You are on page 1of 7

IMPLEMENTING LEAN CONSTRUCTION

CONCEPTS IN A RESIDENTIAL PROJECT


Bruno Pontes Mota1, Ricardo Rôla Mota2 and Thaís da C. L. Alves3

ABSTRACT
The main goals of this paper are to present a case in which Lean Construction
concepts were implemented and to discuss the benefits achieved during the process.
The case study was developed during the construction phase of a residential project in
the urban area of Fortaleza, Brazil. The project comprised the construction of 18
houses financed by a private investor and it was constructed and managed by a small-
sized construction company. After lean concepts were implemented the project
achieved a more stable flow of work and the number of emergency requests for
resources decreased dramatically. Also, the project was completed a month in
advance when compared to its original schedule thus allowing the investor to sell the
units sooner than expected. Finally, after analyzing the benefits achieved in this pilot
project the company’s upper management has decided to use Lean concepts in other
projects, and the private investor wants to make sure Lean is used in other projects
financed by his company. The paper aims at contributing to the literature on Lean
Construction on the industry papers section by presenting a success story experienced
by a small-sized construction company.

KEY WORDS
Production system design, transparency, line-of-balance, home building

alongside the project manager, the


INTRODUCTION foreman, and the company’s owner to
The main goals of this paper are to re-schedule the project and plan its
present a case in which Lean main work and material flows. Special
Construction concepts were attention was given to papers on
implemented and to discuss the production system design, tools and
benefits achieved during the process. principles used to provide transparency
The case study was developed during to work flows and enhance
the construction phase of a home communication between managers and
building project in the urban area of workers at construction sites (Alves
Fortaleza, Brazil. Based on guidelines and Formoso 2000; Schramm et al.
provided in previous IGLC papers 2004).
(e.g., Alves and Formoso 2000,
Ballard 2001), the authors worked

1
Undergraduate student, Civil Engineering, Federal University of Ceará, Brazil. Phone +55 85
3244-1697, brunopmota@yahoo.com.br
2
Director, Pauta Engenharia Ltda, Brazil. Phone +55 85 3244-1697, ricardo@pauta.eng.br
3
Assistant Professor, Department of Structural and Construction Engineering, University of Ceará,
Brazil. Phone +55 85 3366-9607, ext.36, thaiscla@ufc.br

251
Implementing Lean Construction Concepts in a Residential Project

Bruno Pontes Mota, Ricardo Rôla Mota and Thaís da C. L. Alves

LITERATURE REVIEW is one of the most important ones as it


allows the system to communicate
The production system design
with its workers and managers thus
represents one of the first managerial
enhancing their ability to detect
tasks to be performed before a
problems and correct them before they
construction project starts. Through
halt the system’s flows (Koskela
the design of a production system,
1992). For that reason, every effort
engineers aim at reducing variability,
should be made to enhance a system’s
improving predictability, and
ability to communicate with managers
improving the flow of work by
and workers. Santos (1999) provides
aligning multiple interests so that value
several examples of the application of
is delivered to internal and external
transparency and visual management
clients (Ballard et al. 2001). The goal
in construction. It is worth noting that
is to design a system that is capable of
the initiatives related to visual
delivering value with minimal waste
management are usually inexpensive
through better alignment of goals,
and provide a good basis to
definition of assignments, and
communicate decisions related to a
management of flows.
production system design and its
According to Ohno (1988), the
indicators (Alves and Formoso 2000).
foundation of a production system is
Schramm et al. (2004) suggest a
the stability that supports other
series of interactive tasks that should
activities of the system. Stability is one
be carried out to design a production
of the basic tenets of a Lean system
system for housing projects. Initially,
and it is the foundation of the Toyota
a base unit (e.g., a house) should be
Production System which provides the
defined so that the base unit
support to the system’s two columns,
installation sequence and the necessary
namely just-in-time and jidoka. In the
capacity to build it can be set. Parallel
construction literature, Ballard and
to that, a study of workflows should be
Howell (1998) suggest that in order to
done for the base unit. The next step is
achieve stability it is necessary to
to define the project execution
shield production against variations
strategy, i.e., the sequencing of
and undesired effects from interaction
processes and their paths at the
with suppliers, among crews, and with
construction site, and how this
the various flows of resources and
definition impacts the work carried out
information necessary to deliver a
at the base unit level. Finally, the
construction project. Once the system
capability of resources necessary to
is shielded and stable, managers can
complete the project is defined and a
evaluate the system’s actual capacity
study of the project critical tasks is
and test how much of that capacity can
carried out. According to Schramm et
be used to deliver the project.
al. (2004, p.11), once the production
The main goals of a Lean system
system design is set, it is important to
are to deliver the best quality, at the
have ways to communicate the adopted
lowest cost and the shortest lead time
strategies and definitions to managers
to its clients; therefore, the entire
and crews, and “there must be an
system should be designed to achieve
these goals. Amongst the Lean emphasis on process transparency in
concepts that support these goals terms of dissemination of plans and
goals.”
transparency, e.g., visual management,

