Professional Documents
Culture Documents
Water Supply PDF
Water Supply PDF
SCHOOL OF ENGINEERING
DEPARTMENT OF CIVIL AND ENVIRONMENTAL ENGINEERING
BY
J. M. TEMBO
AUGUST 2011
COVERED
With the realisation that the water sources had to be protected from pollution, sanitation methods on
how best waste could be handled developed. Initially, on-site methods were devised. However, with
the increase in population, off-site sanitation methods were devised to deal with the issue of waste.
In our approach to understanding water supply systems, we will try to follow through the above step.
However, the genesis of any water supply system is computation of water demand (amount of water
required). We will therefore start with this before we go through the five steps of a water supply
system.
2.3.1 DOMESTIC: - Water supplied to a city/community for sanitary uses, drinking washing bathing
etc.
1
2.3.2 COMMERCIAL AND INDUSTRIAL:- Water supplied to commercial and industrial plants. In
projects, it is always important to know whether the industries will have independent supply
systems.
2.3.3 PUBLIC:- Water that is supplied to public places like schools, hospitals, prisons and water for
fire fighting.
2.3.4 LOSS AND WASTE:- (unaccounted for water) This is water that goes to service the leaks and
illegal connections in the system. When designing a system, this water is to be catered for if
supply is to be adequate.
Where
Qa = Average water demand
d = Population density
A = Area of the distribution
C = Coverage of the area (i.e. 50% of the area) Thus it is a factor that converts
number of inhabitants into number of consumers.
q = Consumption per capita (varies from place to place for Zambian conditions, refer to
Zambia standard)
qa = average consumption per unit area
Where the demand is to be computed for an area (e.g. town) with different consumption figures
then
n
Qa = A∑ qa piCi
i =1
n
or Qa = A∑ d i qi piCi
i =1
Where
Qa = Average consumption of the town
A = Area of the town
qa = Average consumption per unit area
n = Consumption categories in the district
qi = Unit consumption per category i
pi = percentage of district territory occupied by category i
Ci = Coverage within district territory occupied by category i
di = population density within the district i
However, in estimating the average demand of an area, apart from determination of the number of
people to be served and estimation of per capita consumption, other factors (e.g. provision for fire
fighting, industries etc) should also be considered.
2
2.5 WATER DEMAND PATTERNS
Each demand category cannot be considered only from the perspective of the average of the amounts
needed but also with respect to maximum delivery required within a specific interval of time.
time
Example:
If consumption at 06-07hours is 40m3 and the average consumption is 20m3, the peak factor will then
be 40/20 = 2
Meaning: - at this hour, supply has to be twice the average value to meet the demand. It should be
noted that in design, it is the extreme values that are important and not the average!
Where domestic water demand is considered, it will be noticed that as the population increases, the
peak factor reduces. The curve that results is called a SIMULTANEITY CURVE.
3
Peak
factor
Population
Qd = Qa/(1-L/100)
EXAMPLE:
A community's average daily water demand is 200m3. If losses and wastage is estimated at 30%, how
much water should be pumped into the system (water delivery)to satisfy the demand?
Solution
Qd = Qa /(1-L/100)
= 200/(1-0.3)
= 285.71m3.
To take care of the variations in water demand, the design will be based on maximum hourly demand
for maximum daily demand for maximum monthly demand. The peak factor in this case will be the
overall of peak factors calculated simply by multiply all the peak factors. Thus
Where pfo is the overall peak factor given as pfo = pfh * pfd * pfm
4
2.7 FACTORS AFFECTING CONSUMPTION (DEMAND)
- Size of the city
- Characteristic of the population
- Presence of industries
- Quality of the water
- Cost
- Pressure in the system
- Climate
- Cultural background of the community
- Whether supplies are metered
- Effectiveness of the water works administration.
2.7.5 METERING
Where there are no services meters, (customers being on flat rates) there is carelessness leading to high
consumption figures.
The Engineer should always have the knowledge of the city for which the project is being designed
(i.e. is it expanding industrially? Population? And if so, at what rate.
Several assessments must be taken into account whilst estimation for future demand are being made.
