Professional Documents
Culture Documents
Air Insulated
Metal-Clad Switchgear
Type 8BK88PLUS with
Vacuum Circuit-breaker
Type 3AH0
On withdrawable truck upto 12 kV
Table of Contents
Page Nos Page Nos
1 Technical Description ........................................... 3 3.2.2 With Door Closed ................................................. 22
1.1 General .................................................................. 3 3.3 Checking the Accessory Items .............................. 22
1.2 Design Features ..................................................... 3 3.4 Revising the Circuit Diagram ................................ 22
1.2.1 Switchgear Layout ................................................. 3 3.5 Space Heaters ...................................................... 22
1.2.2 Circuit Breaker Compartment ................................. 4 4 Operations ......................................................... 24
1.2.3 Busbar Compartment ............................................. 4 4.1 Brief Operating Instructions ................................. 24
1.2.4 Cable & CT Compartment ...................................... 5 4.2 Withdrawable Truck ............................................. 24
1.2.5 Compartment for Low Voltage Equipment ............. 5 4.2.1 Positions of the withdrawable truck ..................... 24
1.2.6 Accessories ............................................................ 5 4.2.2 Transferring the Withdrawable truck from
1.2.7 Interlocks ............................................................... 6 the connected position to the test /
1.2.8 Vacuum Circuit Breaker 3AH0 ................................ 6 disconnected position manually ........................... 24
1.2.8.1 Construction .......................................................... 6 4.2.2.1 Normal Operations .............................................. 24
1.2.9 Secondary Eqpts. ................................................... 6 4.2.2.2 Castell Key Operations (Optional) ........................ 25
1.2.10 Vacuum Interrupters .............................................. 6 4.2.3 Transferring the Withdrawable truck
1.2.11 Complement .......................................................... 7 from the test / disconnected position
1.2.12 Closing .................................................................. 7 by hand – Normal Operation ............................... 26
1.2.13 Auxiliary Switch (S1) 3SV92 ................................... 7 4.2.4 Removing the LV Plug .......................................... 26
1.2.14 Shunt Closing Release (Y9) 3AY1510 ..................... 8 4.2.5 Connecting the LV Plug ........................................ 26
1.2.15 Shunt Release (Y1) 3AY1510 ................................. 8 4.3 Circuit Breaker Operating Mechanism .................. 26
1.2.16 Shunt Release (Y2) 3AX1101 ................................. 8 4.4 Circuit Breaker Operation ..................................... 26
1.2.17 Undervoltage Release (Y7) 3AX1103 ..................... 8 4.4.1 Charging the closing spring by hand .................... 26
1.2.18 CT-Operated Release (Y4) 3AX1102 ....................... 8 4.4.1.1 For standard panels ............................................. 26
1.2.19 Wiring .................................................................... 8 4.4.2 Switching State Indication ................................... 26
1.2.20 Dimensions and Weights ........................................ 8 4.5 Earthing ............................................................... 26
1.3 Technical Data ....................................................... 9 4.5.1 Earthing of Busbars by Insulating Pole ................. 26
1.4 Name Plates ........................................................... 9 4.5.2 Earthing of Cables by Insulating Pole ................... 26
1.5 Characteristic Values ............................................ 11 4.5.3 Removing Earthing Connections .......................... 26
1.6 Influence of Environmental Parameters ............... 12 4.5.4 Earthing of Busbars or Cables with a
1.7 Service Life .......................................................... 13 Drawout Truck ..................................................... 26
2 Installation ......................................................... 14 4.5.5 Disconnection of Earthing Drawout Truck ............ 27
2.1 Foundation .......................................................... 14 4.5.6 Earthing the Busbars or Cables with
2.2 Electrical Service Room Dimensions ..................... 14 Earthing Switch ................................................... 27
2.3 Transport Units .................................................... 14 4.5.6.1 Earthing the Busbars with Earthing Switch .......... 27
2.4 Packing ................................................................ 14 4.5.6.2 Earthing Cables with Earthing Switch .................. 27
2.5 Unloading, Movement at Site & Storage ............... 14 4.5.7 Disconnection of Earthing Switches ..................... 27
2.5.1 Unloading ............................................................ 14 4.6 Breaker Compartment Door ................................. 27
2.5.1.1 Handling Equipment Required ............................. 14 4.6.1 To Open the Door ................................................ 27
2.5.1.2 Procedure for Unloading ...................................... 16 4.6.2 To Close The Door ................................................ 27
2.5.1.2.1 Unloading Switchgear with a Mobile Crane .......... 16 4.7 LV Compartment Door ......................................... 27
2.5.1.2.2 Unloading the Switchgear 4.7.1 To Open the Door ................................................ 27
with a fork-lift Truck ............................................. 16 4.7.2 To Close the Door ................................................. 27
2.5.2 Moving Transport Unit ......................................... 16 5 Maintenance ...................................................... 28
2.5.3 Storage at Site ..................................................... 16 5.1 Inspection Schedule ............................................. 28
2.6 Examining the Switchgear against damages ........ 16 5.2 Cleaning .............................................................. 28
2.7 Transferring the Transport Units to 5.3 Lubrication .......................................................... 28
their points of installation .................................... 16 5.4 Replacement of Parts ........................................... 28
2.8 Installation of VCB ............................................... 17 5.5 Defeating the Door Interlock of
2.9 Assembling the Switchboard ................................ 17 HV Compartment ................................................. 28
2.9.1 Removal of withdrawable truck ............................ 17 5.5.1 Drawout Unit in Connected Position .................... 28
2.9.2 Bolting the Panels together .................................. 17 5.5.2 Drawout Unit in Disconnected Position ................ 29
2.9.3 Fixing the Switchboard to the Foundation ........... 18 5.5.3 Restoring the Door Interlock ................................ 29
2.9.4 Bolting the Busbars together ................................ 19 5.6 Maintenance VCB ................................................ 29
2.9.5 Bolting the Main Earth bar 5.6.1 Safety Measures .................................................. 29
sections together ................................................. 19 5.6.2 Inspection ............................................................ 29
2.10 Making the HV Cable Connections ....................... 19 5.6.3 Cleaning .............................................................. 29
2.11 Earthing the Switchboard .................................... 19 5.6.4 Abnormal Operating Conditions ........................... 29
2.12 Other Work to be carried out ................................ 19 5.6.5 Checking the Contact Systems ............................. 30
2.12.1 Checking the HV Connections .............................. 19 5.6.6 Checking the Vacuum .......................................... 30
2.12.2 Checking the bolted Joints ................................... 19 5.6.7 Service Life .......................................................... 30
2.12.3 Cleaning the Switchboard .................................... 19 5.6.8 Accessories and Spares Parts ................................ 30
2.12.4 Inserting the withdrawable truck ......................... 19 5.6.9 Spares List of VCB ................................................ 31
2.12.5 Protecting the panels against 5.6.10 Troubleshooting of 3AH0VCB ............................... 33
Environmental effects .......................................... 20 6 Disposal of the Product ...................................... 34
2.13 Interpanel Wiring ................................................. 20
7 Summary of Important Instructions ................. 34
3 Putting the Switchgear into Service ................. 21
8 Additional Information ...................................... 35
3.1 Commissioning .................................................... 21
8.1 Reference List of Items ......................................... 35
3.2 Test Operations .................................................... 22
8.2 Tightening Torques .............................................. 35
3.2.1 With Door Open ................................................... 22
2
Warning Qualified Person
To ensure personnel & product safety For the purpose of this instruction manual and
product labels, a “qualified person” is one who is
This equipment contains hazardous voltages and familiar with the installation, construction and
mechanical parts which move at high speed and operation of the equipment and the hazards
may be controlled remotely. involved.
