Ramesh Kaka na Plot nu nala nu kam

BBS
S.R.NO DESCRIPTION NO. NO. NO. LENGTH 8 mm
1 0.17 C/C long Span Jali 1 2 5 5.7 57
2 0.20 C/C Short Span Jali 1 2 26 1.1 57.2
3 Pardi Main-Steel 1 2 52 2.1 218.4
4 Pardi Long Span Steel 1 2 14 5.5 154
7 Slab Steel Long Span 1 2 14 5.5 154
8 Bottom Steel Short Span 1 1 26 2.8 84
9 Top Steel Short Span 1 1 26 2.8 72.8
Total 797.4
Total Weight 281.51
Plaster Work upto Plint level in Shed
SR NO. DESCRIPTION NO. NO. LENGTH WIDTH HEIGHT QUANTITY Total Qty
1 Nala Excavation 2 6 1.3 1.5 23.4 23.4

2 Nala P.C.C 2 6 1.1 0.1 1.32 1.32

3 Foundation R.C.C 2 5.8 1 0.23 2.67


R.C.C Pardi 2 5.6 1.25 0.23 3.22
Old Drain R.C.C Pardi 2 5.6 0.35 0.15 0.59
R.C.C Slab 1 5.6 2.86 0.2 3.20 9.68

4 Plaster G.L To Plinth 2 30 1.2 72


2 15 1.2 36 108

5 Centering For Nala


R.C.C Pardi 2 2 1.25 5.6 28
Old Nala Pardi 2 2 0.35 5.6 7.84
Slab 1 2.8 5.6 15.68 51.52
Abstract Sheet
SR NO. DESCRIPTION UNIT QTY RATE AMOUNT
1 Nala Excavation CUM 23.4 175 4095.0
2 Nala P.C.C CUM 1.32 4000 5280.0
3 Nala R.C.C All CUM 9.68 5500 53240.0
4 Centering Nala SMT 51.52 240 12364.8
5 Steel Nala KG 281.51 55 15483.1
6 Plaster G.L TO Plinth SMT 108 200 21600.0
Total 112062.85