You are on page 1of 30

Guideline Technology

Title: Hazard and Operability Unique Identifier: 240-49230111


Analysis Guideline

Alternative Reference Number: N/A

Area of Applicability: Engineering

Documentation Type: Guideline

Revision: 1

Total Pages: 30

Next Review Date: April 2015

Disclosure Classification: CONTROLLED


DISCLOSURE

Compiled by Functional Responsibility Authorised by

………………………………….. ………………………………….. …………………………………..

E Pininski L Fernandez D Odendaal


Chief Engineer: Systems Senior Manager: Systems General Manager: Plant
Design (Reliability Integration (B2B Engineering Engineering (B2B
Engineering) (B2B Perform Processes/System Lead Engineering Tools
Design Analysis Process Programme Lead)
Owner)

Date: …………………………… Date: …………………………… Date: ……………………………

Governance

…………………………………..

D Odendaal
TDAC Chairperson

Date: ……………………………
Unique Identifier: 240-49230111
Hazard and Operability Analysis Guideline
Revision: 1
Page: 2 of 30

CONTENTS
Page
1. INTRODUCTION...................................................................................................................................................... 4
2. SUPPORTING CLAUSES ....................................................................................................................................... 4
2.1 SCOPE.............................................................................................................................................................. 4
2.1.1 Purpose ..................................................................................................................................................... 4
2.1.2 Applicability ............................................................................................................................................... 4
2.2 NORMATIVE/INFORMATIVE REFERENCES ................................................................................................. 4
2.2.1 Normative .................................................................................................................................................. 4
2.2.2 Informative ................................................................................................................................................ 5
2.3 DEFINITIONS ................................................................................................................................................... 5
2.3.1 Disclosure Classification ........................................................................................................................... 6
2.4 ABBREVIATIONS ............................................................................................................................................. 6
2.5 ROLES AND RESPONSIBILITIES ................................................................................................................... 6
2.6 PROCESS FOR MONITORING ....................................................................................................................... 6
2.7 RELATED/SUPPORTING DOCUMENTS ........................................................................................................ 6
3. HAZOP OVERVIEW ................................................................................................................................................ 7
3.1 HAZOP OBJECTIVES ...................................................................................................................................... 7
3.2 HAZOP PRINCIPLES ....................................................................................................................................... 8
3.2.1 Examination .............................................................................................................................................. 8
3.2.2 Design representation ............................................................................................................................. 11
3.2.3 Design requirements and design intent .................................................................................................. 11
3.3 HAZOP PROCESS ......................................................................................................................................... 12
3.3.1 Definition ................................................................................................................................................. 13
3.3.2 Preparation ............................................................................................................................................. 14
3.3.3 Execution ................................................................................................................................................ 16
3.3.4 Documentation ........................................................................................................................................ 18
3.4 GENERAL ASPECTS ..................................................................................................................................... 20
3.4.1 Limitations of HAZOP ............................................................................................................................. 20
3.4.2 Relationship with other analyses ............................................................................................................ 20
3.4.3 Hazard identification analyses during different system life-cycle stages ............................................... 21
3.4.4 Audit ........................................................................................................................................................ 22
4. AUTHORISATION ................................................................................................................................................. 23
5. REVISIONS ............................................................................................................................................................ 23
6. DEVELOPMENT TEAM ......................................................................................................................................... 23
7. ACKNOWLEDGEMENTS...................................................................................................................................... 23
A.1 EXAMPLE GUIDE WORDS ........................................................................................................................... 24
A.2 HAZOP WORKSHEET ................................................................................................................................... 30

FIGURES
Figure 1: HAZOP analysis basic steps .................................................................................................................. 12
Figure 2: Flow chart of HAZOP execution procedure ................................................................................................ 17
Figure 3: Example of risk matrix................................................................................................................................. 19

CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorised version on the system.
Unique Identifier: 240-49230111
Hazard and Operability Analysis Guideline
Revision: 1
Page: 3 of 30

TABLES
Table 1: Examples of process / system parameters .................................................................................................... 8
Table 2: Examples of deviations and their meanings .................................................................................................. 9
Table 3: Guide word / element (or parameter) associations ...................................................................................... 10
Table 4: Severity and probability of occurrence classification ................................................................................... 19

CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorised version on the system.
Hazard and Operability Guideline Unique Identifier: 240-49230111
Revision: 1
Page: 4 of 30

1. INTRODUCTION
Hazard and Operability analysis is a structured and systematic analysis of a defined system,
with the objective to identify potential hazards in the system and to identify potential
operability problems with the system. The resulting knowledge on potential hazards and
operability problems is necessary to determine appropriate remedial measures. HAZOP
analysis (also known as HAZOP study or HAZOP) deals with the identification of potential
deviations from the design intent, examination of their possible causes and assessment of
their consequences. The analysis is carried out by a multi-disciplinary team under the
guidance of a HAZOP analysis leader. It is considered a mandatory process in many
industries (e.g. process industries).

2. SUPPORTING CLAUSES

2.1 SCOPE

This guideline describes the process of performing a HAZOP analysis. It provides guidance
on HAZOP principles, the HAZOP process and the application of HAZOP during the different
system life-cycle stages. The guideline also includes typical HAZOP guide words and a
worksheet as an example.

