You are on page 1of 5

QUANTISURV PRELIM REVIEWER

INTRODUCTION TO QUANTITY SURVEYING ▪ Is done before plans, specifications and


other project details have been developed
QUANTITY SURVEYING ▪ +15 -20% accurate
• Calculating the amount of materials and other incidents necessary
for the realization of work ESTIMATES FOR FEASIBILITY
• Term or process used in the construction industry to take • Using preliminary design information and after project scope is
measurements of civil works, prepare specifications and estimate completely defined.
the cost of works either for each trade of work or for the whole • An estimate of project cost that is prepared before complete
project construction documents are available
• Is the application of standard methods of measurements to quantify • +15-20% accurate
the amount of various items in a construction project, for the
undertaking of valuation and certifying payments ESTIMATES FOR FEASIBILITY
• Based on schematic level design documents, it is probable that
major quantities can be quantified, concrete, steel based from type
SURVEYING
of construction
• Means to inspect, study, review, investigate, asses and hence to • The designer and owner may use the estimate to evaluate
measure expected total project cost but for the purpose of reviewing design
cost drivers and performing value engineering
TASK COVERED IN QUANTITY SURVEYING o VALUE ENGINEERING
1. Preparation of SPECIFICATIONS ▪ A evaluation of a project objective function
2. Taking MEASUREMENTS of civil works for the purpose of bettering the objectives in
3. Preparation of APPROXIMATE (PPRELIMINARY) COST terms of cost and functional parameters
ESTIMATE at the very early stage of the project
ESTIMATES FOR CONSTRUCTION
4. Preparation of DETAIL COST ESTIMATE at different stages
5. VALUATION of property • Itemized cost computation based on complete set of contract
documents
PURPOSE OF QUANTITY SURVEYING • Bid estimate submitted to the owner either for competitive bidding
Preparation of bill of quantities: or negotiation consist of direct construction cost including field
1. Assist the client TO HAVE ACCURATE ESTIMATE of the volume supervision, plus a mark-up to cover general overhead and profits.
of work as well as the REQUIRED BUDGET o Subcontractor quotations
2. To assist in the ACCURATE PREPARATION OF TENDERS, by o Quantity takeoffs
providing uniform measurement of quantities o Construction procedure
3. To GIVE AN ACCURATE CHECKLIST of work accomplished • 5% accuracy
4. To give insight into required VARIATION WORK AMOUNTS
CONTROL ESTIMATES
ESTIMATE • For monitoring the project during construction, a control estimate is
• is the most important of the practical aspects of construction derived from available information to establish:
management and the subject deserve a closest attention of one o Budget estimate for financing
aspiring to a career in the profession o Budgeted cost after contracting but prior to construction
PURPOSE OF ESTIMATING o Estimated cost to completion during progress of
construction
• to give a reasonably accurate idea of the cost
• is necessary to give the owner a reasonably accurate idea of the ESTIMATES FOR CHANGE ORDER
cost to help him decide whether the work can be undertaken as • Performed on the project site in response to an owner - directed
proposed or needs to be curtailed or abandoned, depending upon change in the project
the availability of funds and prospective direct and indirect benefits.
o Estimating Materials ESTIMATING TECHNIQUES
o Estimating Labor
o Estimating Equipment APPROXIMATE ESTIMATE
o Estimating Time • Is the approximate or rough estimate prepared to obtain an
TYPES OF CONSTRUCTION ESTIMATES approximate cost in a short time. For certain purposes the use of
such methods is justified
ESTIMATES FOR CONCEPTUAL PLANNING
• Based on very general parameters of facility size, anticipated DETAILED ESTIMATE
quality of construction and use of facility • A detailed estimate of the cost of a project is prepared by
o CONCEPTUAL ESTIMATE determining the quantities and costs of everything that a contractor
▪ Is prepared based from only the conceptual is required to provide and do for satisfactory completion of the work.
description of the project It is the best and most reliable form of estimate.

GMTD
QUANTISURV PRELIM REVIEWER
DATA REQUIRED FOR PREPARING AN ESTIMATE PLANNING THE WORK
1. Plans, section, and other relevant details of the work • Thoroughly understand the scope of work and the project
2. Specifications, indicating the exact nature and class of material to environment
be used • A detailed review enables the estimator to formulate a construction
3. Rate, at which the different items oof work are carried out sequence and duration
• A site visit is strongly recommended to enable the estimator to
STEPS IN PREPARING ESTIMATE
relate the physical site characteristics to the available design
TAKING OUT QUANTITIES parameters and details.