Non observance of the safety instructions can In addition, he has the following qualifications:
result in severe personal injury or property
damage. (a) Is trained and authorized to energize, de-
energize, clear, ground and lag circuits and
Only qualified personnel should work on or equipment in accordance with established
around this equipment after becoming thoroughly safety practices.
familiar with all warnings, safety notices and
maintenance procedures contained herein. (b) Is trained in the proper care and use of
protective equipment in accordance with
The successful and safe operation of this established safety practices.
equipment is dependent on proper handling,
installation, operation and maintenance. (c) Is trained in rendering first aid.
1. Technical Description The outside covers are bolted to the frame and the
doors are hinged.
1.1 General
Type 8BK88PLUS metal-clad switchgear is of horizontal
isolation and horizontal drawout type (site extensible)
in both direction for system voltages upto 12kV. The
switchgear is designed for single busbar system and is
fully compartmentalised. The design incorporates a set 1.2
of interlocks for safe operation of the switchgear.
– a low voltage compartment (1.4, Fig. 1) Fig 1: Side view of switchgear cubicle
(withdrawable truck in test position)
3
1.2.2 Circuit breaker Compartment 1.2.3 Busbar Compartment (Fig. 4)
The circuit breaker compartment contains a drawout / The busbar compartment contains:
withdrawable truck with vacuum circuit breaker.
– The busbars
The withdrawable truck moves on two in-built (3.7,
Fig. 3) foldable ramps. It can be transferred between – Bushing with Encapsulated Feeder Connections
the Connected and Test positions behind closed doors
The busbars are extending from one switchgear
of circuit breaker compartment using a hand crank.
cubicle to the next. The ends of these sections are
In the Connected (service) position, the upper contact bolted to terminal pad of encapsulated feeder
arms of the withdrawable truck engage with the connections (4.4, Fig. 4).
mating contacts connected to the busbars and the
lower contact arms of the withdrawable truck engage
with the mating contacts connected to the outgoing
circuit.
3.10
3.15
2.2
3.1 3.11
3.16
3.14
3.18
2.1
3.17 3.13
2.3 3.12
3.4
3.2
2.4
2.1
2.4
3.7
2.5
Fig 2: Withdrawable truck with vacuum circuit breaker Fig 3: Withdrawable Truck in Test Position & door open
4
5.4
4.4
4.1 5.3
4.2
4.3
5
1.2.7 Interlocks
The positions of the withdrawable part are described
on page .
State The following operations
are not possible
Withdrawable truck in – Removal of the 8.12
connected/service withdrawable truck
position, switching – Opening of the 3.11
device “ON” circuit breaker
compartment door
– Pulling of the LV plug
3.13 3.14
switching device “OFF” – Opening of the door 8.11
8.10
– Pulling of the LV Plug
8.8
Withdrawable truck – Closing of the
8.9
located between the switching device
service and test – Opening of the
positions circuit breaker
compartment door
– Pulling of the LV plug
3.11 Opening for hand crank
Withdrawable truck in – Transfer of the 3.13 "CLOSE" pushbutton
test position, switching withdrawable truck 3.14 "OPEN" pushbutton
8.8 "CLOSE/OPEN" indicator
device “ON” – Opening of the 8.9 Spring state indicator
circuit breaker 8.10 Mechanical Counter
compartment door 8.11 Cover
8.12 Rating plate
Withdrawable truck in – Closing of the door
disconnected position – Transfer of the Fig 8: 3AH0 vacuum circuit - breaker, front view of
LV plug pulled off, withdrawable truck mechinism housing
switching device “OFF” to service position.
and door open
1.2.8 Vacuum Circuit Breaker 3AH0
6
3.9
9.8
9.1 10.6
10.1
9.2 3.13
3.14 10.2
9.3
10.5
9.4
9.11
8.9
8.10 10.7
9.12
10.4
9.7
10.3
9.13
Fig. 10: Vacuum interrupter
9.1 Gearbox 9.8 Auxiliary switch
9.2 Position switch 3.13 Pushbutton "CLOSED"
9.3 Closing spring 3.14 Pushbutton "OPEN" – Position switch for signalling
9.4 Motor 9.11 2nd shunt release "Closing spring charged" (S4)
8.9 "Closing spring 9.12 1st shunt release
charged" signal 9.13 Mechanical interlocking – Operating cycle counter
8.10 Operating cycle counter 3.9 Low-voltage plug – Shunt release 3AX 11011) (Y2)
9.7 Closing release connector
– Current transformer-operated
Fig 9: Mechanism housing without cover
release 3AX11021) (Y4)
– Undervoltage release 3AX 1103 1)
(Y7)
The fixed contact piece (10.1) is connected directly to – Mechanical interlock
the housing. The moving contact piece (10.2) is fixed
to the terminal bolt (10.3) and is located centrally in Wiring of the electrical equipment to 24-pin terminal
the guide (10.4). The metal bellows (10.5) together strip or 32 pole connector.
with insulators (10.6) made of high alumina ceramics
and the end flanges (10.7) form the vacuum-proof 1) The 3AH0 vacuum circuit-breaker can be fitted with a maximum
interrupter housing. of 1 releases of type 3AX 11. in addition to or instead of the
standard shunt release Y1.
