ement No. 5 Agreement /Work Order No. & Date 88/15/0078/RCD 08/01/16
Measurement Type REGULAR Date of Commencement 01/12/19
Name of the MACAWBER BEEKAY PVT. LTD.
Contractor Due/completion Date 31/01/20 Date of Measurement 15/04/20
Cumulative Total Value Deduct Previous Since last
Main Id Measurements up-to-date % Rate up-to-date measurements measurement
Description of Work Wieghtage
Rs. P. Per Rs. P. Page Qnty. Qnty. Value
No. L B D Contents Rs. P.
3--1.01 Belt laying 1770 1770 Progress 1430.000 Mtr 2024880.00 0 1770 2024880.00
Payment1
5-- Troughing Carrying Idler 3000 3000 Progress 280.000 NOs. 672000.00 2220 780 174720.00
1.02.01 Rollers (35°), 1400mm BW Payment1
6-- Transition Idler Rollers (15° & 12 12 Progress 280.000 NOs. 2688.00 0 12 2688.00
1.02.02 25°), 1400mm BW Payment1
7-- Troughing Impact Idler Rollers 210 210 Progress 280.000 NOs. 47040.00 180 30 6720.00
1.02.03 (35°), 1400mm BW Payment1
8-- Self Aligning Troughing 264 264 Progress 280.000 NOs. 59136.00 174 90 20160.00
1.02.04 Carrying Idler Rollers (35°), Payment1
1400mm BW
9-- Flat Return Idler Roller, 1400 298 298 Progress 280.000 NOs. 66752.00 296 2 448.00
1.02.05 mm BW Payment1
10-- 2 Roll V-type Return Idler 200 200 Progress 280.000 NOs. 44800.00 0 200 44800.00
1.02.06 Rollers, 1400mm BW Payment1
21-- Troughing Carrying Idler Frame 1000 1000 Progress 410.000 NOs. 328000.00 740 260 85280.00
1.03.01 (35°), 1400mm BW Payment1
22-- Transition Idler Frame (15° & 4 4 Progress 410.000 NOs. 1312.00 0 4 1312.00
1.03.02 25°), 1400mm BW Payment1
23-- Troughing Impact Idler Frame 70 70 Progress 410.000 NOs. 22960.00 60 10 3280.00
1.03.03 (35°), 1400mm BW Payment1
26-- 2 Roll V-type Return Idler 100 100 Progress 410.000 NOs. 32800.00 0 100 32800.00
1.03.06 Frame, 1400mm BW Payment1
Page No. 1 of 5
Name of the Work (4X270MW) BHADRADRI T.P.S. Measurement No. 5 Agreement /Work Order No. & Date 88/15/0078/RCD 08/01/16
Measurement Type REGULAR Date of Commencement 01/12/19
Name of the MACAWBER BEEKAY PVT. LTD.
Contractor Due/completion Date 31/01/20 Date of Measurement 15/04/20
Cumulative Total Value Deduct Previous Since last
Main Id Measurements up-to-date % Rate up-to-date measurements measurement
Description of Work Wieghtage
Rs. P. Per Rs. P. Page Qnty. Qnty. Value
No. L B D Contents Rs. P.
34-- Drive Base Frame 4 4 Progress 12000.000 NOs. 38400.00 3 1 9600.00
1.04 Payment1
40--1.1 Stringer & short Post (including 74.813 74.813 Progress 30000.000 MTON 1795512.00 60.014 14.799 355176.00
Rail supporting structure for Payment1
Tripper and Paddle Feeder)
41-- Deck Plate 1177 1177 Progress 1100.000 Mtr 1035760.00 877 300 264000.00
1.11 Payment1
43-- Drive Pulley for Belt Conveyor 4 4 Progress 105000.000 NOs. 336000.00 3 1 84000.00
1.13 Payment1
44-- Tail & Take-up for Belt 6 6 Progress 75000.000 NOs. 360000.00 4 2 120000.00
1.14 Conveyor Payment1
45-- Bend Pulley for Belt Conveyor 8 8 Progress 75000.000 NOs. 480000.00 6 2 120000.00
1.15 Payment1
46-- Snub Pulley for Belt Conveyor 4 4 Progress 75000.000 NOs. 240000.00 3 1 60000.00
1.16 Payment1
52-- Plummer Block for Pulleys & 52 52 Progress 2700.000 NOs. 112320.00 0 52 112320.00
1.22 Tripper Wheel Payment1
53-- Bearing for Pulleys & Tripper 52 52 Progress 3000.000 NOs. 124800.00 0 52 124800.00
1.23 Wheel Payment1
Page No. 2 of 5
Name of the Work (4X270MW) BHADRADRI T.P.S. Measurement No. 5 Agreement /Work Order No. & Date 88/15/0078/RCD 08/01/16
Measurement Type REGULAR Date of Commencement 01/12/19
Name of the MACAWBER BEEKAY PVT. LTD.