This document is based on IEC 61822, Hazard and Operability Studies (HAZOP Studies) –
Application Guide, which should be consulted as the primary informative reference when
additional details are required. The typical guide words are based on the Hazard and
Operability Study Manual published by Integrated Safety-Health-Environment Consultants.

2.1.1 Purpose

The purpose of this document is to provide guidance on the principles of HAZOP analysis
and the procedural steps necessary to consistently perform effective HAZOP analyses on
Eskom assets.

2.1.2 Applicability

This document shall apply throughout Eskom Holdings Limited Divisions. The intended users
of this guideline include both Eskom technical personnel and sub-contractors. It is
applicable, primarily, during system design but can also be used during operations and
maintenance (e.g. analysis of upgrades or modifications).

2.2 NORMATIVE/INFORMATIVE REFERENCES

Parties using this document shall apply the most recent edition of the documents listed in the
following paragraphs.

2.2.1 Normative

[1] ISO 9001, Quality Management Systems.

CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorised version on the system.
Hazard and Operability Guideline Unique Identifier: 240-49230111
Revision: 1
Page: 5 of 30

2.2.2 Informative

[1] IEC 61882, Hazard and operability studies (HAZOP studies) – Application guide,
1st edition, May 2001
[2] IEC 60812, Analysis techniques for system reliability – Procedure for failure mode and
effects analysis (FMEA), 2nd edition, January 2006
[3] IEC 60300-3-9, Dependability management – Part 3: Application guide – Section 9:
Risk analysis of technological systems, 1st edition, December 1995
[4] IEC 61025, Fault tree analysis (FTA), 2nd edition, December 2006
[5] AS IEC 61165, Application of Markov techniques, 2008
[6] Integrated Safety-Health-Environment Consultants, Hazard and Operability Study
Manual, 1991
[7] P.D.T. O‟Connor and A. Kleyner, Practical Reliability Engineering, 5th edition, John
Wiley, 2012
[8] C.A. Ericson, Hazard Analysis Techniques for System Safety, John Wiley, 2005

2.3 DEFINITIONS

a. Design Intent
The designer‟s desired or specified range of behaviour for elements and parameters.

b. Deviation
Departure from the design intent.

c. Element1
A constituent of a part which serves to identify the part‟s essential features.

d. Guide Word
A word or phrase which expresses and defines a specific type of deviation from an element.

e. Harm
Physical injury or damage to the health of people or damage to property or the environment.

f. Hazard
Potential source of harm.

g. Parameter2
The qualitative or quantitative property of an element.

1
The word „node‟ has the same meaning as „element‟, and is often used in some industries.
2
Examples of parameters are pressure, temperature, voltage, etc.

CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorised version on the system.
Hazard and Operability Guideline Unique Identifier: 240-49230111
Revision: 1
Page: 6 of 30

h. Part3
A section of the system, which is the subject of immediate analysis.

i. Risk
A combination of the probability of occurrence of harm and the severity of that harm.

2.3.1 Disclosure Classification

Controlled Disclosure: Controlled Disclosure to external parties (either enforced by law, or


discretionary).

2.4 ABBREVIATIONS

Abbreviation Description
FMEA Failure Mode and Effects Analysis
FTA Fault Tree Analysis
HAZOP HAZard and OPerability (analysis)
PHA Preliminary Hazard Analysis

2.5 ROLES AND RESPONSIBILITIES

Not Applicable.

2.6 PROCESS FOR MONITORING

Not Applicable.

2.7 RELATED/SUPPORTING DOCUMENTS

Not Applicable.

3
A part may be physical (e.g. hardware) or logical (e.g. step in an operational sequence).

CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorised version on the system.
Hazard and Operability Guideline Unique Identifier: 240-49230111
Revision: 1
Page: 7 of 30

3. HAZOP OVERVIEW
HAZOP analysis is a detailed hazard and operability problem identification process, carried
out by a multi-disciplinary team under the guidance of an analysis leader. HAZOP deals with
the identification of potential deviations from the design intent, examination of their possible
causes and assessment of their consequences. Key features of the HAZOP examination
include the following:

a) The examination systematically uses a series of guide words to identify potential


deviations from the design intent.
b) The examination is carried out under the guidance of a trained and experienced analysis
leader.
c) The examination relies on specialists from various disciplines with appropriate skills and
experience.
d) Solutions to identified problems are not a primary objective of the HAZOP examination
(hazards identified by HAZOP for further investigation should be analysed in detail).

There are many different tools and techniques available for the identification of potential
hazards and operability problems, such as checklists, failure mode and effects analysis
(FMEA), fault tree analysis (FTA), HAZOP, etc. Before commencing a HAZOP analysis, it
should be confirmed that it is the most appropriate technique to be used. In making this
judgement, consideration should be given to the purpose of the analysis, legal and
regulatory requirements, possible severity of any consequences, appropriate level of detail,
availability of relevant data and resources, etc.

3.1 HAZOP OBJECTIVES

The primary objective of HAZOP is to:

a) Identify potential hazards (i.e. potential sources of harm) in a system.


b) Identify potential operability problems with a system.

Since hazard refers to physical injury or damage to the health of people or damage to
property or the environment, HAZOP not only relates to the system itself.

CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorised version on the system.
Hazard and Operability Guideline Unique Identifier: 240-49230111
Revision: 1
Page: 8 of 30

3.2 HAZOP PRINCIPLES

3.2.1 Examination

The basis of HAZOP is “guide word examination”, which is a search for deviations from the
design intent. To facilitate the examination, a system is divided into parts in such a way that
the design intent for each part can be adequately defined. A part may be physical (e.g.
hardware) or logical (e.g. operational sequence). The size of the part chosen is likely to
depend on the complexity of the system and the severity of the hazard.

The design intent for a given part of a system is expressed in terms of elements. Elements
may be discrete steps or stages in a procedure, individual signals and equipment in a control
system, equipment or components in a process, material involved, etc. Therefore, the choice
of elements may depend upon the particular application. Elements can often be usefully
defined further in terms of parameters which can be either quantitative or qualitative.

Examples of process/system parameters are shown in Table 1. The list is purely illustrative,
as the words employed in an actual HAZOP analysis will depend upon the system being
analysed. Note that some parameter words may not appear to be related to any reasonable
interpretation of the design intent. For example, one may question the use of the word
„corrode‟ on the assumption that no one would intend that corrosion should occur. However,
most systems are designed with a certain life-span in mind and implicit in the design intent is
that corrosion should not occur or, if it is expected, it should not exceed a certain rate. An
increased corrosion rate, in such circumstances, would be a deviation from the design intent.

Table 1: Examples of process / system parameters

Flow (gas, liquid) Temperature


Pressure Level
Separate (settle, filter, centrifuge) Composition
Reaction Mix
Reduce (grind, crush) Absorb
Corrode Erode
Isolate Drain
Vent Purge
Inspection, surveillance Maintain
Viscosity Shutdown
Instruments Start-up
Corrosion Erosion
Vibration Shock
Software data flow Density
Voltage Current
Ageing

CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorised version on the system.
Hazard and Operability Guideline Unique Identifier: 240-49230111
Revision: 1
Page: 9 of 30

The HAZOP team examines each element (and parameter, where relevant) for deviation
from the design intent which can lead to undesirable consequences. The identification of
deviations from the design intent is achieved by a questioning process using predetermined
guide words. Adjectives (or guide words), such as more, no, less, etc. are combined with
process- or system-conditions, such as flow, pressure, etc. A HAZOP analysis looks for
hazards resulting from potential deviations in design intent. The objective of the guide word
approach is to stimulate imaginative thinking, to focus the analysis and elicit ideas and
discussion, thereby maximizing the chances of analysis completeness. Examples of guide
words and their meanings are shown in Table 2.

Table 2: Examples of deviations and their meanings

Example interpretation for


Deviation Guide Example interpretation for
Programmable Electronic
type word process industry
System
Negative NO No part of the intention is No data or control signal
achieved, e.g. no flow passed
Quantitative MORE A quantitative increase, Data is passed at a higher
modification e.g. higher temperature rate than intended
LESS A quantitative decrease Data is passed at a lower rate
e.g. lower temperature than intended
Qualitative AS WELL Impurities present Some additional or spurious
modification AS Simultaneous execution signal is present
of another operation/step
PART OF Only a part of the intention is The data or control signals are
achieved, i.e. only part of an incomplete
intended fluid transfer takes
place
Substitution REVERSE Covers reverse flow in pipes Normally not relevant
and reverse chemical
reactions
OTHER A result other than the original The data or control signals are
THAN intention is achieved, i.e. incorrect
transfer of wrong material
Time EARLY Something happens early The signals arrive too early
relative to clock time, e.g. with reference to clock time
cooling or filtration
LATE Something happens late The signals arrive too late with
relative to clock time, e.g. reference to clock time
cooling or filtration
Order or BEFORE Something happens too early The signals arrive earlier than
sequence in a sequence, e.g. mixing or intended within a sequence
heating
AFTER Something happens too late The signals arrive later than
in a sequence, e.g. mixing or intended within a sequence
heating

CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorised version on the system.
Hazard and Operability Guideline Unique Identifier: 240-49230111
Revision: 1
Page: 10 of 30

Guide word/element (or parameter) associations may be listed, as shown in Table 3. To


achieve comprehensive hazard identification, it is necessary that the elements and their
associated parameters cover all relevant aspects of the design intent and guide words cover
all deviations. Combinations without credible deviations should be indicated as such on the
list. Combinations with credible deviations are examined in detail and recorded to an agreed
format (i.e. referenced in the HAZOP worksheet).

Table 3: Guide word / element (or parameter) associations

Element 1 Element 2 Element 3

Guide word / element


No Yes Ref No Yes Ref No Yes Ref
(or parameter)

No voltage X
High voltage X 1
Low voltage X
Voltage transients X 2
Intermittent voltage X 3

Appendix 0 contains examples of guide words applicable to continuous processes, batch


processes, manual tasks (operations and maintenance), electrical systems and mechanical
systems. These guide words are provided in this document for guidance only and the
analysis leader remains responsible to determine, use and record guide words applicable to
the specific project.

CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorised version on the system.
Hazard and Operability Guideline Unique Identifier: 240-49230111
Revision: 1
Page: 11 of 30

3.2.2 Design representation

An accurate and complete design representation of the system under analysis is a


prerequisite to examination. A design representation is a descriptive model adequately
describing the system under analysis, its parts and elements, and identifying their
parameters. The representation may be of the physical design or of the logical design and it
should be made clear what is represented.