The vacuum interrupters fitted in the 3AH0 vacuum
circuit-breakers are type-approved in accordance with 1.2.12 Closing (Refer 3.1.1)
the X-ray regulations of the Federal Republic of
Germany. They conform to the requirements of the
X-ray regulations of January 8, 1987 (Federal Law 1.2.13 Auxiliary switch (S1) 3SV92
Gazette Page 144) § 8 and Annex III Section 5 up to Two versions of the auxiliary switch can be supplied.
respective rated short-time AC voltage stipulated in The standard version is fitted with 6 NO contacts and 6
accordance with DIN VDE/IEC (rated power frequency NC contacts. The extended version is fitted with 12 NO
withstand voltage). contacts and 12 NC contacts.
Rated insulation voltage : AC/DC 250 V
1.2.11 Complement Insulation class : C
The basic version of the 3AH0 vacuum circuit-breaker Current : 10 A
comprises: Making capacity : 50 A
Manually operated snap-action mechanism for closing
Voltage Breaking Capacity
– Stored energy "open" with shunt release (Y1)
U (V) Resistive load Inductive load
– Auxiliary switch 6NO/6NC (S1)
up to 230 AC 10 10
Each 3AH0 vacuum circuit-breaker can be equipped
with the following supplementary devices: 24 DC 10 10
48 DC 10 9
Manually operated stored-energy mechanism for
closing 60 DC 9 7
– Electrical operating mechanism (M1) 110 DC 5 4
– with antipumping feature and shunt closing 220 DC 2.5 2
release (Y9) Fig. 11: Breaking capacity of 3SV92 auxiliary switch
7
1.2.14 Shunt Closing release (Y9) 3AY1510 The deliberate tripping of the undervoltage release
(additional feature) generally takes place via an NC contact in the tripping
circuit. But it can also be carried out via an NO contact
The closing solenoid unlatches the charged closing
by short-circuiting of the magnet coil. With this type of
spring and thus closes the circuit-breaker electrically.
tripping, the short-circuit current is limited by the built-
It is available for both AC and DC operation. The
in resistors (see circuit diagram), but make sure that
closing solenoid is not designed for continuous
short-circuiting of the solenoid does not last for longer
operation and it is not automatically de-energized
than 1 minute.
internally. Make sure that the closing command from
the installation is limited to max. 1 min. The supply Undervoltage release can also be connected to voltage
voltage of the closing solenoid may deviate from the transformers. When the operating voltage drops to
rated value by -15% to +10%. In operation with AC impermissibly low levels, the circuit-breaker is tripped
voltage, a rectifier module 3AX1525 is installed in the automatically.
circuit-breaker.
Power consumption approx. 27 VA or 18 W
Power consumption approx. 200 W/VA
1.2.16 Shunt release (Y2) 3AX1101 In the basic version, the control leads are connected
(additional feature) electrically directly to the built-in equipment. For this
purpose, the switching circuits are prewired in
The 3AX1101 shunt release is fitted if more than one accordance with the equipmentplan shown in Fig. 12.
shunt release is required. With its design, the electrical
opening command is transferred in boosted form to When carrying out subsequent wiring work, we
the “Open” latching mechanism via a solenoid recommend that you use the circuitry examples of the
armature through unlatching of a energy store and circuit diagram illustrated in Fig. 12.
thus the circuit-breaker is opened. This opening
solenoid is not designed for continuous operation and
it is not automatically de-energized internally. Make 1.2.20 Dimensions and weights
sure that the opening command from the installation The dimensions of the vacuum circuit-breaker are
is limited to max. 1 min. shown in the relevant drawings, which can be ordered
Power consumption approx. 60 W / VA through your Siemens office.
8
1.3 Technical Data connection with the design code stated on the name
plate, the machine-readable product designation
provides a full description of the circuit-breaker. The
8BK88PLUS
figure below shows what the individual places of the
Rated Voltage Ur 12 kV basic machine-readable product designation stand for:
Rated Power Frequency withstand 28 kV The basic machine readable product designation of the
Voltage Uw circuit breaker is stated on the name plate which can
Rated Impulse Withstand Voltage Up 75 kVp be read in the operating position, contains the
following information:
Rated short time withstand 26.3 kA
current (rms) 3 secs
Basic type
Rated peak withstand current 66 kA
Rated voltage code,
Rated short circuit breaking capacity 26.3 kA design code
Rated current of busbar (maximum) 2000 A Rated short circuit
breaking current code
Rated current of feeders (maximum) 1250 A
Rated normal current
Rated frequency 50 Hz code
3AH0
3 A H 0 1 0 4 - 2 ... Secondary equipment
Rated voltage Ur 12 kV in accordance with
delivery documents
Rated power frequency withstand
voltage Uw 28 kV
Rated lightning impulse withstand
voltage Up 75 kVp ! s !
Rated short time withstand 26.3 kA
current (rms) 3 secs Type Design Code
9
Function schematic diagram (Typical)
10
Close-open time = the interval of time (in a make-
break operating cycle) between the instant when the
contacts touch in the first pole in the closing process
and the instant when the arcing contacts separate in
all poles in the subsequent opening process.
Operating times:
Opening time, 1st shunt release (Y1) < 65 ms
Opening time, 2nd shunt release (Y2) < 50 ms
Arcing time <15 ms
Break time, 1st shunt release (Y1) < 80 ms
Break time, 2nd shunt release (Y2) < 65 ms
Arcing time = the interval of time between the instant Pulse duration of breaker tripping signal 15 ms
of the first initiation of an arc and the instant of final
arc extinction in all poles. Table 2: Operating and pulse duration times
11
Correction factor a
Ambient temperature
Fig. 16.2: Maximum permissible load current as a function of the circuit breaker ambient temperature
12
The standards provide no guideline for altitudes of 1.7.3 Load current
more than 1,000 m with respect to insulation ratings.
The maximum permissible load current as a function of
Our own recommendation is as follows:
the ambient temperature of the 3AH0 circuit breaker
Since this method used for rating insulation up to
has been plotted in Fig. 16.2. The load currents
altitudes of 1,000 m has proved to be satisfactory, it
indicated apply to open-type switchgear. Metal-
should also be applied to higher altitudes. The altitude
enclosed switchgear must be derated as specified by
correction factor ‘a’ in Fig. 16.1 should therefore be
the switchgear manufacturer.
based on the insulation capacity at 1,000 m, which is
lower by 9% than the capacity at sea level.
