3092 7.73
2020 Domestic Water Distribution Gas fired water heater S.F. Floor 4.52 4.52 9.4%
2040 Rain Water Drainage Roof drains S.F. Roof 1.65 1.65
D30 HVAC
3010 Energy Supply N/A — — —
3020 Heat Generating Systems Incuded in D3050 — — —
3030 Cooling Generating Systems N/A — — — 12.2%
3050 Terminal & Package Units Multizone unit, gas heating, electric cooling;
kitchen ventilation S.F. Floor 18.15 18.15
3090 Other HVAC Sys. & Equipment N/A — — —
D40 Fire Protection
4010 Sprinklers Sprinklers, light hazard S.F. Floor 6.12 6.12
5.2%
4020 Standpipes Standpipe S.F. Floor 1.66 1.66
D50 Electrical
5010 Electrical Service/Distribution 400 ampere service, panel board and feeders S.F. Floor 4.30 4.30
5020 Lighting & Branch Wiring T-8 fluorescent fixtures, receptacles, switches, A.C.
and misc power S.F. Floor 9.89 9.89 12.2%
5030 Communications & Security Addressable alarm systems and emergency lighting S.F. FLoor 3.44 3.44
5090 Other Electrical Systems Emergency generator, 7.5 kW S.F. Floor .38 .38

E. EQUIPMENT & FURNISHING


1010 Commercial Equipment N/A — — —
1020 Institutional Equipment N/A — — —
4.1%
1030 Vehicular Equipment N/A — — —
1090 Other Equipment Walk-in refrigerator S.F. Floor 6.06 6.06

F. SPECIAL CONSTRUCTION
1020 Integrated Construction N/A — — —
0.0%
1040 Special Facilities N/A — — —

G. BUILDING SITEWORK N/A


Sub Total 148.22 100%
CONTRACTOR FEES (General Requirements: 10%, Overhead: 5%, Profit: 10%)) 25% 37.06
ARCHITECT FEES 8% 14.82
Reprinted with permission from: Means Square Foots Costs 2009 Total Building Cost 200.10
© R.S. Means Co., Inc., Kingston, MA, all rights reserved.
Canadian Handbook of Practice for Architects January 2009 13
Volume 2 Chapter 2.3.3 Cost Planning and Control

• provide excellent, comprehensive, and full extent of the contingency allowance, can
reliable data if used with appropriate be plainly seen. However, some project managers
qualifications or multipliers; prefer the contingency to be apportioned for
• are assembled from real project data supplied each line item in addition to showing a general
by owners and contractors from the previous contingency at the end.
year;
• are available for Canada only, or for all of Professional Service for
North America (amounts can be adjusted to
the individual cities or regions).
Each Phase of the Project
Use a checklist such as the “Checklist for the
The data may be used for entire buildings or
Management of the Architectural Project” (refer
individual components. Note that the data are
to Chapter 2.3.1, Management of the Project)
more reliable for estimating in Canada when
to ensure that all cost estimating tasks are
obtained from Canadian publications or sources.
attended to at the appropriate time.
Data from non-Canadian sources may not be
reliable for estimating purposes when the value
The sections below are a commentary on the
of the dollar is fluctuating.
lists of tasks.
Architects should:
Phase A. Pre-agreement Phase
• build forecasts using this data carefully and
By listing all cost-related tasks, the architect:
methodically;
• carefully read the descriptions of the • ensures that every aspect of spending on
scope and cost allowances to ensure that the project will be reviewed by either the
the proposed building estimate is based architect, the client or another party;
on a comprehensive list of items which • can prepare a complete proposal for services.
apply exactly;
• become familiar with the format and methods The purpose is to:
employed prior to using any information.
• make the client aware that this service will
be required to complete the entire project;
Contingencies
• identify who will be responsible for
Theoretically, every budget estimate should investigating and supplying the forecasting
predict the actual (final) cost of the completed information.
project. In practice, this means that contingency
allowances of decreasing size must be applied Phase B. Schematic Design Phase
to project and construction budgets as relevant
In this phase, the architect establishes
information develops during the design process.
a preliminary design and a construction cost
There are two contingencies and it is important
estimate for the project, based on the most
to distinguish between design contingencies and
reliable information available at the time from
construction contingencies and identify both in
consultants and other specialists. The architect
any estimate in addition to any escalation
may either:
amount. Contingencies, which may be as high as
25% at the early stages of a project, will • instruct the design team to continue with
decrease to 2%-5% as the degree of uncertainty conceptual work that will meet or satisfy
is reduced. Construction contingencies for the agreed-upon budget; or
renovation work are higher. • review the scope, quality and cost for some
or all of the building elements to re-define
Most government agencies involved in the project to fit within a pre-determined
construction, as well as private companies, cost limit;
banks, and other financial institutions, expect • revise the budget and redefine the scope of
a single contingency amount to be shown at the project.
the bottom of a budget. This figure, giving the