The design representation should convey the function of each part and element in a
qualitative or quantitative manner. It should also describe the interactions of the system with
other systems, with its operator/user and, possibly, with the environment. The conformance
of elements or parameters to their design intent determines the correctness of operations
and, in some cases, the safety of the system.

The representation of the system consists of two basic parts:


System requirements; and
Physical and/or logical description of the design.

The resulting value of a HAZOP analysis depends on the completeness, adequacy and
accuracy of the design representation, including the design intent. Therefore, care should be
taken in preparation of the information package. If HAZOP is being conducted in the
operational or disposal phase, care should be taken to ensure that any modifications are
reflected in the design representation. Before starting the examination, the team should
review this information package and, if necessary, have it revised.

3.2.3 Design requirements and design intent

The design requirements consist of qualitative and quantitative requirements which the
system has to satisfy and provide the basis for development of system design and design
intent. All reasonable use and misuse conditions, which are expected by the user, should be
identified. Both the design requirements and resulting design intent have to meet customer
expectations.

The designer should not only consider what the equipment should do, but also ensure that it
will not fail under any unusual set of conditions or that it will not wear-out during the specified
life-time.

“Design intent“ should be correct and complete, as far as possible. In general, most
documented design intents are limited to basic system functions and parameters under
normal operating conditions. However, provisions for abnormal operating conditions and
undesirable activities which may occur (e.g. severe vibrations, water hammer in pipes,
voltage surges which may lead to failure) are rarely mentioned, but should be identified and
considered during the examination. Furthermore, deterioration mechanisms, such as ageing,
corrosion and erosion and other mechanisms which cause deterioration in material
properties are not specifically stated. However, they have to be identified and considered in
an analysis using appropriate guide words.

Expected life, reliability, maintainability and maintenance support should also be identified
and considered together with hazards which may be encountered during maintenance
activities, provided they are included in the scope of the HAZOP analysis.

CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorised version on the system.
Hazard and Operability Guideline Unique Identifier: 240-49230111
Revision: 1
Page: 12 of 30

3.3 HAZOP PROCESS

HAZOP analysis consists of four basic sequential steps:

Definition
Define scope, objectives, roles, responsibilities and select team

Preparation
Plan for study, collect data, determine style of recording and arrange meetings

Execution
Divide system into parts, define design intent, identify deviation,
identify cause, consequences, protection and indication measures

Documentation
Record examination, compile report, follow up on actions required

Figure 1: HAZOP analysis basic steps

CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorised version on the system.
Hazard and Operability Guideline Unique Identifier: 240-49230111
Revision: 1
Page: 13 of 30

3.3.1 Definition

Define scope, objectives, roles, responsibilities and select team


The scope of the HAZOP analysis will depend on a number of factors, including:

a) Physical boundaries of system


b) Number of design representatives available
c) Level of design representatives available
d) Scope of previous analyses (including HAZOP)
e) Regulatory requirements

The following factors should be considered when defining objectives for the HAZOP
analysis:

a) Purpose for which results will be used


b) Life-cycle stage of system
c) Persons or property that may be at risk
d) Potential operability problems
e) Standards required of the system

A HAZOP analysis is a team effort, with each team member being chosen for a defined role.
The team should be as small as possible, consistent with the relevant technical and
operating skills and experience being available. Generally, this will involve at least four
persons and rarely more than seven. Where a system has been designed by a contractor,
the HAZOP team should contain personnel from both the contractor and the client.

Recommended roles for team members are as follows:

Analysis leader
Not closely-associated with design team and project;
Trained and experienced in leading HAZOP analyses;
Responsible for communications between project management and HAZOP team;
Plans analysis;
Agrees to analysis team composition;
Ensures analysis team is supplied with design representation package;
Suggests guide words and guide word – element/parameter interpretations;
Conducts/facilitates examination; and
Ensures documentation of results.

Recorder
Documents the proceedings of meetings; and
Documents the hazards and problem areas identified, recommendations made and any
actions for follow-up.

Designer
Explains design and its representation; and
Explains how a defined deviation can occur and corresponding system response.

CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorised version on the system.
Hazard and Operability Guideline Unique Identifier: 240-49230111
Revision: 1
Page: 14 of 30

User
Explains operational context within which element under analysis will operate,
operational consequences of deviation and extent to which deviations may be
hazardous.

Specialists

Provide expertise relevant to system and analysis; and


May be called upon for limited participation.

Maintainer

Provides maintenance information (when required).

Operator

Provides operator information (when required).

The viewpoint of the designer and user is always required for the analysis. However,
depending on the particular stage of the life-cycle in which the analysis is carried out, the
type of specialists most appropriate for the analysis may vary. All team members should
have sufficient knowledge of the HAZOP technique to enable them to participate effectively
in the analysis or, at least, suitable introduction should be provided.

3.3.2 Preparation

Plan for analysis, collect data, determine style of recording and arrange meetings
The analysis leader is responsible for the preparation of an analysis plan that should contain
the following:

a) Objective and scope of analysis;


b) List of participating members;
c) Technical details:
Design representation divided into parts and elements (or parameters);
List of proposed guide words to be used; and
Interpretation of guide word/element (or parameters) combinations.
d) List of appropriate references;
e) Administrative arrangements;
f) Form of recording required; and
g) Templates that may be used in analysis.