1.8 Service life
The following expression thus applies for the selection Under normal operating conditions, the circuit
of the air-insulated equipment: breakers are designed for 10,000 operating cycles.
Rated impulse withstand voltage to be selected Due to the optimization of the service life of all parts,
the level of reliability falls if the breakers are used for a
required rated impulse withstand voltage greater number of operating cycles. The manufacturer
>
–
1.1*a can therefore not recommend continued use of the
cirucit breakers, even if certain subassemblies are
Example: renewed.
Switchgear for Rated Voltage of 7.2kV When the permissible maximum has been attained,
Site altitude above sea level 3,000 m the complete pole assemblies must be renewed.
Required rated impulse withstand voltage 60 kV Detailed instructions are supplied with the
Correction factor (according to Fig. 16.1) 0.73 replacement pole assemblies.
Rated impulse withstand voltage to be selected:
When ordering replacement pole assemblies, state the
60 circuit breaker type, design code and serial number
kV = 74.71 kV
1.1*0.73 (see name plate).
This means that equipment designed for a rated
voltage of 12 kV, is required for this application.
13
2. Installation – Concrete Floor
This should be provided with foundation rails on which
The installation sequence should be planned and
the panels are to rest. For floor cutouts refer to Fig. 17.
prepared with care. Ensure that the erectors and the
The foundation should be prepared before the panels
operating personnel read the operation and
arrive. Level differences between the mounting
maintenance instructions.
surfaces of the individual panels should be determined
and compensated for by using a sheet as shown in
2.1 Foundation Fig. 18. The level difference beyond permissible
tolerance have to be suitably compensated.
A false floor or a reinforced concrete floor should be
used as the foundation.
2.2 Electrical Service Room Dimensions
– False Floor
Place a girder frame flush with finished floor, common Height of service room* with LV at least 2400 mm
to several or all of the switchgear panels so that it is chamber of 850 mm height
parallel to the operating front. The girder is meant to Width of control aisle in front of at least 900 mm
support the panel bottom rails below the 30mm x the panel for single row
30mm cutouts. All the edges of the panels should be
resting on this frame. Clearance between the wall and at least 800 mm
cubicle rear
* In case of LV chamber with extra height; it should be
ascertained that a min. clearance of 300 mm is available above
the LV chamber.
2.4 Packing
The transport units are packed in one of the following
methods –
(a) For shipment to inland destinations each transport
unit is fixed on a sturdy wooden pallet and covered
by plastic sheet for surface protection and packed
in normal wooden case.
(b) for shipment overseas each transport unit may be
additionally packed in a seaworthy case. It is
enclosed in plastic sheet, which is sealed air-tight
and includes bags containing dessicant.
Accessory items are packed separately, or kept in one
of the cubicle transport units (see the despatch
advice).
VAR No Rear Box Depth (D)
0-01 ----------- 2.5 Unloading, movement at site & storage
0-02 200mm
0-03 400mm
0-04 600mm 2.5.1 Unloading
0-05 800mm
0-06 1000mm
2.5.1.1 Handling equipment required
Fig 17: Foundation plan – A mobile crane or a chain pulley block of 3 tonne
Note: All dimensions are in mm capacity for unloading the transport units.
14
According to DIN 43 661, DIN 7184 and DIN 18 202, sheet No. 3, the following steps should be adhered to:
– For equalization of all irregularities of the rough floor, the screed to be applied to the floor should be at least 10 mm higher
than the height of the foundation rails.
– Before applying the screed to the floor, the foundation rails should be aligned, leveled and anchored to the rough floor.
– The top edge of the foundation rails should be flush with the upper surface of the finished floor, taking ceramic tiles,
stoneware tiles or any other floor coverings into account. The surface of the screed or of the floor covering should not be
higher than the level of the top edge of the foundation rails.
– The plane defined by the carrying surfaces of both (or several) parallel foundation rails has to be levelled in two directions
90 degrees apart by means of a levelling instrument consisting of two water filled glass tubes connected by a rubber hose.
– The level tolerance, measured along a distance of one meter, shall not exceed one millimeter.
measuring surface
t The straightness tolerances, as required by DIN
43 661 shall include the level tolerance and shall
nowhere in the complete plant to be installed
Tolerance as per DIN 43661:
exceed 2 millimeters.
– The straightness tolerance shall not exceed one millimeter per meter of length of the rails in both the flat and the edgewise
position of the rails. U-channel
reference surface
t
Level 1mm within 1mtr.measured length.
– The top horizontal surfaces of the foundation rails shall be smooth (grind welded joints smooth).
– Foundation rails embedded in concrete shall be fully grouted for their full length and be able to support a load at any point.
the location of fixing holes of the panel for tightening the foundation bolts.
Higher tolerances are to be compensated by laying sheets (below panel)
In case foundation rails or fabricated channel frames are embedded in cement concrete, care should be taken to leave open pockets below
15
– Lifting tackle. • The units must be stored in adequetly covered
location such that they are protected from Sun,
– A fork-lift truck with a fork length of about 1.5 m, Rain, Flood Waters & other such Natural elements.
for handling the switchgear inside the building.
– Hydraulic jacks or winches and roller pads. 2.6 Examining the switchgear against damage
The handling/transport gear must meet the site As soon as the switchgear has been unloaded, carry
requirements with regard to its construction and load out visual inspection and examine it to see that it is
bearing capacity. complete. Record any damage and its cause without
delay, in the presence of the forwarding/insurance
agent, if the damage was caused en route.
2.5.1.2 Procedure for unloading
This report is essential for any damage claims.
Do not unpack before unloading the transport units.
Take care not to damage the plastic sheet because it
protects the switchgear against environmental effects. 2.7 Transferring the transport units to their
points of installation
Use mobile crane or a fork-lift truck for unloading.
• Transfer the transport units including their wooden
pallets to their point of installation using fork-lift or
2.5.1.2.1 Unloading switchgear with a mobile crane mobile crane or trolleys.
• Suspend the lifting tackle from the crane and
position it over the transport unit. • Withdraw the truck from the cubicle (refer clause
2.9.1).