Proceedings for the 16th Annual Conference of the International Group for Lean Construction

People, Culture and Change


252
Implementing Lean Construction Concepts in a Residential Project

Bruno Pontes Mota, Ricardo Rôla Mota and Thaís da C. L. Alves

CASE STUDY 2001) for the management to evaluate


actual productivity rates at the site.
The study presented in this paper was
The project duration had been
carried out in a project that comprised
estimated in 10 months according to
the construction of 18 houses financed
the experience of a company director.
by a private investor. The project was
After the first house was finished, and
constructed and managed by a small-
the initial productivity rates were
sized construction company based in
analyzed, the project managers
the city of Fortaleza in north-eastern
realized that the entire complex could
Brazil. During the study, the project
be executed in 8 months. The original
managers implemented different lean
estimates were far off the mark as the
construction concepts, tools, and
duration indicated in the contract had
techniques aiming at organizing the
too much slack in it.
construction company’s production
planning and control system. DEFINITION OF THE SEQUENCE AND
Managers also worked on the design of STRATEGY OF EXECUTION
the project’s production system Before the implementation of Lean
following the guidelines suggested by concepts and tools, the company did
Schramm et al.’s (2004) model for not have any standard procedure
production system design. regarding the planning and control of
The company decided to embark in its projects. All the decisions were
a lean journey after the crews had made based on the company director’s
almost finished the first of the 18 and long-time collaborators’ (last
houses in the complex. The project planners) experience. Thus, the first
had started at house number 09, in the step in the study was to carefully
front part of the complex, so that this define the sequence and strategy of
house could serve as a model to be execution for the remainder 17 houses
presented to potential customers and (Figure 1), and to define the capacity
serve as a first run study (Ballard et al. available for the project.

Figure 1: Construction site plan and sequence of execution


house it should proceed with its work
ANALYSIS OF THE WORK FLOW
until the last house was finished. The
Activity work flows were analyzed line of balance (LOB) was the tool
based on the production rates defined used to represent the long-term
in the previous stage and a base unit planning of the project because of its
for all the tasks was set as a house. ability to communicate important
Once a trade started working in a concepts such as continuity, pace of

Proceedings for the 16th Annual Conference of the International Group for Lean Construction

