Professional Documents
Culture Documents
Rcca - Training Beechcraft
Rcca - Training Beechcraft
Objective:
07/13/10
“True” RCCA Training Class
Features:
• Utilizes three primary tools:
– Project Rolling Action Item List (RAIL)
– Issue Closure Plan (ICP)
– Root Cause Verification Action Plan (VAP)
07/13/10
“True” RCCA Training Class
Features (cont’d):
07/13/10
“True” RCCA Training Class
Features (cont’d):
• This training is based on the HBC modified 8-D problem solving
steps but with additional instruction offered to increase the focus
needed to assure that a team captures “true” root cause and
confidently prevents re-occurrence. Therefore, Step 4 has been
expanded into 3 sub steps.
– HBC “Modified” 8-D Process (steps 1 and 2 switched, Step 8 includes closure justification):
1. Construct the problem statement
2. Form a team
3. Implement interim containment
4. Determine the root cause (RC)
1. Brainstorm
2. Sort and Analyze
3. RC Verification Action Plan (VAP)
5. Develop corrective action (CA)
6. Validation of corrective action (Implement a permanent fix)
7. Prevent recurrence, preventive action (PA)
8. Project closure justification, recognize the team
This training assumes that you have some familiarity with the 8-D problem 07/13/10
– Start the project RAIL right away (eventually the Project Leaders responsibility)
• First step in a written trackable plan
– Use for logging anything that needs follow up, no need to limit content
• Typical columns needed:
- Item number (entry order) - Assigned to (responsible)
- Priority number - ECD Pert Diagram
- Date initiated - Date complete
- Description - Comments
1 2 3
Communications and
Interim containment are 8D
steps for emerging issues
(normally not applicable for
CAB selected projects)
05/5/11
ICP form available under Form tab at
http://www.hawkerbeechcraft.com/supply_chain/contractual_flowdown/
“True” RCCA Training Class
Form 78-35140: Issue Closure Plan (ICP) Assignee Company PCD
ECD Status
As key as the
Problem Statement
The ICP is the central hub for attached documents and the full project record 08/17/10
07/13/10
Form 78-35140: Issue Closure Plan (ICP)
Significance to Production/Delivery:
No Impact
Significance to Field:
No Impact
(3) Interim
1. Determine suspect lot:
Containment:
2. Stock:
3. WIP:
3. Interim Containment
– This is not part of the True RC training class focus – assumes that if the problem is a
new emerging issue that containment/ remedial action are accomplished in parallel
and recorded in the ICP
07/13/10
“True” RCCA Training Class
Reference the 8-D steps:
4. Find the Root Cause
– 4.1 Brainstorm the potential root causes and the escape point
• Identify what you “know” (supported by data) versus “opinion” but capture/ record/
and explore everything.
07/13/10
“True” RCCA Training Class
• Everyone participates, Repeat until no one can think of another “why” to ask
– Don’t jump to conclusions too quickly – this causes the process to stop too soon
» Think intensely and at multiple levels (ref: the causal chain)
» “Peel the onion” – professionally and unemotionally challenge the basis
» Permit no pride of authorship within the team
» Note: most people can only support 1-2 layers of questions with their basis for
root cause or a corrective action
– Success test – eventually can’t tell who on the team came up with the original idea
or the full string of the idea
» Note: Individuals can’t be perfect but teams can
07/13/10
“True” RCCA Training Class
4. Find the Root Cause – (Cont’d)
07/13/10
“True” RCCA Training Class
Generator main (System Operation Branch Example)
Fault Tree Example contacts remain
closed
07/13/10
“True” RCCA Training Class
07/13/10
“True” RCCA Training class
Design FMEA
Potential
Item/Design S O Current D R Responsibility &
Design Potential Failure Potential Effect(s) of Cause(s) / Recommended Actions
Identifier Function/ e c Design/Process e P Comments / Notes Target
Characteristic Mode Failure Mechanism(s) of Actions Taken
Requirements v c Controls t N Completion Date
Failure
Soft surface
Dimensional
2.2.3 Surface Plating Sealing Surface scores & flakes Leakage 5 Plating too thick 8 8 320
Inspection
easily
High RPNs require more
Mfg and QA controls
Process FMEA
Potential
Item/Process S O Current D R Responsibility &
Process Potential Failure Potential Effect(s) of Cause(s) / Recommended Actions
Identifier Function/ e c Design/Process e P Comments / Notes Target
Characteristic Mode Failure Mechanism(s) of Actions Taken
Requirements v c Controls t N Completion Date
Failure
Non-homogenius
Seal physical Local thinning, Inspection at the
3.2.1 Elongation Leak path thru the seal 5 material 1 3 15
charecteristics microcracks supplier
composition