• Attach the ropes to the tackle and position them so
• Put the cubicles down on the cleaned site or at
that they cannot exert pressure on the switchgear
least immediately in front of it in the correct order,
panel sides.
leaving a clearance of about 25 mm between them.
• Attach the ropes to the wooden pallet.
– To remove the transport units from their wooden
• Carefully raise the transport unit and check to see pallets
that it is correctly balanced, if necessary lower the
• Open the CB door / rear bottom cover.
transport unit and correct any imbalance by
repositioning the ropes on the lifting tackle.
16
• Unscrew the bolts securing the panels to the
wooden pallet. The bolts are located in the
30mmx30mm cutouts in the floor rails (see
Fig. 17).
• Raise the transport units on their mounting site – Open the door of the circuit breaker compartment
and remove the roller pads. (refer clause 4.6.1). The withdrawable truck must
• Lower the transport units as far as possible and still be in the disconnected position.
place them on two wooden beams. – Mark the withdrawable truck and their panels.
• Now raise the units; first on one side and then – Disconnect LV plug (3.5, Fig. 3) and place it in its
on the other, using roller-type crowbars; pull out holder (3.9, Fig. 3) on the door.
the planks & lower the units onto the cleaned
foundation. Position the crowbars only at the – Unscrew the bolts (3.12, Fig. 3) on the interlocking
corners of the transport units below the vertical plate.
frame members.
– Slowly move the truck away from the panel. The
two ramps drop automatically enabling free easy
2.8 Installation of VCB withdrawal of truck.
The breaker can be lifted by means of the two – Put back the ramp to normal position and close the
transport holes marked by a crane symbol-using CB chamber door (refer clause 4.6.2).
suitable hoisting gear. Ref. Fig. 20.
– Remove the other drawout trucks in the same
The 3AH0 vacuum circuit breakers are supplied in the manner.
open (OFF) state with closing spring discharged.
Never handle a withdrawable truck by its contact
arms.
2.9 Assembling the switchboard
Carry out the work described under clauses 2.9.1 to
clause 2.9.5 in that sequence. While bolting the 2.9.2 Bolting the panels together
panels/busbars, keep the bolts loose (not fully It is assumed that the first transport unit is in its final
tightened) till all the bolts for sections (refer clause position and that the other units are positioned on the
2.9.2 to 2.9.5) are in position. Then tighten the joining foundation rails in the correct order but with a
bolts (refer clause 2.9.2) followed by busbar bolts, clearance of approximately 50 cms between them.
(refer clause 2.9.4.2) followed by foundation bolts
(refer clause 2.9.3). It is always preferable to install the central transport
unit first. This practice should be invariably adopted for
a board with 20 or more panels. After installing the
2.9.1 Removal of withdrawable truck central transport unit, the other units can be installed
– Bring the withdrawable truck to disconnected on its left and right in proper sequence.
position (refer clause 4.2.2).
• Procedure
– Place platform of same height as of wooden pallet
in front of the panel but joining the pallet. – Centrally align the central transport unit on its
17
foundation. The switchgear cubicle must be at the
correct level (refer Fig. 18) and be absolutely
vertical. If necessary place shims.
18
• Welding 2.12 Other work to be carried out
Weld the bottom rails to the foundation at the cutouts.
Insert shims (refer clause 2.9.2), where necessary, to 2.12.1 Checking the HV Connections
avoid having to weld across air gaps. Coat the welds
On all HV cables, check
with any anti-corrosion paint.
– the bolts for tightness
• Bolting Down
– the sealing and earthing
Embed anchor-bolts in the foundation (through the 30
mm x 30 mm cutout) or drill the appropriate holes in – the core spacing on three core cables and the anti-
the foundation rails (false floor). magnetic clips on single-core cables.
19
– Transfer the drawout truck inside the panel and (b) Fit the parts supplied to protect against the ingress
push it as far as it will go. of reptiles. Check in case they are removed during
installation.
– Fix the racking mechanism/interlocking plate to
structure frame. (c) Close all the doors & covers properly.
20
3. Putting the switchgear into service On the 3AH0 vacuum circuit breaker with
undervoltage release (Y7) 3AX1103, the arresting
For details of operation refer section 4 screw of the hammer must be moved from position A
to B (see instruction card in the mechanism housing of
3.1 Commissioning the 3AH0 vacuum circuit breaker).
21
the vacuum circuit-breakers and must be ordered 3.3 Checking the Accessory Items
separately).
The accessory items required must be easily available
To protect the motors, we recommend and MCB with G in the switchgear room or an adjacent room. They
characteristics. include one hand crank each for transferring the
withdrawable truck and for charging the breaker
The supply voltage of the motor-operated mechanism closing spring, a double-kit key for locking the hand-
may deviate from the rated value by - 15% to + 10%. operating mechanism, the basic circuit diagram,
operating instructions and warning signs. The hand
DC/AC DC 220 V/
Rated supply voltage DC 24 V DC 48 V DC 60 V 110 V AC 230 V crank for transferring the withdrawable truck is also
50/60 Hz 50/60 Hz suitable for all M8 bolts. Operating rod for manual
Recommended rating 10 A 8A 6A 4A 2A
closing and opening.
of protection device
Fig. 26: Rated currents of motor protection devices 3.4 Revising the Circuit diagrams
If circuits have to be modified during installation, the
3.2 Test operations existing circuit diagrams are marked up. When work
has been completed make sure that the original
3.2.1 With door open diagrams are revised.
22
s
23
4. Operations • The breaker compartment door can be opened.
• The circuit breaker can be tested/operated, also
4.1 Brief operating instructions from the control room.
Each row of cubicles is provided with brief operating • Functions such as ‘ON/OFF’ indication and
instructions. Refer to figure 25. electrical interlocks can be tested.
Non-observance of the safety instructions can result 4.2.2 Transferring the withdrawable truck from
in severe personal injury or property damage. the connected position to the test/
disconnected position manually
In particular:
Do not remove the cover of the mechanism housing.
Do not reach inside any openings in the operating 4.1.2.1 Normal operations
mechanism. Do not touch pole assemblies and
In brief:
operating rods.
1st Step 2nd Step 3rd Step
Turn double-bit key Insert and Turn double-bit key
4.2 Withdrawable truck turn hand
crank
The circuit breaker is connected with the busbars and 90° 90°
the outgoing circuit Auxiliary circuit is connected
through LV plugs and socket.