• Measurements are taken off from the drawings and entered on QUANTITIES
measurement sheets or dimension paper. Depend upon the unit of • Quantity Take-off
measurement o Must be as accurate as possible and should be based
on all available engineering and design data
SQUARING OUT • Quantities should be shown in standard units of measure and
• Working out volumes, areas, and casting up their total recognized should be consistent with the design units
units
TYPES OF COST
ABSTRACTING • Direct Cost
• In the third step all items along with net results obtained in the o All cost elements that can be associated with a specific
second step are transferred from measurement sheets to item of project work e.g cost of labor, cost of materials,
specifically ruled sheets having rate column ready for pricing cost of equipment
• Indirect Cost
WORK BREAKDOWN STRUCTURE (WBS) o Cost that cannot be attributed to a single task or
construction work e.g, overhead, profit, bonds
• Provide a common hierarchical framework for summarizing o Profit
information and for the quantitative reporting to customers ▪ Amount of money, if any that a contractor
(client/owner) and management retains after completing a [project and paying
• Purpose of WBS: all const of materials, labor and overhead
o Provide an organized manner of collecting project cost
data in a standard format for estimating, cost reporting PRODUCTIVITY AND PRICE RESOURCES
and cost tracking • Historical production and cost data from similar past work are
o Provide checklist for categorizing cost excellent resources of when adequate details have been saved and
o Provide a means to maintain historical cost data in a adjustments to project specifics can be defined.
standard format
PRODUCTIVITY AND PRICE RESOURCES
BASICS FOR PREPARATION OF ESTIMATES
• Development task descriptions must describe the scope and
REVIEW CONTRACT DOCUMENTS material requirement

• Thoroughly examine the constructions documents UNIT COST


o Drawings and Specifications • Labor Unit Cost
o General Conditions o Cost based on defined crew that performs the task at an
▪ Part of the contract documents that defines assigned production rate
the rights, responsibilities and relationships • Equipment Unit Cost
of all parties to the construction contract. • Material Unit Cost
• It is appropriate to make notes of anything that can affect o Developed using various quotes, historical cost,
construction duration and the cost to perform the work or add commercial pricing sources and component
indirect and overhead cost to the work. calculations.
o Prebid Conference
▪ A meeting held prior to bid opening for the COST AND PRICING
purpose of explaining the project and • Cost for each task is developed by summing up the direct cost
answering questions that bidders have with elements for labor, equipment, materials, supplies, and
respect to the contract documents and the subcontractor
work • Indirect cost and other markups associated with each task or work
item should be identified and considered properly

GMTD
QUANTISURV PRELIM REVIEWER
SUPPORTING DOCUMENTS GUARANTEE BOND

• Should always remain mindful of the documents necessary to • Is approved form of security furnished by the contractor and his
support the estimates surety as guarantee of the quality of materials provided, equipment
• Narratives of Contract cost – contains discussion, considerations installed, and workmanship performed by contractor
and the developed construction plans
o Project Narrative INSTRUCTION TO BIDDERS
o Construction Schedule • Refers to the list of instructions regarding the manner bids are to
o Equipment and Material Utilization be prepared and the conditions for the award of contracts
o Labor Discussion and Utilization
• Estimate backup data – back up documents PAYMENT BOND
• Quotations • Is approved form of security furnished by the contractor and his
• Drawing and sketches surety as guarantee of good faith on the part of the contractor to
faithfully comply with the contract in respect of his obligations
arising therefrom to its workers, subcontactors, and suppliers
PART 1: DEFINITION OF KEY TERMS
PERFORMANCE BOND
ADVERTISMENT OR INVITATION TO BID
• Is approved form of security furnished by the contractor and his
• Refers to the notice published by the owner or the invitation issued surety as guarantee of good faith on the part of the contractor to
to prospective bidders, giving information as to the nature of the execute the work in the accordance with the contract
project
SCHEDULE OF MATERIALS AND FINISHES
BID • Is an outline specification enumerating the type of trade names of
• Is the tender, or proposal, or quotation, or offer of a bidder to materials required to be used by the contractor for the work
perform the work described in the contract
SPECIFICATIONS
BID DOCUMENTS • Are written or printed description of the work to be done describing
• Collectively refers to all documents provided or made available to qualities of the material to be used, the equipment to be installed
prospective bidders and the mode of construction

BID BONDS SPECIAL PROVISIONS OR CONDITIONS


• Refers to any acceptable form of bond accompanying the Bid • Are instructions which are issued prior to the bidding to supplement
submitted by the bidder as guarantee that the bidder will enter into and/or modify the drawings, specification, and/or general
the contract with the owner conditions of the contract

BID BULLETIN SUPPLEMENTARY SPECIFICATIONS


• Is a document containing additional information on the bid • Refers to additional information which may be issued as an
documents issued by the bidders before date of bidding additional to or amendment of the provisions of the specifications

CONTRACT
PART 2: INTERPRETATION OF BID DOCUMENTS
• Is the term used to describe the agreement and the contract
document RULE 1
The Agreement and the Contract Documents shall be taken as mutually
CONTRACT DOCUMENTS explanatory of one another. The various provisions of the Contract shall be
• Are documents attached to the agreement identified therein as interpreted together, attributing to the doubtful ones that sense which may
contract documents, including all additions, deletions and result from all of them taken jointly.
modifications incorporated therein.
RULE 2
a. Special Provision or Conditions
b. General Conditions The provisions of the Civil Code of the Philippines on the interpretation of
c. Specifications contracts and of the Rules of Court on the Interpretation of Documents shall
d. Drawings be applied.
e. Other bid documents
RULE 3
DRAWINGS Where the conflict between or among the provisions of the Agreement and/or
• Are the graphical representation of the work. They include all the
supplementary details and shop drawings Contract Documents cannot be resolved by Rules 1 and 2, it shall be
understood that:
(a) the Detailed Drawings shall prevail over the General Drawings;

GMTD
QUANTISURV PRELIM REVIEWER
(b) words and figures shall prevail over the Drawings; reference books that list typical unit prices Spreadsheets of unit prices for
(c) words shall prevail over figures in Contract Documents; various types of work on different structures may be maintained by a
(d) written dimensions shall prevail over measured dimensions. contractor.