The success of the HAZOP analysis firmly depends on the alertness and concentration of
the team members and it is, therefore, important that the sessions are of limited duration and
that there are appropriate intervals between sessions.

CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorised version on the system.
Hazard and Operability Guideline Unique Identifier: 240-49230111
Revision: 1
Page: 15 of 30

Typically, a design description may consist of some of the following documentation which
should be clearly and uniquely identified, approved and dated:

a) For all systems:


Design requirements and descriptions, flow sheets, functional block diagrams, control
diagrams, electrical circuit diagrams, engineering data sheets, arrangement
drawings, utilities specifications, operating and maintenance requirements.

b) For process flow systems:


Piping and instrumentation diagrams, material specifications and standards
equipment, piping and system layout.

c) For programmable electronic systems:


Data flow diagrams, object-oriented design diagrams, state transition diagrams,
timing diagrams, logic diagrams, etc.

In addition, the following information should be provided:

a) boundaries of object of analysis and interfaces at these boundaries


b) environmental conditions in which system will operate
c) operating and maintenance personnel qualifications, skills and experience
d) procedures and/or operating instructions
e) operational and maintenance experience and known hazards with similar systems

In the planning stage of a HAZOP analysis, the analysis leader should propose an initial list
of guide words to be used, and test the proposed guide words against the system and
confirm their adequacy. The choice of guide words should be considered carefully, as a
guide word which is too specific may limit ideas and discussion, and one which is too
general may not focus the HAZOP analysis efficiently.

CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorised version on the system.
Hazard and Operability Guideline Unique Identifier: 240-49230111
Revision: 1
Page: 16 of 30

3.3.3 Execution

Divide system into parts, define design intent, identify deviation, identify cause,
consequences, protection and indication measures

The analysis should follow the flow or sequence related to the subject of the analysis, tracing
inputs to outputs in a logical sequence. Hazard identification techniques, such as HAZOP,
derive their power from a disciplined step-by-step examination process. The sequence of
examination is shown in Figure 2.

a) The analysis leader explains the overall design to ensure that all team members have an
adequate understanding of the design representation. The analysis leader selects a part
of the design representation to be analysed. Thereafter, the design intent of that part is
examined and the relevant elements and any parameters associated with these elements
are identified.

b) The analysis leader chooses an element and the first applicable guide word. Thereafter,
the team examines the guide word interpretation in the context of the element to see if
there is a credible deviation from the design intent. If a credible deviation is identified, it is
examined for possible causes and consequences. In some applications, it is useful to
categorise the deviations either in terms of the severity of the consequences or in terms
of a relative risk-ranking based on the use of a risk matrix.

c) The team should identify the presence of protection, detection and indication mechanisms
for the deviation, which may be included within the selected part or form a portion of the
design intentions of other parts. The presence of such mechanisms should not stop the
potential hazard or operability problem being explored or listed or attempts being made to
reduce the probability of its occurrence or mitigating its consequences.

d) The analysis leader should summarise the results that are documented by the recorder.
Where there is a need for additional follow-up work, the name of the person responsible
for ensuring that the work is carried out should also be recorded.

e) Thereafter, the process is repeated for any other interpretation of that guide word; then
for another guide word, and then for each element of the part under analysis. After a part
has been fully examined, it should be marked as completed. The process is repeated until
all parts have been analysed.

CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorised version on the system.
Hazard and Operability Guideline Unique Identifier: 240-49230111
Revision: 1
Page: 17 of 30

Explain and understand


overall design

Select part of design


representation to be analysed

Examine and understand


design intent of part

Identify relevant elements

Determine if elements can be


divided into parameters

Select element
(and parameter)

Select guide word

Apply guide word to selected


element (and parameter)

Record whether deviation from


design intent is credible or not

Yes Investigate and record


Deviation credible? cause, consequences,
protection and indication

No

No All parameters
been examined?

Yes

No All guide words


been applied?

Yes

No All elements
been examined?

Yes

No All parts
of design been
examined?

Yes

HAZOP study completed

Figure 2: Flow chart of HAZOP execution procedure

CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorised version on the system.
Hazard and Operability Guideline Unique Identifier: 240-49230111
Revision: 1
Page: 18 of 30

3.3.4 Documentation

Record examination, compile report, follow-up on actions required


The primary strength of HAZOP is that it presents a systematic, disciplined and documented
approach. To achieve full benefits from a HAZOP analysis, it has to be properly documented
and followed up. The analysis leader is responsible to ensure that suitable records are
produced for each meeting.

Full recording of all results of applying each guide word/element combination to every part or
element on the design representation is required. Although cumbersome, it provides the
evidence that the analysis has been thorough and should satisfy the most stringent audit
requirements.

HAZOP analyses are not aimed at redesigning a system nor is it usual for the analysis
leader to have the authority to ensure that the analysis team's recommendations are acted
upon.

Before any significant changes resulting from the findings of the HAZOP have been
implemented, and once the revised documentation is available, the project manager should
consider reconvening the HAZOP team to ensure that no new hazards or operability or
maintenance problems have been introduced.

