You are on page 1of 5

BOQ Checklist

Project Name: Residential Phase III, Raintree Boulevard Bangalore

Package Title: Diaphragm wall

Date: 03.03.20

Sr No Checklist Points

1 Approved Budget Sheet

2 Page Numbers

3 Make list

4 Drawings (Based on which BOQ is prepared)

5 Is this LTR standard BOQ

6 Scope Attached

Vendor List:
1.
7 2.
3.

Package owner’s signature

# Sensitivity : This Document is Classified as "LNT Internal Use".


Date: 03.03.2020

Document No.

SIGN OFF - BOQ - Diaphragm wall

PROJECT NAME Residential Phase III, Raintree Boulevard Bangalore

VENDOR ON BOARD DATE ( BY PROJECT TEAM ) Immediate

CONTRACT STRATEGY ( BY PROJECT TEAM) Direct Order to Contractor

ENGINEER-IN-CHARGE ( BY PROJECT TEAM) Mr. Anil Kumar Arunachalam

WING Towers 26- 35 and NTA

WING BUDGET (In Lakh.)

PACKAGE Core and Shell

PACKAGE BUDGET (In Lakh.) - A

SUB PACKAGE Core and Shell

SUB PACKAGE BUDGET (In Lakh.) - B

SUB PACKAGE BUDGET FOR BOQ UNDER 1.93


CONSIDERATION (In Cr.) (Excl. Tax)

SUB PACKAGE BUDGET FOR BOQ UNDER 2.28


CONSIDERATION (In Cr.) - C (Incl. Tax)

TAXES Including GST

VARIANCE (IF ANY) (In Lakh.) = B - C

REASON FOR VARIANCE

SUB PACKAGE ALREADY RELEASED

COST OF SUB-PKG RELEASED (In Lakh.)- D

BALANCE SUB PACKAGE

FORECASTED COST OF BALANCE SUB PACKAGE (In Lakh.) - E

FORECASTED VARIANCE = A-C-D-E

MITIGATION PLAN

WBS REFERENCE

Note : This BOQ required to revalidated, if WO is not placed within 3 Months from date of Signed off BOQ

Sensitivity : This Document is Classified as "LNT Internal Use".


#
Design Cost Management Project

Sensitivity : This Document is Classified as "LNT Internal Use".


#
PROJECT : RTB Phase 3 (T26 to T35)
Diaphragm wall
Sl No Description of Item Unit Qty Rate Amount
Scope of work Include Designing of 600mm thick and 11 mtr depth Diaphragm wall as per site
1 conditions. Design to be done as per IS 9556 and take approval from structural consultant & EIC EACH 1 100,000 100,000
from and to issue GFC drawings.

Mobilization -: all required machinery equipment tools and tackle for Diaphragm wall work
required to complete the scope of work as per project requirement. set up on site ready to start
2 the work (Casacanda/Smiler machine with 600mm grab, one 35 Ton crovler crane,Polimer mixing EACH 1 - -
tank two numbers each tank 25000 litters capacity ,Anchoring machine and other component)

Guide wall : Providing and construction of guide wall 600mm X 1200 mm depth for drilling works
as per site requirement. Cost including require excavation machine or manual, Shuttering ,
3 Reinforcement and Concreting as per the design & drawing. RMT 130 4,000 520,000
Note : Reinforcement and Concreting to be paid in the separately
D'wall excavation : Excavating for D Wall using hydraulic rig machine with 600mm jaw
attachment for Diaphragm wall in soil , sand , clay , grevel , Soft rock , weathered rock and
4 disposing the same with on site. Cost include with providing required Polymer slurry for soil SQM 1,430 4,000 5,720,000
stabilisation of excavated surface. excavation start from Guide wall top to founding level as per
drawing.

D'wall excavation in Hard Rock : Excavating for D Wall using hydraulic rig machine with 600mm
jaw attachment for Excavation In rock strata and disposing the same with on site. Cost include
5 with providing required Polymer slurry for soil stabilisation of excavated surface. excavation start SQM 100 15,000 1,500,000
from Guide wall top to founding level as per drawing.
Concreting work -: providing , placing and removal of MS tube (Stopped) ,fabricated steel cage
lifting with sufficient capacity crane and concreting done as per tremie method with crane for
6 Diaphragm wall (We are providing our Design mix)., please refer our Methodology. SQM 1,430 450 643,500