Shelf life Seal dried out, brittle- may Poor inventory Cure date label on
4.2.2 Seal storage Shelf life 5 1 3 15
exceeded crack mgmt (FIFO) seal bag
08/24/10
“True” RCCA Training Class
Example RPN scoring values
Ranking Severity
1 No effect
Ranking Detection/Prevention
5 Will not prevent failure mode from happening but will detect it with notification
10 No controls in place
07/13/10
“True” RCCA Training Class
Example RPN scoring values
Possible Failure
Ranking Probability of Failure Occurrence
Rates
5 1 in 400 Moderate: Occasional Failures Happens rarely and may cause FM / effect sometimes
07/13/10
“True” RCCA Training Class
• Review the LAI/ FAI and re-qualification process and reports for change of source or
manufacturing location
• Construct a sub tier supplier map
– Recent interview results, recommendations
– Audit reports and findings
– Turnover rate, business level changes
– Training and certifications compliance controls
07/13/10
“True” RCCA Training Class
4. Find the Root Cause - (Cont’d)
07/13/10
“True” RCCA Training Class
Generator main
07/13/10
Root Cause Verification Action Plan
PCD (Promised Completion Date)
Root Cause Verification Action Plan: "Generator main contacts remain closed" VAP
Fault Tree Status:
Fault Tree Sub- Fault Tree Sub- Fault Tree Sub- Fault Tree Sub- Verification Action/ Potential RC
Locator Fault Tree Element RPN Root Cause Theory Statement Assigned to: ECD A = Active C Results
element element element element Task Description = Complete Conclusion
Number
No
1.1.2 FOE
Contacts welded
1.2 closed
Maybe
1.2.1 Overcurrent
Yes
1.2.1.3.1 Commands to relays
1.2.2 Magnitesed
2.0 Commanded close (A new sheet typically started for each major fault tree element)
08/24/10
Root Cause Verification Action Plan
Root Cause Verification Action Plan: "Generator main contacts remain closed"
Fault Tree
Fault Tree Sub- Fault Tree Sub- Fault Tree Sub- Fault Tree Sub-
Locator Fault Tree Element RPN
element element element element
Number
Spar Capproblems
1.0 Physical fractured
1.1 Developedstuck
Physically crack
return
Any level could be the
Damaged during
1.1.1 spring
transportation root cause
Handling procedures
1.1.2 FOE not followed
New employees
1.1.3 Damaged parts not trained
PCD
VAP
Status:
Verification Action/ Potential RC
Root Cause Theory Statement Assigned to: ECD A = Active C Results
Task Description = Complete Conclusion
No
08/24/10
“True” RCCA Training Class
4.3 Set up the “Verification Action Plan (VAP)” – (cont’d)
- Separate section/ sheet of the spreadsheet for each fault tree major element may be needed
- Determines what verification action required to dismiss or confirm every potential RC at each level
• Verification = proving beforehand that the planned action will do what is intended
- Ex.) analysis, tests/ trials (objective evidence), comparisons with similar activities utilizing a subject
matter expert (SME)
- Without a completed verification action the potential RC can’t be eliminated based on available data
• Validation = after CA implementation, checking that the action is achieving it’s goal and
without adding a new problem (proof that the change has worked)
– A minimum of three relevant people to commit they concur the “True” RC is correct,
comprehensive in terms of multiple levels of contributing causes, and the escape point is clear
• Reference them in the ICP for future info (willingly held accountable)
• Should also include the champion
07/13/10
“True” RCCA Training Class
– A minimum of three relevant people to commit they concur the CA plan is correct and
comprehensive in terms of appropriate action assigned to all levels of contributing cause
• Reference them in the ICP for future info (willingly held accountable)
• Should also include the champion
07/13/10
“True” RCCA Training Class
Reference the 8-D steps:
7. Preventative Action (PA) plan definition and implementation
1. Systemic analysis – “where else” or “what else” could be impacted by this problem and RC?
• Think both other products and processes- assure they take action
3. What potential unintended effects could occur from implementing the CA?
• This requires repeat of the brainstorm process and a check of the lessons learned database
for applicability
• What will be the verification action to assure they’re avoided
4. Mistake proofing: ex. physical/ mechanical controls on tooling (see Juran training material)
07/13/10
“True” RCCA Training Class
– Typically status ICP as closed once CA and PA closure plan accepted and
implemented
• Update the ICP once the validation step is complete (Leaders responsibility)
– Assured lessons learned are recorded and shared across the organization for
continuous improvement
07/13/10