The output from a HAZOP analysis should include the following:

a) Details of identified hazards and operability problems together with details of any
provisions for their detection, and/or mitigation.
b) Recommendations for any further analyses of specific aspects of the design using
different techniques, if necessary.
c) Actions required for addressing uncertainties discovered during the analysis.
d) Recommendations for mitigation of the problems identified based on the team‟s
knowledge of the system (if within the scope of the analysis).
e) Notes which draw attention to particular points that need to be addressed in the
operating and maintenance procedures.
f) List of team members for each session.
g) Guide word check lists.
h) HAZOP worksheets.
i) Risk matrix (if required).

Risk4 can be defined as the combination of mishap severity and probability of occurrence.
The severity and probability of occurrence classifications listed in Table 4 may be used for
this purpose.

4
Refer to Failure Mode and Effects Analysis Guideline, Eskom document number xyz for more information.

CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorised version on the system.
Hazard and Operability Guideline Unique Identifier: 240-49230111
Revision: 1
Page: 19 of 30

Table 4: Severity and probability of occurrence classification


Severity Probability
1 Catastrophic A Frequent
2 Critical B Probable
3 Marginal C Occasional
4 Negligible D Remote
E Improbable

A typical risk matrix may be compiled to show the results of the HAZOP in a graphical
format, as shown in Figure 3. It is evident that risk increases with higher probability of
occurrence and higher severity levels. There are many risk matrices in existence but the
most appropriate one for a given analysis depends on the particular application5. Therefore,
risk should be managed in its context. Some companies assign descriptions, such as
“unacceptable”, “undesirable” and “acceptable” to sections of the criticality matrix. This
practice can easily result in inferior engineering decisions and is, therefore, not
recommended. The results of the analysis (e.g. individual hazards) should rather be
evaluated by persons to whom specific responsibilities are assigned (e.g. system engineer,
project manager, etc.) in relation to all project specific risks.

A
Probability of occurrence

Increase in risk
C

4 3 2 1

Severity

Figure 3: Example of risk matrix

5
IEC 60300-3-1, Dependability management – Part 3-1: Application guide – Analysis techniques for
dependability – Guide on methodology.

CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorised version on the system.
Hazard and Operability Guideline Unique Identifier: 240-49230111
Revision: 1
Page: 20 of 30

3.4 GENERAL ASPECTS

3.4.1 Limitations of HAZOP

HAZOP analyses have limitations that should be taken into account when considering a
potential application:

a) HAZOP is a hazard identification technique which considers system parts individually


and methodically examines the effects of deviations on each part. Frequently, a serious
hazard will involve the interaction between a number of parts of the system. In such
cases, the hazard may need to be studied in more detail using techniques such as event
tree and fault tree analyses.
b) As with any technique for the identification of hazards or operability problems, there can
be no guarantee that all hazards or operability problems will be identified in a HAZOP
analysis. The analysis of a complex system should not, therefore, depend entirely upon
HAZOP.
c) Many systems are highly inter-linked and a deviation at one of them may have a cause
elsewhere. Adequate local mitigating action may not address the real cause and still
result in a subsequent mishap or accident.
d) The success of a HAZOP analysis depends greatly on the ability and experience of the
analysis leader and the knowledge, experience and interaction between team members.
e) HAZOP only considers parts that appear on the design representation. Activities and
operations which do not appear on the representation are not considered.

HAZOP is particularly useful for identifying weaknesses in systems (existing or proposed)


involving the flow of materials, people or data, or a number of events or activities in a
planned sequence or the procedures controlling such a sequence. As well as being a
valuable tool in the design and development of new systems, HAZOP may also be profitably
employed to examine hazards and potential problems associated with different operating
states of a given system, e.g. start-up, standby, normal operation, normal shutdown and
emergency shutdown.

3.4.2 Relationship with other analyses

HAZOP may be used in conjunction with other analysis methods, such as FMEA and FTA.
Such combinations may be utilised in situations when:

a) The HAZOP analysis clearly indicates that the performance of a particular item of
equipment is critical and needs to be examined in considerable depth (the HAZOP may
then be usefully complemented by an FMEA of that item of equipment).
b) Having examined single element/single parameter deviations by HAZOP, it can be
decided to assess the effect of multiple deviations using FTA or to quantify the likelihood
of the failures, again, using FTA.

FMEA and HAZOP analyses are both systematic inductive analysis methods, with many
similarities. FMEA starts with identification of potential failure modes and, thereafter,
determines the possible causes and the failure effects at higher system levels. HAZOP
begins with identification of potential deviations from the design intent and then determines
the possible causes and the consequences at higher system levels (including operations).
Therefore, a major difference between the two analyses is the starting point of the analyses.

CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorised version on the system.
Hazard and Operability Guideline Unique Identifier: 240-49230111
Revision: 1
Page: 21 of 30

FMEA defines a failure mode as “the manner in which an item fails”, while HAZOP
specifically focuses on deviations, which are defined as “departures from the design intent”.
Another difference is that HAZOP is always performed from a safety viewpoint, while FMEA
may or may not be performed from a safety viewpoint.