7 Providing and fixing PVC 230mm width rubber stopper. RMT 300 450 135,000
i) Anchor including materials, Drilling, Grouting, Stressing and including 4t -12.7mm
8 stand PT cable ( 1 mtr - Without cement only. ) (Free length 5 mtr. Fixed length 12mtr. Total RMT 900 3,500 3,150,000
length = 17mtr. (Vary as per design)
Guide wall M-15 concrete
Providing and laying Controlled concrete from In house batching plant at site (at times of Batching
plant being in operational, RMC source from outside shall be used), using 10 mm & 20 mm
downgraded aggregates for Reinforced Cement Concrete (RCC) of various grade conveyed to all
locations, lifted and placed in position by pumping or other approved means, vibrated,
consolidated finished evenly and cured. etc. complete (excluding form work, reinforcement and
structural steel, Mesh, Insert Plates). The Item rate shall include cleaning with air jet the surfaces
of formwork to receive concrete before placing of concrete, preparing surfaces & junctions of
adjacent RCC works completed earlier, cost of all materials, miscellaneous consumables,
labours, transportation of material to all required locations by pumping or other approved means,
Placing vibrating, compacting, Curing etc. tools, plant and machinery, hire and fuel charges and
all other incidental charges , grout filling of tie-rod holes, wall-ties holes with approved non-
shrinking and waterproofing grout material etc. complete all as per specifications, drawings and
as directed by EIC. All Construction joints/Cold Joint/Pour joints needs to be brushed, cleaned
9 and treated with approved chemical bonding agents as per approved manufacture's specification Cum 65 3,800 247,000
to the satisfaction of EIC and Consultant. The item rates shall hold good for work at all Levels ,
lead, lifts, Heights, Depths, elevations, basements, trenches, pits, tunnels, etc. Designing of
concrete mix for different grades of controlled concrete should be done in accordance with latest
IS-SP-23 (Hand book on concrete mix design) in an approved lab and the same should be got
approved by EIC, The providing and laying of Concrete shall be designed irrespective of the type
of formwork Aluminium / Conventional, the item rates also includes cost for the same. Item rate
shall also include testing charges required for quality check as per approved quality plan.
Mode of Measurement : RCC members shall be certified as per theoretical quantity from GFC
drawing."

Sensitivity : This Document is Classified as "LNT Internal Use".


#
Diaphragm wall M-30 concrete
Providing and laying Controlled concrete from In house batching plant at site (at times of
Batching plant being in operational, RMC source from outside shall be used), using 10 mm & 20
mm downgraded aggregates for Reinforced Cement Concrete (RCC) of various grade conveyed
to all locations, lifted and placed in position by pumping or other approved means, vibrated,
consolidated finished evenly and cured. etc. complete (excluding form work, reinforcement and
structural steel, Mesh, Insert Plates). The Item rate shall include cleaning with air jet the surfaces
of formwork to receive concrete before placing of concrete, preparing surfaces & junctions of
adjacent RCC works completed earlier, cost of all materials, miscellaneous consumables, labours,
transportation of material to all required locations by pumping or other approved means, Placing
vibrating, compacting, Curing etc. tools, plant and machinery, hire and fuel charges and all other
incidental charges , grout filling of tie-rod holes, wall-ties holes with approved non-shrinking and
waterproofing grout material etc. complete all as per specifications, drawings and as directed by
EIC. All Construction joints/Cold Joint/Pour joints needs to be brushed, cleaned and treated with
approved chemical bonding agents as per approved manufacture's specification to the
satisfaction of EIC and Consultant. The item rates shall hold good for work at all Levels , lead,
lifts, Heights, Depths, elevations, basements, trenches, pits, tunnels, etc. Designing of concrete
mix for different grades of controlled concrete should be done in accordance with latest IS-SP-
10 23 (Hand book on concrete mix design) in an approved lab and the same should be got approved Cum 858 4,200 3,603,600
by EIC, The providing and laying of Concrete shall be designed irrespective of the type of
formwork Aluminium / Conventional, the item rates also includes cost for the same. Item rate
shall also include testing charges required for quality check as per approved quality plan.
Mode of Measurement : RCC members shall be certified as per theoretical quantity from GFC
drawing."

Reinforcement D wall & guide wall


"Providing, Straightening, cutting, bending and binding in position of reinforcement bars (TMT
bars- Fe 550D ) high yield strength deformed bars conforming to IS:1786-2008 with 18 gauge
annealed binding wire, to correct shape and size as per detailed drawings, specifications and
approved bar-bending schedules, for all reinforced concrete work such as pile caps, footings,
RCC walls, columns / stub columns, plinth beams, floor slabs, floor beams, Staircase, Lintels,
OHWT, LMR, rafts etc. at all heights and all levels; with correct sizes approved concrete cover
blocks of same grade as of concrete and galvanized binding wire of 18 gauge; if required
dewatering, required labour and machines / equipment /tools / tackles / vehicles for handling,
shifting etc. and cutting and bending as per drawing, reinforcements all complete to the
satisfaction of the EIC. The Item rate shall include providing all materials required such as
reinforcement steel bars (TMT bars- Fe 550D conforming to IS:1786-2008 ), miscellaneous
consumables such as 18 gauge annealed Galvanised Iron binding wire , chairs ,pins ,spacers
,correct sizes approved concrete cover blocks or approved PVC cover block , Cost of Labour,
machines / equipment / tools / tackles / vehicles for all transportation, Handling, unloading
reinforcement in the stocking yard, shifting the same to cutting & bending yard, Straightening,
11 cutting, bending, shifting from yard to all required locations, heights, depths & levels, all MT 75 47,000 3,525,000
necessary miscellaneous handling charges, tying reinforcement steel as per drawing and all
incidental work required etc. complete as directed by EIC. Item rate shall also include testing
charges required for quality check as per approved quality plan.- No separate payment for
binding wires, chairs, Pins, spacer and cover blocks shall be considered. Only authorized laps
shall be considered for payment as per GFC drawing."

12 Cement for anchoring Bag 470 350 164,500


Total Amount -: 19,308,600

Sensitivity : This Document is Classified as "LNT Internal Use".


#

You might also like