Professional Documents
Culture Documents
AND COSTING
UNIT 1
INTRODUCTION TO ESTIMATION
Construction
Project FEASIBILITY DESIGN
PLANNING
DEVELOPMENT CLOSEOUT OPERATIONS
Management
Phase Fin.&Eval. Organization
Risk
Estimating
Planning
Conceptual Detailed
Feasibility Pre-bid Construction
Design & design design
Estimating
Process
Conceptual & Preliminary Definitive
Detailed Estimates
Estimates Estimates
WHAT IS
Estimation is the scientific way of working out the
ESTIMATION ? approximate cost of an engineering project before
execution of the work.
Itis used for framing the tenders for the works and to check
contractor’s work during and after the its execution for the
purpose of making payments to the contractor.
AFFECTING THE
OVERALL COST
6. The source of availability of a sufficient supply of materials of
good quality is also a factor.
AFFECTING THE
OVERALL COST 8. Access to the site must be reasonable. If the access is poor,
temporary roads may be constructed.
GOOD
ESTIMATOR
ESSENTIAL
QUALITIES • He must thoroughly understand the drawings of the
structure, for which he is going to prepare an estimate.
OF A GOOD
ESTIMATOR • He must also be clearly informed about the
specifications showing nature and classes of works and
the materials to be used because the rates at which
various types of works can be executed depend upon its
specifications.
A good estimator of construction costs should possess the
following capabilities, also:-
OF A GOOD 4 = Good judgment with regard to different localities, different jobs and
different workmen.
ESTIMATOR 5 = Selection of a good method for preparing an estimate.
DRAWINGS
A. General Specifications: This gives the nature,
quality, class and work and materials in
general terms to be used in various parts of
work. It helps to form a general idea of
building.
SPECIFICATIONS
B. Detailed Specifications: These gives the
detailed description of the various items of
work laying down the Quantities and qualities
of materials, their proportions, the method of
preparation workmanship and execution of
work.
RATES For preparing the estimate the unit rates of each
item of work are required.
1. For arriving at the unit rates of each item.
2. The rates of various materials to be used in
the construction.
3. The cost of transport materials.
4. The wages of labor, skilled or unskilled of
masons, carpenters, Mazdoor, etc..,
COMPLETE
ESTIMATE:
Most of people think that the
estimate of a structure includes cost
of land, cost of materials and labor,
But many other direct and indirect
costs included and is shown.
While preparing an estimate, it is not possible to workout in
detail in case of petty items. Items other than civil engineering
LUMPSUM such items are called lump sum items or simply L.S.Items.
The following are some of L.S. Items in the estimate.
1. Water supply .(4 to 5%) and sanitary arrangements.(4 to 5%)
2. Electrical installations like meter, motor, etc..,(9%of the
estimated cost of building works and electric Fans, Lights= 3% of
the estimated cost of building works
3. Architectural features.
4. Contingencies and unforeseen items.
In general, certain percentage on the cost of estimation is
allotted for the above L.S.Items
Even if sub estimates prepared or at the end of execution of
work, the actual cost should not exceed the L.S.amounts
provided in the main estimate.
WORK During the construction of a project
CHARGED considerable number of skilled supervisors,
ESTABLISHME work assistance, watch men etc.., are employed
on temporary basis.
NT
The salaries of these persons are drawn from
the L.S. amount allotted towards the work
charged establishment. that is, establishment
which is charged directly to work. an
L.S.amount of 1½ to 2% of the estimated cost is
provided towards the work charged
establishment.
Short Answer Questions
1. State the requirements of an estimate?
2. Briefly Explain need for estimation?
3. What is work charged establishment?
EXERCISE
UNITS OF
MEASUREMENTS