Fig. 27
24
In detail:
– Ensure that the circuit breaker is open.
– Turn the castell key (which is trapped in the
28.9
mechanism) anti-clockwise through 90º from
“Connected position (locked)” to “Manual Racking”.
– In this position the castell key can be removed for
any interlocked operations which are to be
28.2
performed with circuit breaker in open condition.
The hexagon shank opening (28.8, Fig. 28) is now
3.1
accessible.
Fig 28 In detail:
– Turn the double-bit key anti-clockwise through 90° – Ensure that the circuit breaker is open, the LV plug
from the position “Manual Racking” to (3.5, Fig. 3) and socket connector (3.15, Fig. 3) has
“Disconnected Position (locked)” and pull it off. been put together and lock it up with the clip (3.10,
Fig. 3). The breaker compartment door is closed.
Opening (28.8, Fig. 28) is now closed.
The hand racking mechanism is locked. – The castell key can be removed in this position also
for any interlocked operations which are to be
4.1.2.2 Castell Key Operations (optional) performed with circuit breaker in open position.
Fig. 29
25
4.2.4 Removing the LV Plug 4.5 Earthing
– Transfer the withdrawable part to the test position
(in accordance with clause 4.2.2) and lock it. 4.5.1 Earthing of busbars by insulating pole
– Open the breaker compartment door (refer clause – Switch off all breakers feeding to the busbars.
4.6.1).
– Open upper rear cover (of busbar chamber). Touch
– Unlock the plug (3.5, Fig. 3) and socket connector all phases with an earthing conductor mounted on
(3.15, Fig. 3) by turning down the clip (3.10, a long insulating pole.
Fig. 3).
– Short all the phases with a conductor and bolt it to
– Pull off the plug and attach it to the holder (3.9, earth.
Fig. 3) which is fixed to the door.
– Place necessary warning plates at all noticeable
locations.
4.2.5 Connecting the LV Plug
– Put the plug (3.5, Fig. 3) and socket connector
4.5.2 Earthing of Cables by insulating pole
(3.15, Fig. 3) together and lock it with the clip
(3.10, Fig. 3). – Switch off the breaker in the cubicle where cable
earthing is desired.
– Close the breaker compartment door (refer clause
4.6.2). – Ensure that the cables are not getting the supply
from the other end.
4.3 Circuit-breaker operating mechanism – Remove the lower rear cover of the cable chamber.
The operating mechanism is of the stored energy type. – Follow the procedure described for busbar
For electrically operated breakers, motor automatically earthing.
charges the closing spring after each switching “ON”
operation. Should the motor supply fail, the closing
spring can also be charged by hand. 4.5.3 Removing earthing connections
– Disconnect and remove the shorting and insulating
4.4 Circuit-breaker Operation pole.
– Close the rear cover and bolt it firmly.
4.4.1 Charging the closing spring by hand:
– Remove the warning plates.
• Procedures
If the breaker compartment door 4.5.4 Earthing of busbars or cables with a
drawout truck
is closed (connected is open (disconnected
position) turn plate (3.16, position), fit the hand Separate drawout trucks can be supplied optionally for
Fig. 3) so that it clears crank directly to the busbar and cable earthing. In case fault making
opening. Insert the hand breaker operating capacity is required, a circuit breaker is mounted on
crank and fit it to the opening mechanism in such drawout trucks.
(3.11, Fig. 3) of breaker. opening (3.11, Fig. 3).
• Procedure
• Operating Mechanism
– Remove the circuit breaker or the link drawout
Turn the crank until the symbol “Spring Charge” truck from the panel where earthing is to be done
appears in viewing window (Fig. 28) on the Spring (refer clause 2.9.1).
Charge indicator. The operator is not at risk should the
motor supply recover, because the hand crank free- – Insert the desired earthing drawout truck i.e. cable
wheels and detaches in the anti-clockwise direction. or busbar earthing drawout truck in the panel (refer
clause 2.12.4).
– Pull the crank off.
– Connect the LV plug and socket (refer clause 4.2.5).
4.4.1.1 For standard panels – Close the cubicle door (refer clause 4.6.2).
– Insert handle (6.5, Fig. 6) in respective hole (3.18, – Ensure that there is no voltage available on the part
Fig. 3) to “ON” / “OFF” the VCB. to be earthed when earthing drawout truck without
– If necessary charge the closing spring manually if making capacity is used.
LV plug has been pulled off in disconnected – Transfer the drawout unit to the connected position
position. (refer clause 4.2.3). In case the earthing drawout
truck has an electro-mechanical interlocking unit
4.4.2 Switching State Indication mounted on it, the transfer is possible only after all
the interlocking conditions are satisfied.
In the middle part of viewing window (3.17, Fig. 28)
‘O’ means “OFF”, ‘I’ means “ON”. – Lock it in the connected position.
26
– In case the drawout truck has a circuit breaker – In case the earthing switch is provided with electro-
mounted on it, switch it “ON”. magnetic interlocks, ensure that all interlocking
conditions are satisfied. Otherwise the earthing
– Place the warning plates at all necessary locations.
switch cannot be closed.
– Close the earthing switch by inserting the earthing
4.5.5 Disconnection of Earthing Drawout truck
switch handle in position and turning it in the
– Switch “OFF” the breaker in case of earthing clockwise direction till stop. Withdraw the handle.
drawout truck with making capacity.
– Place the warning plates at necessary locations.
– Transfer it to the disconnected position (refer
clause 4.2.2).
4.5.6.2 Earthing Cables with Earthing Switch
– Disconnect the LV plug (refer clause 4.2.4). (Fig. 30)
– Open the circuit breaker compartment door (refer – Move the truck to test/disconnected position.
clause 4.6.1). Earthing switch cannot be closed until this position
– Remove warning plates. is reached.
– Insert the original drawout truck of circuit breaker – Ensure that the cables cannot be energized from
or link drawout truck in the panel (refer clause the other end.
2.12.4).
– Follow the procedure for Busbar earthing switch.
– Connect the LV plug (refer clause 4.2.5).
– Close the door (refer clause 4.6.2). 4.5.7 Disconnection of Earthing Switches
– The original drawout truck is now ready for transfer
– Insert the earthing switch handle in position. Turn
to connected position.
it in the anti-clockwise direction till it stops.
Withdraw the handle.
4.5.6 Earthing the Busbars or Cables with
Earthing Switch – Remove warning plates from location.