They can be classified into the following groups:-
a) Projections of total consumption based on historical growth trends
b) Projections based on per capita consumption and population growth trends for domestic
category
c) Forecast based on assessment of growth trends of other main consumer categories (Industry,
Commercial)
d) Forecast based on developmental plans and programs.
5
Two models commonly used in calculation of demand trends are: -
a) Linear model
a
Qi + n = Qi * (1 + n * )
100
b) Exponential model
a n
Qi + n = Qi * (1 + )
100
Where
Qi = Water demand at year "i"
Qi+1 = forecasted water demand after n years
n = design period
a = average annual growth rate during the design period
SELECTION OF a AND n
The average annual growth rate can easily be obtained from statistical data. However, as to what value
of n is used, a lot of factors have to be considered some of which are:-
1. Useful life-span of component structures and equipment
2. Easy or difficulty of extensions
3. Anticipated population growth
4. Economy at time of designing (interest rates)
5. Anticipated industrial potential of the area etc
6
Due to operational problems in developing countries, it is always import to go for safe sources. Only
as a last resort should sources that require chemical treatment be developed.
The first two exert the greatest influence on process selection. On local constraints one must evaluate
- limitations of capital
- availability of skilled and unskilled manpower
- availability of major equipment items , construction materials and water treatment chemicals
- applicability of local codes demanding water standards and specifications for materials
- influence of local traditions, customs and cultural standards
- influence of national sanitation and pollution policies
The raw water so abstracted should meet a certain quality for the intended purpose after treatment.
Mostly, it is the chemical and bacteriological parameters that matter most in selecting whether a water
source can be developed or not. This is because physical parameters are easily removed by the
available treatment methods. Examples of physical parameters are turbidity, suspended solids; etc.
7
4.0 URBAN DISTRIBUTION NETWORKS
Under this topic, we will discuss transport, storage and networks.
The water transport and distribution networks deliver water from the treatment or production facilities
to the user.
Continuity equation
Q = VA = V1A1 = V2A2
Meaning the discharge is calculated by multiplying the cross sectional area of the pipe and the velocity
of the fluid. The maximum velocity in the pipe should not go above 2.6m/s.
Graphically
V12/2g
P 1 / rg Hf
V22/2g
P 2 / rg
Z1 Z2
Reference:
L
8
Definition of the terms
Elevation Head:
An amount of flow potential energy in one cross section defined by its elevation.
Pressure Head:
An amount of flow potential energy in one cross section defined by the water pressure.
Velocity Head:
An amount of flow kinetic energy in one cross section defined by the water velocity.
Energy Head:
This is the total energy of the system.
When written to incorporate frictional losses, minor losses, energy input (e.g. from pumps) and losses
from other type of work done, the Bernoulli equation becomes the energy equation and can be
rewritten as:
Also take the pressure at the inlet to be atmospheric so that P1 = 0 and assume the only losses in the
system are those due to friction. Take the difference in elevation between the two ends is 15m with the
source being lower than the other end.
9
4.3 STORAGE
Water can be provided to a distribution area by means of direct pumping and/or by properly elevated
water storage.
Clear water storage facilities are normally part of any sizable water supply system. They can be
located at the treatment plant, at the end of the distribution system or at any suitable place in the
distribution system. They serve two general purposes:
1. Meeting variations in water demand
2. Providing a reserve supply in case of emergence.
In case there is no storage, the flow in the trunk main should follow the demand patterns. This would
entail having bigger pipes to accommodate huge flows in times of higher demand. Secondly, the
pumping regime would then have to follow the demand patterns, which is technically demanding. (in
this case, variable speed pumps have to be used, a technology that would be very expensive for
developing countries). Without storage, the flow in the treatment facilities would also need to vary
according to demand. This would also lead to big treatment units which would not economical.
With storage reservoirs, the pipe size need to be big enough to only convey the maximum average
demand (pumping by fixed speed pumps). When demand is higher, the difference would be supplied
from the storage which would be filling in times of low demand.
1.6
1.5
1.4
1.3
1.2
Peak Factor
1.1
1
0.9
0.8
0.7
0.6
0.5
0.4
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
10
T (h)
Solution
Average demand for the district = 190m3/h
With 35% leakages, the amount to be delivered to satisfy demand will be = 190m3/h/(1-0.35) =
292.31m3/h. We compute the table below. Where deliverly is more than consumption, there will be
accumulation and vice versa.