People, Culture and Change


253
Implementing Lean Construction Concepts in a Residential Project

Bruno Pontes Mota, Ricardo Rôla Mota and Thaís da C. L. Alves

work, as well as information related to necessary to complete each house for


activity durations, interferences each phase of the project.
between trades, and trade location. It is worth noting that this project
The LOB was developed using MS had a longer timeline than what was
Excel®. In order to assure a achieved by its end. Reaching a
continuous flow of work and maintain shorter schedule was not only a matter
the stability of workflows, the of shaving some time off the schedule
managers analyzed the project by re-programming activities through
suppliers’ lead times and defined the LOB, but also a matter of engaging
milestones for the acquisition of workers to work in a faster pace than
materials. Also, all materials they used to. Thus, the management
necessary to complete a service used to decided to design an incentive system
be delivered to work stations before for workers to commit to and follow
the beginning of work shifts. The what was defined by the LOB. For
managers separated internal and each half day saved, the worker
external set-up times by separating the received coupons to participate on a
work that could be done before crews raffle with different prizes at the end of
arrived at each work station. the project.
COMMUNICATION OF PLANS, GOALS,
DISCUSSION OF THE RESULTS
AND INCENTIVES
After lean concepts were implemented
A set of tools was used to improve the
the project achieved a more stable flow
communication of the plans and goals
of work and the number of emergency
to the last planner and his crews, as
requests for resources decreased
well as to the investor and the
dramatically. The project was
company’s managers. Along these
completed a month in advance and
lines, an agenda with a bill of
allowed the investor to recover his
resources needed for construction was
investment sooner than expected.
created to indicate when each of them
Besides the qualitative data collected
had to be quoted and ordered so that
for this project, hard numbers were
they would be delivered before
also collected to prove the efficiency
activities planned starting dates. The
of the new concepts and tools used by
procurement system developed in MS
the company.
Excel® alerted the buyer about the
After the company owner decided
need to start the purchasing process to implement Lean concepts and tools,
and it acted like a kanban system the project management team revised
pulling materials when needed the project duration once more. The
according to the plan represented in new duration (7 months) represented a
the LOB. Also, the LOB set the pace, decrease of 12,5% in time when
path, and the sequence of work and compared to the duration achieved for
these information was displayed to the first house (8 months). Table 1
workers in the form of A4 cards in shows a comparison of average daily
front of each house. The cards productivities for the main activities
indicated the work that had to be done necessary to complete one base unit
in each house by a specific team in a (one house). The productivities
period of time, the starting date, and indicated for 8-month duration
the due date. The cards worked like (column C) were collected from the
kanbans which pulled the work

Proceedings for the 16th Annual Conference of the International Group for Lean Construction

People, Culture and Change


254
Implementing Lean Construction Concepts in a Residential Project

Bruno Pontes Mota, Ricardo Rôla Mota and Thaís da C. L. Alves

execution of the first house whereas Other indicators were collected to


the productivity rates indicated for 7- compare and contrast the status of the
month duration (column D) were project with other projects built by the
obtained after the other 17 houses were company. The managers wanted to
completed according to what was verify the results achieved with the
defined by the LOB. The improvement implementation of Lean concepts and
in productivity (column E) observed tools used.
for the activities presented in table 1
represents an average of 15.7%.
Table 1: Productivity improvement for selected activities

Productivities
Activities Unit Improvement in productivity
(A) (B) 8 months 7 months (E)
(C) (D)

Excavation m3 / man / day 13.13 15.00 14.2%


Mansonry (rocks) m3 / man / dia 3.85 4.50 16.9%
Mansory (bricks, course) m2 / man / day 8.47 10.00 18.1%
Slab (assembly) m2 / man / day 15.09 17.50 16.0%
Structural concrete (25 Mpa) m3 / man / day 4.38 5.00 14.2%
Mansory (bricks, bull stretcher) m2 / man / day 10.50 12.00 14.3%
Plastering 1 (chapisco) m2 / man / day 71.63 82.00 14.5%
Plastering 2 (reboco) m2 / man / day 13.78 16.00 16.1%
Plastering 3 (emboço) m2 / man / day 12.64 15.00 18.7%
Finishings m2 / man / day 10.56 12.00 13.6%
Painting m2 / man / day 16.33 19.00 16.4%

A list with the main indicators is materials to complete the


presented: planned activities. About 10%
of the bids and requests for
• About 85% of the tasks were
material purchase were delayed
initiated at the planned time,
or had wrong information in
whereas the other 15% started
them. The percentage of
late due to supplier delays (doors
late/wrong requests was reduced
and windows) and the painting
to close to zero after the
activity (due to rain).
procurement system was
• About 15% of the activities were implemented. This helped the
completed as planned. About achievement of a continuous
80% of them were finished flow on site because materials
before their due date. were delivered according to what
was needed and at the time they
• Before the procurement system
were necessary.
was implemented, workers often
stopped because they lacked

