EXHIBIT A.3
COMPLETION SCHEDULE
COMPLETION SCHEDULE
1.0 SCHEDULE
CONTRACTOR shall complete all WORKS within 214 calendar days from the COMMENCEMENT
DATE. Within this overall completion period, CONTRACTOR shall achieve completion of parts of
the WORKS in accordance with the following milestone dates:
F Construction Milestones
2.1.1 Completion of Phase 1 -
dismantling works as defined 28 calendar days
EXHIBIT A.1, Section 4.2
2.1.2 Completion of Phase 1 -
installing works as defined
EXHIBIT A.1, Section 4.2 for AED 15,000 /
70 calendar days
EMPLOYER to issue a calendar day
PROVISIONAL ACCEPTANCE
CERTIFICATE (PAC-1)
2.2.1 Completion of Phase 2 -
dismantling works as defined 57 calendar days
EXHIBIT A.1, Section 4.3
2.2.2 Completion of Phase 2 -
installing works as defined
EXHIBIT A.1, Section 4.3 for AED 15,000 /
99 calendar days
EMPLOYER to issue a calendar day
PROVISIONAL ACCEPTANCE
CERTIFICATE (PAC-2)
2.3.1 Completion of Phase 3 -
dismantling works as defined 87 calendar days
EXHIBIT A.1, Section 4.4
2.3.2 Completion of Phase 3 2 -
installing works as defined
EXHIBIT A.1, Section 4.4 for AED 10,000 /
129 calendar days
EMPLOYER to issue a calendar day
PROVISIONAL ACCEPTANCE
CERTIFICATE (PAC-3)
2.4.1 Completion of Phase 4 -
dismantling works as defined 121 calendar days
EXHIBIT A.1, Section 4.5
CONTRACTOR's aggregate liability for liquidated damages shall not exceed 10% of the
CONTRACT PRICE.
Immediately after the COMMENCEMENT DATE, CONTACTOR will submit its proposed progress
measurement and reporting system for WORKS for review and approval of EMPLOYER.
CONTRACTOR shall submit the progress report of WORKS on weekly and monthly basis. The
formats for progress reporting of WORKS shall be discussed and mutually agreed between
EMPLOYER and CONTRACTOR.