The reservoir has to accommodate maximum accumulated volume (i.e at 6 = 634.31 as well as the
maximum deficit at 23hours = 87.69m3
Normally, in practice, some reserve has to be added. If Three hour reserve is to be added to our tank,
then tank volume will be V=722+3*292.31 = 1598.923 = 1600m3
11
4.4 WATER DISTRIBUTION NETWORKS
A water distribution network can be defined as a network of pipes that convey water to the consumer.
Pipes in the system can be classified according to the purpose they serve as follows:-
a) TRUNK MAIN:
This is a pipe for the transport of the water from the water treatment plant to the distribution area.
Common sizes are in the range of 250 to 1500mm; size depending on size of area to be served.
Branching is possible but connection of customers on this line is extremely rare!
b) SECONDARY MAIN:
These are pipes providing the basic structure of the distribution networks. They are used to link the
main distribution pipes with the service reservoirs or/and with the trunk distribution mains. A number
of direct connections can be made especially for large consumers. Common diameters are between 150
and 400 mm.
c) DISTRIBUTION MAIN:
Distribution mains carry water from the secondary mains to the smaller consumers. Theses are usually
laid along the roads and streets. Size are usually between 80 and 150mm.
d) SERVICE PIPE:
This is the pipe bringing water from the distribution main to the consumer/customer. For domestic
consumers, the service pipe is usually less than 25mm in diameter.
a) SERIAL NETWORK
This is a network without branches or loops. It generally has only one source, one dead end and a
couple or more demand points (called demand nodes). All the nodes are linked by two pipes; a supply
link upstream and a distribution link downstream. Flow is in one direction; from supply point. Design
is based on principles single pipe calculations.
12
b) BRANCHED
This is a network with one supply source and several (dead) ends. The intermediate nodes in the
system in are connected by one supply link upstream and one or more distribution links downstream.
d) COMBINED NETWORK
This is a network where the central part is looped while the supply of localities or outskirts is either
serial or branched. This is the most common type.
13
Disadvantages are:
- they need a lot of electric energy
- operation and maintenance is complex
- high maintenance costs
- the system is prune to pressure surges
1) STAND PIPE
This is the lowest level of service and mostly common to peri-urban areas. It consists of a tap (stand
pipe) serving a number of households in a community. Consumption is low due to distance.
2) YARD CONNECTIONS
This is a service level where a tap is provided in the yard of each house.
14
SOCIAL-ECONOMICAL CRITERIA
a) Political decisions which are usually the most import "in the beginning there has to be a
political vision to have a distribution network)
b) Planning phase
- Is the project feasible?
- What is the best approach?
- What are the estimated costs?
- What is the required time for execution?
c) Economic aspects
- What are the interest rates
- What is the inflation rate?
- What are the energy prices?
1) PRESSURE CRITERION
Pressure in the system should be adequate. Generally a minimum pressure of 5-6mwc above the
highest tap in the system is adequate. This translates to about 15 - 25mwc above the street level if we
take into consideration head losses that will result through connections and valves.
Very high pressures are not desirable as high grade pressure resistant pipes would have to be used
which would be very expensive. Secondly, leakages are direct proportional to pressure. (thus in
systems like ours, minimum pressure possible should be maintained to reduce on leakages). Generally,
the pressure should never be above 60 - 70mwc.
2) VELOCITY CRITERION
Very high velocities are undesirable as they induce Head loss. Velocities should be restricted to a
maximum of 1.5m/s. Very low velocities are also undesirable for hygienic reasons (long retention
times in the system).
15
BASIC DESIGN PROCEDURE
Initially, the known data are the locations and quantities of supply and demand points in the
distribution area (allocation of demand to a node) taking into consideration local population densities,
coverage, existence of different demand categories, concentration of demand due to large consumers,
etc). With this information the definition of the main route can be done (need to decide on the
configuration)
After the network is spread over the area, pipe sizing and analysis of hydraulic behaviour is next. This
is usually achieved through the use of computer models
16