4.5.6.1 Earthing the Busbars with Earthing Switch 4.6 Breaker Compartment Door
– Switch off the supply to the main busbars. The door can be opened and closed when the truck is
in the test position and the plug-and-socket connector
– Ensure that the supply to main busbars cannot be for the LV cables has been connected together.
switched “ON” from remote points.
The door interlock can be defeated as described under
clause 5.5.
27
5. Maintenance Cast resin parts should be cleaned with either a clean
dry cloth or cloth moistened with distilled water. Silver
plated and other contact surfaces to be cleaned with a
5.1 Inspection Schedule clean cloth.
– Each year
• Make a general visual check for all parts/ 5.3 Lubrication
supports.
Immediately after cleaning:
• Check whether the accessories are complete and
in proper order. – Lubricate the isolating contacts and their mating
contacts with neutral grease.
• Lubricate the wheels and moving parts of the
truck and interlocking plate. – Apply a film of neutral grease to the bearings and
articulated joints of the operating mechanisms, to
– Every five years, in addition to checks carried out the withdrawable parts and shutters, and to the
every year door hinges and locks.
• Transfer the drawout truck to the disconnected – Using a wooden spatula to lubricate the auxiliary
position. switches of the drawout unit with grease.
• Test-operate the circuit-breakers.
Recommended neutral greases are:
• Remove the drawout trucks (refer clause 2.9.1)
and carry out all maintenance work, also on the (i) SERVOGEM 2 (multipurpose) of Indian Oil
switching devices. Corporation make.
• Clean the panels and check the connections for (ii) Multipurpose Grease ‘H’ of Hindustan Petroleum
tightness, if any. Ltd. make.
• Lubricate all bearing surfaces, bearings and (iii) Any other chemically neutral grease which can
articulated joints. withstand temperature upto 150°C.
• Reinsert the drawout trucks. – Lubricate non-current carrying parts with
• Check the switchgear panel functions and put general purpose grease.
the board back into service.
If work has to be carried out in the panels, isolate the 5.4 Replacement of Parts
board, make sure that it cannot be made live again, Items such as post insulators, bushings, measuring
check its isolated state and earth and short-circuit the instruments, current transformers etc., can be
feeders and where applicable, the busbars. Adhere to replaced. If replacement is likely to prove difficult, ask
all regulations and safety measures, maintain and the nearest Siemens representative in good time for
service the built-in equipment, e.g. circuit-breakers, deputation of suitable personnel. The representative
vacuum contactors, voltage transformers, current will also assist you in deciding what spare parts to keep
transformers, relays, meters, protective devices, etc. in in stock.
accordance with their operating instructions.
When ordering spare parts and units, give the
Before removing the interlocking plate of the breaker following details:
operating mechanism, discharge the closing and
tripping springs. – Type and Serial No. of the equipment (see
Only standard tools are required. Put the switchgear nameplate).
back into service as described under clause 3 above. – Exact description of the unit or part, referring to the
Service the switchgear at shorter intervals if the air is appropriate operating instructions where
very moist or full of dust or is otherwise polluted. The applicable, or to a drawing, sketch or circuit
cause of any disturbance or short-circuit must be diagram.
determined immediately and damaged parts replaced,
irrespective of whether an inspection is due or not.
5.5 Defeating the Door Interlock of HV
Compartment
5.2 Cleaning
Caution : Take utmost care while defeating any
Cleaning Agents:
interlock, as the defeat operation leads to access to
Perchlorethylene, 1.1.1 trichloroethane, small brushes, the areas / parts which are likely to be live.
dusters and vacuum cleaner.
Trichlorethylene, perchloroethylene and 5.5.1 Drawout Unit in Connected Position
tetrachloroethylene and similar other agents have a
The breaker compartment door interlock should only
harmful effect on cast-resin parts and must not come
be defeated if the withdrawable part cannot be
into contact with them.
28
transferred to the disconnected position and the 5.6.2 Inspection
situation cannot be cleared in any other way.
Under normal operating conditions, the 3AH0 vacuum
– Switch off the circuit-breaker. circuit-breaker is maintenance-free. We recommend
nonetheless a regular visual inspection to check for
– Make sure that the busbars are not live. soiling (e.g. dust, saline fog, fungus etc.) of the circuit-
breaker.
– Open all the locking bolts.
– Open 2-M4 screws (28.10, Fig. 28) for emergency 5.6.3 Cleaning
release of the door.
To assure the insulating capacity, it is necessary that
– Open the door (refer clause 4.6.1). the insulating components are clean. Insulating
components and external breaker parts must be wiped
with a damp cloth. Use only warm water with the
5.5.2 Drawout Unit in disconnected position addition of a mild liquid household detergent as
– Press the leaf spring on interlocking plate by hand / cleaning agent.
small connector.
Caution
5.5.3 Restoring the Door Interlocks
All springs of the operating mechanism must be
After carrying out the operations to defeat the door
discharged and the vacuum-breaker be brought into
interlock as described in clause 5.5.1 or clause 5.5.2,
the open state, "Closing spring charged" indication not
the door of the HV compartment can be closed and
visible.
interlocks can be restored by following the procedures
in clause 5.5.1 in the reverse sequence. Nonobservance can result in personal injury.
29
5.6.5 Checking the contact system
The contact system is subject to wear both by contact
erosion and by compression of the contact pieces and
the terminal bolts. To check the contact wear, a
marking is provided on the lower interrupter support
(Fig. 31). The position of the indicator (1) relative to
the stripe (2) in closing state indicates changes in the
contact system. The breaker may be operated only
when the indicator is within the range of the stripe.
30
The following table lists the necessary work:
Maintenance schedule
2. Breaker pole
2.1 – Perform H. V test ... .... .... .... X –
– Replace vacuum interrupters ... .... .... .... X While ordering replacement
after 20000 operations interrupters, state CB type, design
code & sr. no. (refer rating plate)
3. Breaker operating mechanism
3.1 – Replace motor M1 ... .... .... .... X –
3.2 – Replace closing spring ... .... .... .... X –
Fig. 32
31
5.6.9 3AH0 Breaker Spares List
32
5.6.10 Troubleshooting of 3AH0 VCBs
33
6 Disposal of Product During disposal of the product, care must be taken to
dismantle as far as possible in more environmentally
This product is environmentally compatible. accepted way as Recyclable & Non-cyclable scraps i.e.