3.4.3 Hazard identification analyses during different system life-cycle stages

HAZOP analyses are most suitable in the later stages of detailed design, for examining
operating facilities and when changes to existing facilities are made. However, HAZOP (and
other methods of analysis) should be applied during all life-cycle stages of a system:

1 Concept and definition stage


In this stage of a system‟s life-cycle, the design concept and major system parts are
decided, although the detailed design and documentation required to conduct the HAZOP do
not exist. However, it is necessary to identify major hazards at this time to allow them to be
considered in the design process and to facilitate future HAZOP analyses. To carry out these
analyses, other methods, such as checklists, reviews of historical data, FMEA and FTA, may
be used. Alternatively, a formal Preliminary Hazard Analysis may be performed.

Preliminary Hazard Analysis (PHA)6 is an inductive method of analysis, in which, the


objective is to identify the hazards, hazardous situations and events that can cause harm for
a given activity, facility or system. Most commonly, it is carried out early in the development
of a project when there is little information concerning design details or operating procedures
and can often be a precursor to further analyses. It can also be useful when analysing
existing systems or prioritising hazards where circumstances prevent a more extensive
technique from being used. A PHA formulates a list of hazards and generic hazardous
situations by considering parameters, such as:

a) Materials used or produced.


b) Equipment employed.
c) Operating environment.
d) Layout.
e) Interfaces among system components
f) Etc.

The method is completed with the identification of the possibilities that the accident happens,
the qualitative evaluation of the extent of possible injury or damage to health that could result
and the identification of possible remedial measures.

6
IEC 60300-3-9, Dependability management – Part 3: Application guide – Section 9: Risk analysis of
technological systems, 1st edition, December 1995

CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorised version on the system.
Hazard and Operability Guideline Unique Identifier: 240-49230111
Revision: 1
Page: 22 of 30

2 Design and development stage7


During this stage of a life-cycle, detailed design is developed, methods of operation are
decided upon and documentation is prepared. The design reaches maturity and is frozen.
The best time to carry out a HAZOP analysis is just before the design is frozen. At this stage,
the design is sufficiently detailed to allow the questioning mechanism of a HAZOP to obtain
meaningful answers. It is important to have a system that will assess the implications of any
changes made after the HAZOP has been carried out. This system should be maintained
throughout the life of the system.

3 Manufacturing and commissioning stage


It is advisable to carry out an analysis before the system is started up, if commissioning and
operation of the system can be hazardous and proper operating sequences and instructions
are critical or when there has been a substantial change of intent in a late stage. Additional
data, such as commissioning and operating instructions should be available at this time. In
addition, the analysis should also review all actions raised during earlier analyses to ensure
that these have been resolved.

4 Operational stage
The application of HAZOP should be considered before implementing any changes that
could affect the safety or operability of a system or have environmental effects. A procedure
should also be put in place for periodic reviews of a system to counteract the effects of
“creeping change”. It is important that the design documentation and operating instructions
used in an analysis are up to date.

5 Decommissioning or disposal stage


An analysis of this stage may be required due to hazards that may not be present during
normal operation. If records from previous analyses exist, this analysis can be carried out
expeditiously. Records should be kept throughout the life of the system in order to ensure
that the decommissioning issues can be dealt with expeditiously.

3.4.4 Audit

The program and results of HAZOP analyses may be subjected to internal company or
regulatory authority audits. Criteria and issues which may be audited should be defined in
the company‟s procedures. These may include: personnel, procedures, preparations,
documentation and follow-up. A thorough check of technical aspects should also be
included.

7
The HAZOP process described in this document (e.g. Figure 2) refers primarily to the HAZOP analysis
performed during the design and development stage.

CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorised version on the system.
Hazard and Operability Guideline Unique Identifier: 240-49230111
Revision: 1
Page: 23 of 30

4. AUTHORISATION
This document has been seen and accepted by:
Name Designation
Document Approved by TDAC ROD 31 January 2013

5. REVISIONS

Date Rev. Compiler Remarks


November 2012 1 E Pininski Final Document for Authorisation and
Publication

6. DEVELOPMENT TEAM
The following people were involved in the development of this document:

RWA Barnard, Lambda Consulting, ab@lambdaconsulting.co.za


E Pininski, Eskom, pininse@eskom.co.za

7. ACKNOWLEDGEMENTS
NONE

CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorised version on the system.
Hazard and Operability Guideline Unique Identifier: 240-49230111
Revision: 1
Page: 24 of 30

A.1 EXAMPLE GUIDE WORDS

The following checklists contain examples of guide word/deviations that may be used in the
HAZOP analysis. The team leader should ensure that any other applicable guide
word/deviations are also considered by the analysis team, recorded and analysed.

The example guide words are grouped under the following categories:

1. Continuous processes
2. Batch processes
3. Manual tasks (Operations and Maintenance)
4. Electrical systems
5. Mechanical systems

CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorised version on the system.
Hazard and Operability Guideline Unique Identifier: 240-49230111
Revision: 1
Page: 25 of 30

1 CONTINUOUS PROCESSES

Engineering drawing (e.g. Drawing title, number, revision and date)

Element identification (e.g. Element #1) (e.g. Element #2) (e.g. Element #3)
Guide word / element Yes No Ref Yes No Ref Yes No Ref
High flow x
Low flow x
No flow x
Reverse flow x
High pressure x 1
Low pressure x
Vacuum x
High temperature x 2
Low temperature
High level
Low level
High composition
Low composition
High pH
Low pH
Fast reaction
Slow reaction
Fast mixing
Slow mixing
High differential
High stress
Poor integrity
Malfunction
Impurities
Contamination
Lost containment
Radiation
Generation
Maintenance
Start/stop/emergency/test
Inoperability
Security

CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorised version on the system.
Hazard and Operability Guideline Unique Identifier: 240-49230111
Revision: 1
Page: 26 of 30

2 BATCH PROCESSES

Engineering drawing (e.g. Drawing title, number, revision and date)

Element identification (e.g. Element #1) (e.g. Element #2) (e.g. Element #3)
Guide word / element Yes No Ref Yes No Ref Yes No Ref
Excessive / over
Little / under
Not initiated
Interrupted
Stopped
Backwards
Opposite
Cancel
Faster
Slower
Late start
Early start
Long duration
Short duration
Higher pressure
Lower pressure
Higher temperature
Lower temperature
Higher composition
Lower composition
Higher pH
Lower pH
Together with
Wrong item
Other route
Higher differential
Higher stress
Poor integrity
Malfunction
Impurities
Containment loss
Radiation with
Generation with
Instead maintenance
Start/stop/emergency/test
Inoperable

CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorised version on the system.
Hazard and Operability Guideline Unique Identifier: 240-49230111
Revision: 1
Page: 27 of 30

3 MANUAL TASKS (OPERATIONS AND MAINTENANCE)

Engineering drawing (e.g. Drawing title, number, revision and date)

Element identification (e.g. Element #1) (e.g. Element #2) (e.g. Element #3)
Guide word / element Yes No Ref Yes No Ref Yes No Ref
Many operations
Long haul / reach
High rate / speed
Late starting
Increased energy
High force / tension
Heavy weight / load
Few operations
Short haul / reach
Low rate / speed
Early starting
Decreased energy
Low force / tension
Light weight / load
Stopped / interrupted
Opposite direction
Spillage while
Impurities
Inadequate conditions
Partial completion
Distortion
Breakage
Interference
Loss of control
System failure
Human failure
Distractions
Repetitive actions
Additional tasks
Friction with
Vibration with
Wear of equipment
Noise emission
Toxic emission
Heat radiation
Nuclear radiation
Wrong operation
Other direction route
Wrong material
Instead maintenance
Cleaning
Checking
Emergency

CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorised version on the system.
Hazard and Operability Guideline Unique Identifier: 240-49230111
Revision: 1
Page: 28 of 30

4 ELECTRICAL SYSTEMS

Engineering drawing (e.g. Drawing title, number, revision and date)

Element (e.g. Element #1) (e.g. Element #2) (e.g. Element #3)
Guide word / element Yes No Ref Yes No Ref Yes No Ref
High voltage
High current
High power
Leading power factor
High frequency
Increased temperature
Surges / transients
Low voltage
Low current
Low power
Lagging power factor
Low frequency
Reduced temperature
Slow response
No current
No voltage
Spurious trips
Reverse current
Reverse polarity
Stresses
Shorting
Distortion
Breakage
Interference
Instrument failure
Mechanical failure
Service failure
Human failure
Arcing
Burning
Melting
Wear/friction/impact
Ingress of dust
Noise emission
Toxic emission
Electromagnetic emission
Loss of control
Other direction/route
Wrong unit
Instead maintenance
Checking
Emergency

CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorised version on the system.
Hazard and Operability Guideline Unique Identifier: 240-49230111
Revision: 1
Page: 29 of 30

4 MECHANICAL SYSTEMS

Engineering drawing (e.g. Drawing title, number, revision and date)

Element (e.g. Element #1) (e.g. Element #2) (e.g. Element #3)
Guide word / element Yes No Ref Yes No Ref Yes No Ref
High throughput / feed
Long stroke / travel
High rate / speed
Increased temperature
High tension / thrust
High force / torque
High pressure / load
Low throughput / feed
Short stroke / travel
Low rate / speed
Decreased temperature
Low tension / thrust
Low force / torque
Low pressure / load
Stoppage / interruption
Opposite direction
Backwards run
Spillage while
Loose rate
Loose heat
Gain rate
Gain heat
Incomplete execution
Distortion
Breakage
Contaminate
Interfere
Failures while
Expansion stress
Contraction stress
Vibration stress
Depositing
Built-up
Wear with
Pollution
Emissions with
Radiation with
Loss of control
Other direction route
Wrong material
Instead maintenance
Checking
Emergency

CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to
ensure it is in line with the authorised version on the system.
Hazard and Operability Analysis Guideline Unique Identifier: 240-49230111
Revision: 1
Page: 30 of 30

A.2 HAZOP WORKSHEET

The following worksheet should be replaced with a relevant Eskom example using the selected software application.

Guide word / element


Ref Cause Consequence Protection Indication Sev Prob Recommendation Comments
(or parameter)

1 High pressure Pressure sensor faulty Rupture of feeder Pressure relief valve Pressure sensor 2 C Installation of dual redundant Refer to Design Authority for
pipes possible installed analogue output pressure sensor implementation
monitored by control
system continuous Modification of control system to
test function monitor out of range pressure
measurements
2 High temperature Temperature sensor Damage to feeder None Temperature sensor 2 D Installation of dual redundant Refer to Design Authority for
faulty pipe connections analogue output temperature sensor implementation
possible monitored by control
system continuous
test function
etc.

CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system.

You might also like