14 January 2009 Canadian Handbook of Practice for Architects


Cost Planning and Control Chapter 2.3.3 Volume 2

Using up-to-date cost forecasting information,


as well as carefully defining the project scope Itemized prices are costs for a specific item or
and cost limits for the project elements, will section of work for information purposes only.
minimize the risk of significant re-design and Unit prices should only be requested when an
re-definition later. estimated quantity is supplied. Unit prices are
typically requested for large civil engineering
Phase C. Design Development Phase projects; however, certain components (such as
site development work, hidden or indeterminate
In this phase, the architect may:
work) within architectural projects may require
• provide for review and updating of the unit prices.
construction cost estimate as the reliability
of the design and specifications improves; Refer also to Chapter 2.3.9, Construction
• undertake additional analysis, if necessary, to Procurement.
check the construction cost estimate and its
assumptions; RAIC Document Six: The Canadian Standard Form
• refine the building’s scope, design, quality of Contract Between Client and Architect indicates
and details, to ensure they will not exceed in General Condition 3.4 that if the lowest bona
the limits of the construction cost budget. fide bid exceeds the construction cost estimate
by 15%, the architect shall either:
Phase D. Construction Documentation Phase • obtain approval from the client for an
In this phase, the architect may: increase in the construction budget;
• re-bid or negotiate;
• update the construction cost estimate based • modify the construction documents to reduce
on the construction documents (often at the construction cost (for no additional fee).
50% completion and at 95% completion –
the pre-tender stage or at other defined Phase F. Contract Administration Phase
milestones); The architect is usually required to determine
• include allowances in the bid documents. the amounts owing to the contractor under the
contract, based on the architect’s observations
Refer to Chapter 2.3.8, Construction Documents and evaluation of the progress of the work.
— Specifications. The architect then processes the contractor’s
application for payment and prepares a Certificate
Phase E. Bidding and Negotiation Phase for Payment. The elemental cost analysis method
In preparing the bidding documents, the is well-suited for use on a comparative basis in
architect must determine what cost information assessing the contractor’s schedule of values
is needed. The architect must consider the submitted at the outset of the construction phase.
following cost information:
Another architectural service provided during the
• alternative prices; Contract Administration Phase is the evaluation
• itemized prices; of the costs of changes. Having ready access
• unit prices. to historic cost data, to ensure that the
contractor’s quotations are realistic, is very
Refer also to CCDC 23, A Guide to Calling Bids important.
and Awarding Construction Contracts.
Refer also to Chapter 2.3.10, Contract
Traditionally, the architect analyzes the bids. Administration — Office Functions.
The various “alternative prices” from each bidder
must be evaluated and the best overall value for
the client determined. The lowest combination
of base bid and acceptable alternative prices is
normally the choice.

