Integrated Waste Management System

Type Name Method of


S.No Sources Resources required for implementaion
disposal
Bio – Bio :- Spilled Land filling at 1) Arragement of 210 Nos. Waste Bin (Green – Bio, Red – Non-Bio &
degradable food item from the earmarked Yellow – For Glass) to put in front of each block in township.
colony houses, site near STP in
guest house and colony for 2) Arragement for Garbage Pick up Van with different coloured master
canteen, Papers, further waste bin.
Wood, Etc. utilization as 3) Bio Degradable wastes shall be shifted to Dump Pit(DP-1) near STP
& manure in for manure prepartion by using the earth worms culture.
horticulture.
4) Non-Bio Degradable Wastes shall be shifted to Dump Pit (DP -2)
near Mines for further dispose off into kiln as a fuel.
Non- Bio Non- Bio:- Land filling at
degradable Plastic items, the earmarked 5) The Glass wastes shall be shifted to Dump Pit (DP – 3) near Mines
glass items etc. site near Mines for sold out to recylcler(Kabadi Wala)
Lease Area & 6) Have to make a Covered Shed & with covering by nets - Waste
Shall be burn Dump Pit of size 10 m lenght x 10 m width x 2m depth with having 04
into cement kiln. compartments near STP for DP – 1
Residential
waste 7) Have to make a Waste Dump Pit of size 20 m lenght x 20 m width x
2m depth near Mines for DP – 2 with Chain Link Fencing and Locking
arragement.
8) Have to make a Waste Dump Pit of size 10 m lenght x 05 m width x
2m depth near Mines for DP – 3 with Chain Link Fencing and Locking
arragement.
9) Feeding arragement at Cement Kiln for Non-Biodegradable Waste
as fuel
10) The Pick up Van shall run in township on daily basis to lift the
colleted wastes from the dust bins to dispose off to the designated
places.

Sewage Domestic Sewage Already provided


effluent Treatment Plant

2 Commerci Non - Cotton waste Land filling at 1) Total 37 Locations identified in plant to kept two colured (Green – Bio
Biodegrada containing oil, the earmarked & Red – Non-Bio) dust bins.
ble grease residue & site near Mines
Plastic items, Lease Area & 2) Glass waste generated from Laboratory shall be disposed off inot the
Shall be burn DP – 2. For this Two Nos. Yellow Dust Bin have to provided in
into cement kiln. laboratory (One at TPP & One at CCR).

3) The rest as above.


Iron/Steel Store yard 1) Area have to be earmarked for Steel Scraps at identified 37 locations
Scrape, Metal inside plant.

2) The collected metal scrap on weekly basis shall be shifted to


designated location at store yard for further sell out/re-use the same.
al Waste
Biodegrada Stationary items Land filling at 1) Total 37 Locations identified in plant to kept two colured (Green – Bio
(Plant side)
ble & Canteen the earmarked & Red – Non-Bio) dust bins.
Wastes site near STP in
colony for 2) The rest as above.
further
utilization as
manure in
horticulture.
Sewage Plant Domestic Sewage 1) Presently this sewage is being dispossed off in sock pits via septic
effluent Treatment Plant tank.

2) Entire office building of plant shall be connected by laying sewage


line to STP at Colony.
3 Dispensary Bio-Medical Medical Collection in the 1) Category wise record of Biomedical waste & its disposal shall be
Waste laboratory colour coded maintained at dispensary.
wastes (Sharps containers
wastes, needles, (Yellow, Red, 2) Authorization shall be taken if treating more than 1000 patients per
syringes, Blue/white, month, otherwise no need for authorization.
scalpels, glass, Black) and shall
etc. & discarded be disposed off 3) Putting different coloured waste bin inside the Dispensary.
medicines) as under:
1) Needle 4) Tie up with Near By Govt. Hospital, Bio-meidacl waist management
destroyer cell.
2) Shredding
machines for
plastic syringe
and plastic
items.
3) Deep burial of
the sharp waste
and discarded
medicines by
applying lime
layering on it.

After
accumilating the
same in huge
quantity, the
same shall be
send to Govt.
Hospital for final
disposal.