Professional Documents
Culture Documents
The design took into account, applicable TEPNG (the client) General
Specifications, international codes/standards which include but not
limited to:
3.3.1.1 GS EP PVV 001 Correspondence between Elf and
Total Piping Material Classes.
3.3.1.2 GS EP PVV 111 Piping design specification
3.3.1.3 GS EP PVV 112 Piping material classes
3.3.1.4 GS EP PVV 119 Design of Standard Piping Support
3.3.1.5 GS EP PVV 148 Glass – Reinforced Plastic Piping
Materials (Tubes & Accessories)
3.3.1.6 GS EP PVV 178 Design and Erection of Glass
Reinforced Plastic (GRP) Piping System.
34
ASE-050501), with 28” GRE pipe, at tie-in point 16-01 (see NG-
ODU-UNITY-ASE-050101). Other pipe routings which were majorly
temporary involved three pipe sizes. The first was the modification
of a 10” Carbon Steel piping. This was done by decommissioning of
a 10” cap on the line, 10"-NW-1801-B513, which was replaced
temporarily at tie-in point, 16-03, by two flanged carbon steel
spools holding a ball valve in place. This connection preceded the
10” flexible hose which spanned all the way to the portside. On
approaching the portside, there was a carbon steel connection
between the flexible hose running from the tie-in point (16-03) and
all the way down the portside to the sea. This was done to enable
the vacuum breaker, which is made of carbon steel, to be installed.
The vacuum breaker was not installed with the initial carbon steel
connection at the tie-in point because it has to be very close to the
portside.
The second temporary pipe routing was the modification of a 20”
GRE Piping connected to the 28” header. This was to stop flow to
the 28” header during the period of maintenance. This was done by
temporarily decommissioning the GRE line, 20"-SW-2450-B700 and
replacing it with a 20” carbon steel line, 20"-SW-2451-B513, at tie-
in point, 16-02. This 20” carbon steel line was reduced to 12” by a
20”x12” eccentric reducer. But between the tie-in point, 16-02 and
the reducer was placed a 20”x4” weldolet (on the 20” carbon steel
line) carrying a 4” carbon steel weldneck flange to retain the
connection of the existing 4” GRE line, 4"-SW-2407-B630, with the
initially existing but temporarily decommissioned 20” GRE line.
This temporary connection between the 4” carbon steel weldneck
flange and the 4” GRE line was at tie-in point, 16-04. After the
20”x12” reducer was placed a 12” carbon steel line 12”-SW-2451-
B513, routed towards the starboard (away from the 28” header)
carrying the 12”x6” vacuum breaker which was close to the
starboard, before the introduction of a 12” flexible hose connected
down to the sea at the starboard.
36
GRE – CL150
Flat gasket –
8. Neoprene 3mm thk 28 1 15.00 15.00
shore – CL150
Flat gasket –
9. Neoprene 3mm thk 4 2 3.00 6.00
shore – CL150
Studs – A193 B7 + 2
washers Hh Nut A192 1
10. 2H Zinc- 28 8.50 238.00
1
×195 mm
plate/bichromate 4
treated
Studs – A193 B7 + 2
washers Hh Nut A192
5
11. 2H Zinc- 16 5.00 80.00
8
plate/bichromate
treated
N/B: All cost are not exact, but are approximate values within range
of the quoted values above.
Flange – Composite
flange WN stub end
7. 2
stock finish A105 –
GRE – CL150
Flat gasket –
Neoprene 3mm thk
8. 28
shore – CL150
Flat gasket –
9. Neoprene 3mm thk 4
shore – CL150
10. Studs – A193 B7 + 2 1
washers Hh Nut A192
1
×195 mm
2H Zinc- 4
39
plate/bichromate
treated
Studs – A193 B7 + 2
washers Hh Nut A192
5
11. 2H Zinc-
8
plate/bichromate
treated
3.6 Recommendations
Routine checks and maintenance should be carried out
regularly to avoid failure or shutdown of operation which could
lead to extra loss or cost.
More research should be done as to determine materials with
better resistance to harsh operating conditions so as to reduce
damage on piping systems and operations.
3.7 Conclusion