Proceedings for the 16th Annual Conference of the International Group for Lean Construction

People, Culture and Change


255
Implementing Lean Construction Concepts in a Residential Project

Bruno Pontes Mota, Ricardo Rôla Mota and Thaís da C. L. Alves

• Managers noticed that the a different point of view. The project


productivity rates turned out to managers and the investor realized the
be better than originally planned, importance of shielding production
in the beginning of the project, against variation, and organized the
because the last planner had procurement and scheduling systems,
underestimated productivity rates and the physical flows on site as a
to protect workers. As the means to reduce non-value added
managers realized this fact, they activities. The tools used provided
adjusted the line of balance and managers and workers with more
set activities’ pace according to information, simultaneously available
actual productivities verified on to all of them, than they had ever had
site. After the line of balance in any of the company’s projects. The
was adjusted, the productivity initiatives increased productivity (an
rates kept going up revealing that average of 15%) and reduced the
workers were motivated by the project duration (from 8 to 7 months).
goals set and the incentives they An incentive system was put in place
would get to meet the deadlines. to motivate workers to achieve the
goals set by the project managers, and
CONCLUSIONS it succeeded as workers responded to
The paper presented the beginning of a the challenges dictated by the
Lean journey of a small-sized schedule. Several project indicators
company in Fortaleza/Brazil. The reflect the positive results obtained
authors shared the experience they with the implementation of Lean
gained while following the changes so Construction concepts and tools.
that other companies, regardless of Currently, the company is refining
their size, can also be motivated to its procurement system, training the
achieve gains through the management team on Lean concepts
implementation of Lean concepts and and tools, and trying to innovate by
tools. However, it is worth noting that creating new ways to put Lean into
the results achieved are limited by the practice.
conditions present in the case study,
ACKNOWLEDGEMENTS
i.e., project’s favorable cash flow,
incentives given to early completion of Thanks are due to the project team for
tasks, high level of repetitiveness, use being receptive to the implementation
of actual productivity vs. planned to of the Lean concepts and tools and for
re-schedule the project. participating actively in making the
During the project, the company changes happen.
decided to implement different
initiatives based on Lean concepts and
understood the project dynamics from

REFERENCES
Alves, T.C.L. and Formoso, C.T. (2000) Guidelines for managing physical flows in
construction sites. Proc. 8th Annual Conference of the International Group for Lean
Construction (IGLC-8), Brighton, UK, 12pp
Ballard, G. (2001) “Cycle time reduction in home building.” Proc. 9th Annual Conf. of
the Intl Group for Lean Construction (IGLC-9), 6-8 August, Singapore.

Proceedings for the 16th Annual Conference of the International Group for Lean Construction

People, Culture and Change


256
Implementing Lean Construction Concepts in a Residential Project

Bruno Pontes Mota, Ricardo Rôla Mota and Thaís da C. L. Alves

Ballard, G. and Howell, G. (1998) “Shielding production: an essential step in production


control.” ASCE, J. of Constr. Engrg. and Mgmt., 124(1) 11-17, Jan/Feb issue.
Ballard, G., Koskela, L., Howell, G. and Zabelle (2001) T. Production system design:
work structuring revisited. Lean Construction Institute White Paper #11
Koskela, L. (1992) Aplication of the new production philosophy to construction.
Stanford, CIFE, 1992. Technical Report# 72. 75pp.
Ohno, T. (1988) Toyota Production System: beyond Large-Scale Production.
Productivity Press: Cambridge, Mass. 142pp.
Santos, A., dos (1999). Application of Flow principles in the production management of
construction sites. PhD Thesis. School of Construction and Property Management,
University of Salford, England. 463 pp.
Schramm, F.K., Costa, D.B., Formoso, C.T. (2004). “The Design of Production Systems
for Low-Income Housing Projects.” Proc. Twelfth Annual Conference of the
International Group for Lean Construction (IGLC-12), Elsinore, Denmark.

Proceedings for the 16th Annual Conference of the International Group for Lean Construction

People, Culture and Change


257

You might also like