Contractor Due/completion Date 31/01/20 Date of Measurement 15/04/20
Cumulative Total Value Deduct Previous Since last
Main Id Measurements up-to-date % Rate up-to-date measurements measurement
Description of Work Wieghtage
Rs. P. Per Rs. P. Page Qnty. Qnty. Value
No. L B D Contents Rs. P.
63-- Rail Clamp for Tripper 2 2 Progress 5000.000 NOs. 8000.00 0 2 8000.00
1.33 (Thruster Operated) Payment1
88-- Rail for Travelling Tripper 25.633 25.633 Progress 6500.000 MTON 133291.60 9.43 16.203 84255.60
1.58 Payment1
93-- Gear Box for HT Drive 4 4 Progress 140000.000 NOs. 448000.00 2 2 224000.00
1.63 Payment1
96-- Scoop type Fluid Coupling for 4 4 Progress 130000.000 NOs. 416000.00 0 4 416000.00
1.66 Conveyors (along with oil Payment1
cooler and pump assembly)
99-- Travelling Tripper 1 1 Progress 215000.000 NOs. 172000.00 0 1 172000.00
1.69 Payment1
100-- CRD for Travelling Tripper 1 1 Progress 24900.000 NOs. 19920.00 0 1 19920.00
1.7 Payment1
101-- Geared Motor for Travelling 2 2 Progress 30000.000 NOs. 48000.00 0 2 48000.00
1.71 Tripper Payment1
164-- Local Panel for Tripper 1 1 Progress 50000.000 NOs. 40000.00 0 1 40000.00
2.29 Payment1
165-- Power Cum Control JB for 1 1 Progress 3000.000 NOs. 2400.00 0 1 2400.00
2.3 Tripper Payment1
Page No. 3 of 5
Name of the Work (4X270MW) BHADRADRI T.P.S. Measurement No. 5 Agreement /Work Order No. & Date 88/15/0078/RCD 08/01/16
Measurement Type REGULAR Date of Commencement 01/12/19
Name of the MACAWBER BEEKAY PVT. LTD.
Contractor Due/completion Date 31/01/20 Date of Measurement 15/04/20
Cumulative Total Value Deduct Previous Since last
Main Id Measurements up-to-date % Rate up-to-date measurements measurement
Description of Work Wieghtage
Rs. P. Per Rs. P. Page Qnty. Qnty. Value
No. L B D Contents Rs. P.
170-- Belt Watch Panel 2 2 Progress 50000.000 NOs. 80000.00 1 1 40000.00
2.35 Payment1
176-- Local Panel for Scoop Coupling 7 7 Progress 5000.000 NOs. 28000.00 4 3 12000.00
2.41 Payment1
180-- Local Push Button Station 15 15 Progress 2500.000 NOs. 30000.00 12 3 6000.00
2.45 Payment1
182-- Pull Cord Rope 1655 1655 Progress 10.000 Mtr 13240.00 0 1655 13240.00
2.47 Payment1
183-- Eye Hook 1100 1100 Progress 10.000 NOs. 8800.00 800 300 2400.00
2.48 Payment1
184-- Trailing Cable for Tripper 215 215 Progress 250.000 Mtr 43000.00 0 215 43000.00
2.49 Payment1
Page No. 4 of 5
Name of the Work (4X270MW) BHADRADRI T.P.S. Measurement No. 5 Agreement /Work Order No. & Date 88/15/0078/RCD 08/01/16
Measurement Type REGULAR Date of Commencement 01/12/19
Name of the MACAWBER BEEKAY PVT. LTD.
Contractor Due/completion Date 31/01/20 Date of Measurement 15/04/20
Cumulative Total Value Deduct Previous Since last
Main Id Measurements up-to-date % Rate up-to-date measurements measurement
Description of Work Wieghtage
Rs. P. Per Rs. P. Page Qnty. Qnty. Value
No. L B D Contents Rs. P.
197-- ILMS- Rectified Panel 4 4 Progress 50000.000 NOs. 160000.00 2 2 80000.00
2.62 Payment1
Page No. 5 of 5