Date: 03.03.20
Sr No Checklist Points
2 Page Numbers
3 Make list
6 Scope Attached
Vendor List:
1.
7 2.
3.
Document No.
MITIGATION PLAN
WBS REFERENCE
Note : This BOQ required to revalidated, if WO is not placed within 3 Months from date of Signed off BOQ
Mobilization -: all required machinery equipment tools and tackle for Diaphragm wall work
required to complete the scope of work as per project requirement. set up on site ready to start
2 the work (Casacanda/Smiler machine with 600mm grab, one 35 Ton crovler crane,Polimer mixing EACH 1 - -
tank two numbers each tank 25000 litters capacity ,Anchoring machine and other component)
Guide wall : Providing and construction of guide wall 600mm X 1200 mm depth for drilling works
as per site requirement. Cost including require excavation machine or manual, Shuttering ,
3 Reinforcement and Concreting as per the design & drawing. RMT 130 4,000 520,000
Note : Reinforcement and Concreting to be paid in the separately
D'wall excavation : Excavating for D Wall using hydraulic rig machine with 600mm jaw
attachment for Diaphragm wall in soil , sand , clay , grevel , Soft rock , weathered rock and
4 disposing the same with on site. Cost include with providing required Polymer slurry for soil SQM 1,430 4,000 5,720,000
stabilisation of excavated surface. excavation start from Guide wall top to founding level as per
drawing.
D'wall excavation in Hard Rock : Excavating for D Wall using hydraulic rig machine with 600mm
jaw attachment for Excavation In rock strata and disposing the same with on site. Cost include
5 with providing required Polymer slurry for soil stabilisation of excavated surface. excavation start SQM 100 15,000 1,500,000
from Guide wall top to founding level as per drawing.
Concreting work -: providing , placing and removal of MS tube (Stopped) ,fabricated steel cage
lifting with sufficient capacity crane and concreting done as per tremie method with crane for
6 Diaphragm wall (We are providing our Design mix)., please refer our Methodology. SQM 1,430 450 643,500
7 Providing and fixing PVC 230mm width rubber stopper. RMT 300 450 135,000
i) Anchor including materials, Drilling, Grouting, Stressing and including 4t -12.7mm
8 stand PT cable ( 1 mtr - Without cement only. ) (Free length 5 mtr. Fixed length 12mtr. Total RMT 900 3,500 3,150,000
length = 17mtr. (Vary as per design)
Guide wall M-15 concrete
Providing and laying Controlled concrete from In house batching plant at site (at times of Batching
plant being in operational, RMC source from outside shall be used), using 10 mm & 20 mm
downgraded aggregates for Reinforced Cement Concrete (RCC) of various grade conveyed to all
locations, lifted and placed in position by pumping or other approved means, vibrated,
consolidated finished evenly and cured. etc. complete (excluding form work, reinforcement and
structural steel, Mesh, Insert Plates). The Item rate shall include cleaning with air jet the surfaces
of formwork to receive concrete before placing of concrete, preparing surfaces & junctions of
adjacent RCC works completed earlier, cost of all materials, miscellaneous consumables,
labours, transportation of material to all required locations by pumping or other approved means,
Placing vibrating, compacting, Curing etc. tools, plant and machinery, hire and fuel charges and
all other incidental charges , grout filling of tie-rod holes, wall-ties holes with approved non-
shrinking and waterproofing grout material etc. complete all as per specifications, drawings and
as directed by EIC. All Construction joints/Cold Joint/Pour joints needs to be brushed, cleaned
9 and treated with approved chemical bonding agents as per approved manufacture's specification Cum 65 3,800 247,000
to the satisfaction of EIC and Consultant. The item rates shall hold good for work at all Levels ,
lead, lifts, Heights, Depths, elevations, basements, trenches, pits, tunnels, etc. Designing of
concrete mix for different grades of controlled concrete should be done in accordance with latest
IS-SP-23 (Hand book on concrete mix design) in an approved lab and the same should be got
approved by EIC, The providing and laying of Concrete shall be designed irrespective of the type
of formwork Aluminium / Conventional, the item rates also includes cost for the same. Item rate
shall also include testing charges required for quality check as per approved quality plan.
Mode of Measurement : RCC members shall be certified as per theoretical quantity from GFC
drawing."