The following materials have been used to make up steel, copper, aluminium, rubber, PVC, cast-resin &
the device : Steel, Copper, Aluminium, Cast-resin, glass-fibre-reinforced materials segregated properly.
glass-fibre-reinforced thermoplastics, rubber, The cyclable materials like Steel, Copper, Aluminium
porcelain, greases etc. PVC is used as an insulation can be reused. Non cyclable materials like Cast-resins,
material for control wires. glass-fibre-reinforced etc. can be broken into pieces &
In as-supplied condition, the product does not then used as land filling materials.
incorporate any hazardous substances. Local customer support-Siemens office will be able to
In operation, the product does not emit any hazardous answer any questions concerning disposal.
materials or gases.
During Installation & Commissioning Stages :- (8) Ensure that the shutters are close and pad
locked before starting the maintenance or
(1) Brush the contact surfaces properly before cleaning of the panels.
bolting busbars. Also grease the joints &
apply proper torque on the bolts. (9) Depending on site conditions, inspect
(2) Check rated voltages of equipments such as – the interior of the panels for dust,
motor, closing & tripping releases mounted cobwebs etc. & clean them.
in the operating mechanism with the
available auxiliary supply to be connected to – post insulators & clean them,
these equipments in the substation. – operating mechanism parts such as
(3) Ensure that all the foundation bolts are plungers of releases, moving joints etc. &
tightened along with the square washer and clean them, and
also seal of all control and power cable – functioning of space heaters.
cutouts to prevent vermin entry.
(10) Lubricate moving parts with lubricants
During service life of the panel- provided for the breaker.
(4) Keep door & covers firmly closed to prevent (11) Check insulation resistance with a megger
entry of dust, moisture, insects etc. before putting the breaker back into service.
(5) Ensure spring charging handle & manual (12) Keep a log-book for each panel.
handle are available easily.
(13) Follow instructions given in the operating
(6) Decide maintenance schedule based upon manual.
(a) no. of short circuit operations,
(b) frequency of breaker ON/OFF operations, (14) Ensure panel operations, maintenance etc. is
(c) pollution level (d) humidity, etc. done by trained persons.
(7) Isolate & earth the breaker before carrying (15) Operate the defeat interlock of CB door only
out maintenance & ensure it is in OFF in case of emergency.
position & springs are discharged completely
before cleaning.
DON’Ts
(1) Do not leave any equipments or tools in the (3) Do not operate the breaker during cleaning
panel. process.
(2) Do not put hands or tools in operating (4) Do not use any other chemical or grease for
mechanism when electrically operated. clearing or lubricating other than mentioned in
these instructions.
34
8 Additional Information
Item No. Description Fig. No. Item No. Description Fig. No.
1.1 Circuit Breaker Compartment 1 6.1 Spring charging handle 6
1.2 Busbar compartment 1 6.2 Hand crank for movement 6
1.3 Cable & CT compartment 1 between service & test
1.4 Low Voltage compartment 1 6.3 Double bit key 6
2.1 Circuit-breaker operating mechanism 2, 3, 7 6.4 Handle for operation of earth switch 6
2.2 Contact arms 2 6.5 Handle for manual operation of C.B. 6
2.3 Encapsulated housing 2, 7 7.2 Vacuum Interrupter 7
2.4 Interlocking plate 2, 3 7.3 Switching Bar 7
2.5 Scaping earthing contact 2 8.8 ‘Close/Open’ indicator 8
3.1 CB Chamber Door 3, 21, 28 8.9 Spring state indicator 8, 9
3.2 Door close interlock 3 8.10 Mechanical counter 8, 9
3.3 Viewing window for truck position 3 8.11 Cover 8
3.4 Viewing window for spring charge 3, 28 8.12 Rating plate 8
indicator & mechanical counter 9.1 Gear box 9
3.5 32-pin LV socket 3 9.2 Position switch 9
3.7 Ramp 3 9.3 Closing spring 9
3.9 Holder for LV plug 3, 9 9.4 Motor
3.10 Clip for locking LV plug 3 9.7 Closing release 9
3.11 Opening for hand crank 3, 8 9.8 Auxiliary switch 9
3.12 Bolts of interlocking plate 3 9.11 Second shunt release 9
3.13 ‘ON’ push button 3, 8, 9 9.12 First shunt release 9
3.14 ‘OFF’ push button 3, 8, 9 9.13 Mechanical interlocking 9
3.15 LV socket connector 3 10.1 Fixed contact piece 10
3.16 Plate for covering manual spring 3, 28 10.2 Moving contact piece 10
charging opening 10.3 Terminal bolt 10
3.17 Viewing window for ON/OFF indicator 3, 28 10.4 Guide 10
3.18 Opening for manual operation 3, 28 10.5 Metal bellows 10
4.1 Encapsulated feeder connection-L1 4 10.6 Insulators 10
4.2 Encapsulated feeder connection-L2 4 10.7 End flanges 10
4.3 Encapsulated feeder connection-L3 4 21.2 Upper metallic shutter 21
4.3.1 Upper insulated bushing - L3 22 21.3 Lower metallic shutter 21
4.3.2 Upper fixed contacts - L3 22 28.2 Window for inspecting 28
4.4 Terminal pad for bolting 4 withdrawable part
5.1 Main earth bus 5, 30 28.7 Opening for double bit key 28
5.2 Insulating bushing for lower 5 28.8 Opening for hand crank for 28
mating contacts movement between test &
5.2.3 Lower insulated bushing - L3 22 service positions
5.2.4 Lower fixed contacts - L3 22 28.9 Door for LV equipment copartment 28
5.3 Current transformers 5 28.10 Opening for defeating interlock 28
5.4 Cable connecting piece 5 30.1 Earth switch (fixed contacts) 30
5.5 Metal cover for control wire ways 5 30.2 Earth switch (moving contacts) 30
5.6 Gland plate for power cables 5 30.4 Flexible for earth switch connection 30
35
Siemens Ltd.
Power Transmission & Distribution Division
Medium Voltage Switchgear
Thane Belapur Road,
Thane 400 601.
Tel. : +91-22-2762 3544
Fax : +91-22-2762 3715 Order No. 4-XXBXX-03-29790-001
Siemens Ltd. 'Product development is a continuous process. Consequently, the 030001
data indicated in this Booklet is subject to change without prior
PTD-63-152-017
notice. For the latest information please contact our Sales Offices.'