All Material received at site shall be inspected and ensured all material as per drawing. Any discrepancies, damage etc. found will be notified and reported take necessary action. Site engineer has to ensure that all equipment’s used at site free from any damage or dust. The unit shall be loaded from the store place on the suitable trailer by suitable crane or fork lift to shift the respective generator from the room location. The unit shall be offloaded near the generator room. The unit shall be shifted on the respective foundations by the suitable loader, which the unit will taken from outside to inside. Proper care to secure the units, while above shifting loading/unloading as well place shall be carried out with most care and precaution required. Pre delivery inspection shall be performed at manufacture plant. Prior to start the installation, site Engineer has to ensure that material received at site as per drawings. The nameplate will be checked against the name plate date sheet to conform the unit. Ensure the all the civil works completed, for the area including floor paint to carry out the installation. Installation procedures are be followed as per the manufacture recommendations. Installation works shall be carried out only with respect to the approved shop drawings. Site Engineer has to ensure that the orientation of the DG set Exhaust duct and fuel pipe installation shall comply with relevant cause of specification as per manufacture recommendation. Alternator neutral terminal and body shall be connected with external earth as per approved drawing. Alternator control panel shall be connected as per approved drawing and manufacture recommendations. Cable connection between alternator, control panel and Emergency panel shall be done as per approved drawing Required power and control termination shall be terminated as per approved drawing. After inspection of DG set proper care will be taken to protect the unit from the dust by suitable covering and shall be further released for testing.