RULE 4 STEP 5: HIDDEN COST


Where the conflict cannot be resolved by applying Rule 3 or where Rule 3 does Carefully examine the general conditions of the contract and visit the site, to
not apply, the conflict shall be resolved by giving precedence to the Agreement have a full knowledge of all the possible hidden costs, such as special
or to provisions of a Contract Document higher in order of priority among the insurance requirements, portions of site not yet available, and complicated
various documents which comprise the Contract. The order of priority among logistics.
these documents shall be as follows:
a) Agreement as modified by Notice of Award of Contract, if such be FINAL STEP: RECEIVE PRICES
the case, and the Contractor’s conformity thereto: Review the estimate and carefully note exclusions and exceptions in each
b) Instruction to Bidders and any amendment thereto: subcontract bid and in material quotations.
c) Addenda to Bid Documents; BASIC CONCEPTS OF QUANTITY SURVEY
d) Specifications;
e) Drawings; QUANTITY SURVEY
f) Special Conditions of Contract; • Is a schedule of quantities of all the items of work in a building
g) General Conditions of Contract; • Describe quantity survey as follows:
h) Other Contract Documents; and o Description and preparation of the bill of quantities and
i) Other documents forming part of the Contract attached thereto or its items required for the tender
incorporated therein by reference. o Preparation of the site material, material types and
distribution
RULE 5
DATA REQUIRED
Where there is discrepancy, defective description, error or omission in any
Contract Document, the Contract Documents shall be interpreted as being DRAWINGS
complementary to each other. Thus, what is called for in one Contract • Complete and fully dimensioned drawings of the building or work in
Document, although not mentioned in another Contract Document where it question are required
should have been mentioned, shall be deemed to be called for by the Contract.
SPECIFICATIONS
RULE 6
• Detailed specifications, giving the nature, quality and class of work,
The apparent silence of the Drawings, Specifications or any other Contract materials to be used, quality of the material, their proportions and
Document as to any detail, or the lack of detailed description concerning any method of preparation are required
part of the work, shall be understood to mean that good and accepted
construction practice in accordance with the usage or custom of the place shall RATES
be followed. • Rates of various of work, materials to be used in the construction,
RULE 7 wages of different categories of labor

Rules 1 to 6 shall yield to specific rules of interpretation in this document or in TYPES OF ESTIMATES AND QUANTITY SURVEY
the Contract. (enumeration)
True of false 1. Preliminary or Approximate Estimate
2. Detailed Estimates
3. Quantity Estimates
PART 3: STEPS IN REVIEWING BID DOCUMENTS 4. Revised Estimates
5. Maintenance Estimates
STEP 1: BID DOCUMENTS
The documents should be examined for completeness of plans and
DATA REQUIRED FOR THE PREPARATION OF AN ESTIMATE
specifications, and for the probable accuracy that an estimate will yield from
the information being furnished. 1. Drawings
2. Specifications
STEP 2: PREPARATION OF TOP SHEET 3. Rates
This is usually based on an examination of the specifications table of contents.
TYPES OF CONSTRUCTION ESTIMATES
STEP 3: SUBCONTRACTOR PRICES
1. Estimates for Conceptual Planning
Decide on which trades sub bids will be obtained, and solicit prices from 2. Estimates for Feasibility
subcontractors and suppliers in those trades. 3. Estimates During Engineering and Design
STEP 4: PRICING 4. Estimates for Construction
5. Control Estimates
Use either unit prices arrived at from the contractor’s own past records, 6. Estimates for Change Order
estimates made by the members of the contractor’s organization, or various

GMTD
QUANTISURV PRELIM REVIEWER
WORKS IN CONSTRUCTION
1. Concrete
2. Masonry
3. Metal Reinforcements
4. Lumber

PRE CONSTRUCTION PHASE


1. General Requirements
a. Permits
b. Design plans
c. Lot survey
d. Clearing and Grabbing
e. Temfacil
f. Mobilization

CONSTRUCTION PHASE
2. Earth Works
a. Excavation
i. Footing
ii. Backfilling
3. Structural Works
a. Construction footing
b. First level column
c. Ground floor column
d. Beams
e. Slabs
f. Roof beams
g. Framework and Scaffolds
4. Masonry Works
5. Plastering Works
6. Architectural Works
a. Ceiling works
b. Tiling Works
c. Painting Works
d. Doors & Windows
e. Cabinet Works
7. Metal Works
8. Plumbing Works
9. Electrical Works

POST CONSTRUCTION PHASE


Hulaan niyo nalang diko na sulat sa notes e :P

GMTD

You might also like