Professional Documents
Culture Documents
Project Delivery
Riverside Museum
Agenda
2004 - OJEU Tender for Design Team & Exhibition Designer sees appointment
of Zaha Hadid , Buro Happold and Event Communications.
• Interviews invigilated by the RIAS were held with three 44 – Following Review
highest scored Architects and the two highest scoring
Exhibition Designers. 6 - Shortlisted
‘Combining geometric complexity with structural ingenuity and material authenticity , continues
Glasgow’s rich engineering traditions and will be part of the city’s future as a centre of innovation’
Riverside Museum
What the Engineer said…
• Achieving a Column Free Vision - The steelwork
solution utilises the folded plate geometry of the
roof, translating it into a system of inclined trusses.
Utilising support from the facades, the side walls
and the structurally stiff zones where the roof
changes direction it was possible to minimise the
depth of the structure which is hidden within the
building shell to 700mm.
• Integrated services - Substantial tunnels below the
floor , up to 3.5m deep are the main routes for the
building services including lighting, heating, IT “ Creating the spectacular roof
cables and pipework. Rainwater , brought in from
the roof via a network of pipes is also transmitted was an achievement in itself but
through these conduits. many other , hidden aspects of
• Functional Façade - Providing a low level of air this museum required
leakage and substantial insulation to reduce the exceptional engineering even
extremes of temperature and thus reducing the although they will go un-noticed
demand for heating and cooling. The north and by most visitors “
south glass facades are also multi-purpose
Riverside Museum ‘The Riverside
Funding & Costs Appeal has raised
£4.5m since the
“The Riverside Museum Project opening of the
cost totalled £74million” museum’
STAGE 1 STAGE 2
Issued in June 2006 and required pricing for Open book tendering of the remaining
Prelims/OHP and Programme as well as cost plan allowances/work package
strategic work packages:- after appointment of Stage 1 Contractor
•Substructure.
•Concrete superstructure.
•Steel Frame. ‘ During the tender period 3
•External envelope-roof . bidders withdrew because of
•wall cladding and glazing. workload and /or risk profile ‘
Riverside Museum
Contractor Procurement
• BAM Stage 1 tender accepted November 2006
Buro Happold
Zaha Hadid
Beck Mivan Directs
BAM
Contractual Link
Management Link
Overview/Reporting
Riverside Museum
Concurrent Works
Clyde
Maritime Trust
Capita Symonds
CAR PARK /
SLIPWAY SV GLENLEE CSO POINTHOUSE FERRIES HIGHWAYS
Kelvin Clyde GHL
Scottish LES
Harbour Ltd Maritime LES
Water
Trust CSPM/DBA/G
DRS &T/Gillespies
Halcrow
Leslies
Luddon Luddon
McLays Farrans /
Farrans
BBV Varis Atkins
Atkins Atkins
Contractual Link
Management Link
Overview/Reporting
Riverside Museum
Key Construction Issues
“ Structural Steelwork –
There will be books written
about this one! “
Super Trenches
‘Heavily
reinforced
tanked
underground
structures’
Riverside Museum
Key Construction Issues
• The exhibition floor-polished
concrete-that won’t crack (much !)
• Getting water !
Picking
the
colour
Suspended
ceilings
both
curved and
flat.
Riverside Museum
Key Construction Issues
The
facades
and soffits.
Riverside Museum
Key Construction Issues
Integrating and working around others:-
•Quay wall.
•Key Attracts - SA Locomotive, Trams, Buses.
•Fitting Out.
•Public Realm, SV Glenlee, River Kelvin Slip.
Riverside Museum Concurrent Works - Externally
Public Realm
- Incorporated into
BAM’s contract in
November 2009
and started in
December 2009,
substantially
completed in
December 2010 and
fully completed in
conjunction with
the closing out the
interfaces with the
other contracts
Riverside Museum
Concurrent Works - Internally
• Street 1 Fit Out- Beck Interiors started on the
Fitting out of street 1 in February 2010 and
completed this area in September 2010
Riverside Museum
Concurrent Works - Internally
• Delivery of the large key attracts at various
stages to suit the fitting out - Subway car,
Locomotives, Tramcars and Buses.
Riverside Museum
Concurrent Works - Internally
• Main exhibition hall Fit Out - MIVAN
commenced in October 2010.
Riverside Museum
Concurrent Works - Internally
• Ship Conveyor mechanism - Installed by Dodds
Engineering in December 2010.
Riverside Museum
Concurrent Works - Internally
• Velodrome - Overhead bicycle display installed
by Engage Engineering in October 2010
Riverside Museum
Facts & Figures
24,000 Individual Zinc 185 Tonnes -
Panels in the outer surface
Total Weight of
of the undulating roof,
Roof, supported by
most of which are
bespoke and were 2,500 Tonnes
engineered on site. of steelwork.
QUESTIONS
and Answers.