Abu Dhabi Ports Company PJSC

Contract No. 2101-240


Contract Title: Khalifa Port - Relocation of Borouge Tents

EXHIBIT A.3
COMPLETION SCHEDULE

Exhibit A.3, Rev.B SW Page 1 of 3


Abu Dhabi Ports Company PJSC
Contract No. 2101-240
Contract Title: Khalifa Port - Relocation of Borouge Tents

COMPLETION SCHEDULE

1.0 SCHEDULE

CONTRACTOR shall complete all WORKS within 214 calendar days from the COMMENCEMENT
DATE. Within this overall completion period, CONTRACTOR shall achieve completion of parts of
the WORKS in accordance with the following milestone dates:

SL. Milestone Description Completion Period from Liquidated Damages


COMMENCEMENT DATE

C Access Milestone to Contractor

1.1 Access to Phase 1 7 calendar days

1.2 Access to Phase 2 36 calendar days

1.3 Access to Phase 3 66 calendar days

1.4 Access to Phase 4 100 calendar days

1.5 Access to Phase 5 116 calendar days

1.6 Access to Phase 6 137 calendar days

F Construction Milestones
2.1.1 Completion of Phase 1 -
dismantling works as defined 28 calendar days
EXHIBIT A.1, Section 4.2
2.1.2 Completion of Phase 1 -
installing works as defined
EXHIBIT A.1, Section 4.2 for AED 15,000 /
70 calendar days
EMPLOYER to issue a calendar day
PROVISIONAL ACCEPTANCE
CERTIFICATE (PAC-1)
2.2.1 Completion of Phase 2 -
dismantling works as defined 57 calendar days
EXHIBIT A.1, Section 4.3
2.2.2 Completion of Phase 2 -
installing works as defined
EXHIBIT A.1, Section 4.3 for AED 15,000 /
99 calendar days
EMPLOYER to issue a calendar day
PROVISIONAL ACCEPTANCE
CERTIFICATE (PAC-2)
2.3.1 Completion of Phase 3 -
dismantling works as defined 87 calendar days
EXHIBIT A.1, Section 4.4
2.3.2 Completion of Phase 3 2 -
installing works as defined
EXHIBIT A.1, Section 4.4 for AED 10,000 /
129 calendar days
EMPLOYER to issue a calendar day
PROVISIONAL ACCEPTANCE
CERTIFICATE (PAC-3)
2.4.1 Completion of Phase 4 -
dismantling works as defined 121 calendar days
EXHIBIT A.1, Section 4.5

Exhibit A.3, Rev.B SW Page 2 of 3


Abu Dhabi Ports Company PJSC
Contract No. 2101-240
Contract Title: Khalifa Port - Relocation of Borouge Tents

2.4.2 Completion of Phase 4 -


installing works as defined
EXHIBIT A.1, Section 4.5 for AED 10,000 /
164 calendar days
EMPLOYER to issue a calendar day
PROVISIONAL ACCEPTANCE
CERTIFICATE (PAC-4)
2.5.1 Completion of Phase 5 -
dismantling works as defined 137 calendar days
EXHIBIT A.1, Section 4.6
2.5.2 Completion of Phase 5 -
installing works as defined
EXHIBIT A.1, Section 4.6 for AED 10,000 /
179 calendar days
EMPLOYER to issue a calendar day
PROVISIONAL ACCEPTANCE
CERTIFICATE (PAC-5)
2.6.1 Completion of Phase 6 -
dismantling works as defined 158 calendar days
EXHIBIT A.1, Section 4.7
2.6.2 Completion of Phase 6 -
installing works as defined
EXHIBIT A.1, Section 4.7 for AED 10,000 /
200 calendar days
EMPLOYER to issue a calendar day
PROVISIONAL ACCEPTANCE
CERTIFICATE (PAC-6)
2.7 Completion of all WORKS
214 calendar days

CONTRACTOR's aggregate liability for liquidated damages shall not exceed 10% of the
CONTRACT PRICE.

2.0 PROGRESS MEASUREMENT AND REPORTING

Immediately after the COMMENCEMENT DATE, CONTACTOR will submit its proposed progress
measurement and reporting system for WORKS for review and approval of EMPLOYER.
CONTRACTOR shall submit the progress report of WORKS on weekly and monthly basis. The
formats for progress reporting of WORKS shall be discussed and mutually agreed between
EMPLOYER and CONTRACTOR.