Canadian Handbook of Practice for Architects January 2009 15


Volume 2 Chapter 2.3.3 Cost Planning and Control

The architect usually: The total cost as defined above is relevant to


the long-term costs of owning a building and is
• delivers effective cost management service
of special interest to owner-occupiers such as
throughout the project;
government bodies, condominium corporations,
• provides the owner with regular cost updates
and large institutions.
and advice (this will occur naturally to some
extent during the construction phases when
Before the design development phase begins,
the client receives copies of Proposed
the architect should discuss the importance of
Changes, Change Orders, and Certificates
life cycle costs to the client for the following
for Payment);
reasons:
• endeavours to maintain the supply of
• different construction materials, techniques,
excellent cost advice and well-presented
and systems have different effective life
information throughout a project.
spans;
• considerable expense can arise during the life
Life Cycle Costs of a building to maintain a satisfactory level
of performance;
In the past, building costs often considered only • low construction costs may result in higher
initial or capital construction costs and did not maintenance costs later in the life of the
always include costs associated with operations building.
and maintenance. Recently, high energy and
maintenance costs have highlighted the fact Using a pre-determined and agreed-upon “design
that the “real cost” of a building is not limited length of life” as a base, the life cycle costs
to the construction phase. An analysis of life analysis will:
cycle costs is not a basic service but an optional
or additional service. • assess the initial, maintenance, and
replacement costs for each element of
The objective of life cycle costing is to determine a building (for example, different types
the “total cost” of a building over its lifetime. of mechanical systems and roof membranes
This costing method: can vary significantly in initial cost and in
their anticipated serviceable life);
• allows comparisons to be made between • compare this information with total costs
alternative components or systems; for alternative selections or designs;
• generates an understanding of the design of • study different combinations of all major
a project, how it functions, and how costs elements to identify the best choices to
arise; minimize capital cost;
• facilitates further development of the design. • determine the most advantageous or lowest
life cycle cost for the entire structure;
Life cycle costing of a building can be expressed • incorporate operating costs, including energy
as follows: consumption, in the study.
Total Cost = Capital Cost + Operating Cost +
Maintenance Cost Architects can effectively undertake most
life cycle cost comparison exercises if they
The three types of costs are: have access to adequate cost and material
specification information. A more detailed
• capital costs: the initial cost of constructing analysis should be undertaken by qualified
the project, including the land, fees, and specialist consultants.
carrying costs;
• operating costs: all expenditures for the
servicing of the building during its life
period, for example, lighting, energy,
management, and insurance;
• maintenance costs: those costs associated
with repairs and renewals.

16 January 2009 Canadian Handbook of Practice for Architects


Cost Planning and Control Chapter 2.3.3 Volume 2

Value Analysis or Value The owner may choose to engage an independent


reviewer, rather than the architect/engineers of
Engineering record, in the belief that this will be more likely
to achieve the desired results. This approach can
Sometimes a project will be subjected to value
sometimes result in the substitution of inferior
analysis or value engineering. This service is not
or inappropriate products, simply because they
a basic service of the architect and is frequently
are cheaper, however, this is not true value
undertaken with the use of an external
engineering but rather cost-cutting. In these
facilitator. The best time to apply any value
circumstances, the architect must be informed and
analysis is early in the design process. One
given the opportunity to advise the owner on the
limitation of value engineering is that it
consequences of the proposed changes.
generally does not take into account the
The architect should document all changes in
architect’s logical and sometimes intuitive
construction documentation requested by the
design process.
owner. The architect should provide written
comments and recommendations on all changes,
Value engineering is a systematic procedure
and clearly describe the positive and negative
to determine the best or optimum value for
aspects of the substitutions.
investments in a construction project. Value
engineering is an analytical approach to modifying
features which may add cost to a building but do Embodied Energy Cost Analysis
not contribute to its quality, appearance, useful or Embodied Energy Consumption
life or functional performance. Architects usually
work with cost consultants and value engineers This type of cost analysis assesses the
to compare trade-offs between design concepts, environmental impacts and energy consumption
arrangements, materials and finishes, systems, resulting from the extraction, manufacture,
construction techniques as well as capital and delivery, installation, demolition, and recycling
life cycle costs. This analysis should begin during of building materials in buildings.
the schematic design phase when conceptual
drawings and outline specifications are prepared. Increasing emphasis is being placed on the need
Ideally, value engineering is planned and to conserve natural and manufactured building
scheduled at the outset of a project; however, materials and to reduce the embodied energy
the architect should be willing to undertake contained within all products used in building
such a study at any stage of the project. As construction.
noted above, the best time for value engineering
is early in the design process. Work in this field is frequently undertaken by
specialists. Architects are well equipped to
Certain project delivery methods are better suited develop knowledge and skills in this area of
to value engineering and different owners will expertise, rather than relinquishing the field
apply different criteria for such studies. For to others.
example, developers or Design-Builders may plan
to dispose of an asset soon after construction,
with more interest in reducing capital spending
and less interest in life cycle costs. Landlords and
building owners may be more concerned about
reduced operating and maintenance costs as well
as lower replacement costs. Lower capital costs are
almost always a significant consideration. The
objective should be to minimize construction cost
while maintaining quality through the substitution
of alternative materials and systems.

Canadian Handbook of Practice for Architects January 2009 17


Volume 2 Chapter 2.3.3 Cost Planning and Control

Definitions
Construction Budget: The client’s budget for the construction cost, including contingencies for cost
increases.

Element: Term used in cost estimating to describe a component of a building, such as sub-structure
(footings, foundations) or envelope (walls and roof).

Estimate: To form and state a general idea of; an opinion or judgement (as to such factors as value,
time, size).

Indexing: Applying an index or factor to adjust costs for one geographic region to another. (A typical
index might be expressed as a percentage such as 102.7%.)

Project Budget: The client’s estimated total expenditure for the entire project. It includes, but is not
limited to, the construction budget, professional fees, costs of land, rights of way, and all other costs
to the client for the project.

Quantity Survey: A bill of quantities or a detailed listing and quantities of all items of material and
equipment necessary to construct a project.

References
American Society for Testing Materials (ASTM). publishes 24 various standards on from the Committee
E06.81 on Building Economics.
www.astm.org/COMMIT/SUBCOMMIT/E0681.htm

Canadian Institute of Quantity Surveyors.


Quantity Surveying and Cost Consulting Services: Schedule of Services and Recommended Charges.
Elemental Cost Analysis, Format, Method of Measurement, Pricing, 3rd Edition, 2000.
Method of Measurement of Construction Works, 7th Edition, 2000.

Dell’Isola, Alphonse. Value Engineering: Practical Applications… for Design, Construction,


Maintenance & Operations. Kingston, MA: R.S. Means Co., Inc., 1998.

Derman, Asher, Ph.D. “Embodied Energy, Air Pollution, and Materials, Part 1.” AIA Environmental Guide.
Washington, D.C.: The American Institute of Architects Press, January 1993.

Foster, Norman et al. Construction Estimates From Take-Off to Bid. Third Edition. New York, NY: Hill, 1961.

Kirk, Stephen J. and Alphonse Dell’Isola. Life Cycle Costing for Design Professionals. Second Edition.
New York, NY: McGraw-Hill, 1995.

REED Construction Data publishes a range statistics and economic information on the construction
industry, as well as cost estimating tools and books.
www.canadata.com
www.rsmeans.com

Toronto Real Estate Board. Schedule of Unit Costs. Published annually. Toronto, Ont.

18 January 2009 Canadian Handbook of Practice for Architects


Cost Planning and Control Chapter 2.3.3 Volume 2

Appendix — Description of the Classes of Estimates used by PWGSC


for Construction Costing of Building Projects
Class “D” Estimate
This estimate provides an indication of the total cost of the project, based on the user’s functional
requirements to the degree known at the time. It is based on historic cost data for similar work, suitably
adjusted for such factors as: effect of inflation, location, risk, quality, size, and time. All related factors
affecting cost are considered to the extent possible. Such an estimate is strictly an indication (rough
order of magnitude) of the project total cost and completion date. This estimate
is used to establish the indicative estimate required by Treasury Board for Preliminary Project Approval.
Expected degree of accuracy: 20%.

Class “C” Estimate


This estimate is prepared at the end of the Design Concept stage and is based on updated user
requirements, general description of the end built works, preliminary site information and existing
conditions, and production. It takes into consideration construction experience and market conditions
as well as basic implementation logistics. The estimate includes costs for design, documentation,
and construction supervision. Expected degree of accuracy: 15%.

Class “B” Estimate


This estimate is prepared at the end of the Preliminary Design stage and is based upon data (on cost,
time, and construction) of a level of precision as is typically available when the design of the major
systems and sub-systems of the facility (including outline specifications and preliminary drawings and
models), as well as when the results of all site or installation investigations are completed. This
estimate also makes allowance for all costs resulting from the anticipated schedule, expected market
conditions, and suitable level of contingencies. This estimate is used to establish the substantive
estimate required by Treasury Board for Effective Project Approval. Expected degree of accuracy: 10%.

Class “A” Estimate


This estimate is based on the B estimate which has been updated concurrently with the development of
Construction Documents and is submitted as a final pre-tender estimate. It requires that project systems
be designed and specified to near completion, and is based on a realistic construction schedule as well
as accurate labour and material costs. This is the final estimate before tender call or construction start.
Typically, the total forecast is presented in elemental format and includes all actual associated fees and
costs. Expected degree of accuracy: 5%.

(Source: Public Works and Government Services Canada)

Canadian Handbook of Practice for Architects January 2009 19

You might also like