You are on page 1of 5

Technical Note

Managing the Cost of Power Transmission Projects:


Lessons Learned
Hani M. Gharaibeh, Ph.D. 1
Downloaded from ascelibrary.org by Universidad Peruana De Ciencias Aplicadas on 12/10/19. Copyright ASCE. For personal use only; all rights reserved.

Abstract: A major driver to project success is the ability to manage the project cost effectively. Despite the agreement among scholars and
practitioners on the importance of managing the project cost, excessive cost overruns continue to occur on major power transmission projects.
In this paper, the author, through a Delphi method, will discover problems of managing the project cost, suggest solutions to
overcome these problems, and identify lessons learned from these projects. The study was conducted with two different project teams
in the same organization in Canada. Key findings from this study will highlight similarities and differences between the two cases in terms
of how each team managed the project cost and learned from it. The paper will contribute to the body of knowledge by identifying lessons
learned from power transmission projects on how to manage the project cost and by suggesting solutions to overcome the problem of cost
overrun in these projects. DOI: 10.1061/(ASCE)CO.1943-7862.0000665. © 2013 American Society of Civil Engineers.
CE Database subject headings: Construction costs; Electric transmission structures; Electric transmission lines; Construction
management.
Author keywords: Cost overrun; Cost control; Lessons learned; Underestimation; Power utility.

Introduction studies with two different project teams involved in two major
transmission projects in western Canada. The purpose of this study
Project cost control is a cornerstone of successful delivery for any was to understand problems and challenges faced by project teams
project, yet we continue to see problems of cost overrun in a variety in controlling costs, suggest solutions to overcome these problems,
of projects across the world and in several industries including and identify lessons learned.
oil and gas, telecommunication, manufacturing, and information
technology, among several other industries. Among the industries
that gained considerable attention during the past few years is the
Methodology
power utility industry.
High-voltage power transmission projects are gaining a lot of In this research, a Delphi method was used. The Delphi method is
attention in Canada due to their significance to the public and an iterative process used to collect and distill the judgments of
the urgent need to upgrade the transmission grid across several experts using a series of questionnaires incorporating feedback
Canadian provinces to cope with the huge expansion in residential from previous rounds of questions. The questionnaires are designed
and industrial infrastructure. The Canadian transmission system is to focus on problems, opportunities, solutions, or forecasts. Each
old, congested, and inefficient. The upgrading of existing transmis-
subsequent questionnaire is developed based on the results of
sion facilitates in Canada for the last 25 years was insufficient and
the previous questionnaire. The process stops when the research
resulted in the overloading of the national grid. As a result, the
question is answered, when consensus is reached, when theoretical
transmission system in Canada needs massive upgrade and expan-
saturation is achieved, or when sufficient information has been
sion (Alberta Economic Development Authority 2004). Although
exchanged. Gustafson et al. (1973), Skulmoski et al. (2007), and
there is a strong belief in the urgent need to execute power trans-
mission projects, the question of how much it costs is a growing Rowe and Wright (1999).
concern for transmission facility owners (TFOs), industry regula- Before starting the Delphi study, the author collected internal
tors, and the public unions. As a result, the utility regulators and documents, polices, and procedures applied by the company to
TFOs are putting enormous pressure on all project stakeholders to understand the current process of cost management within the
control the costs. organization. The analysis of these documents highlighted the
To understand the problems and challenges associated with con- problem of cost overruns and the lack of cost management on each
trolling the cost of transmission projects and the lessons learned on project, which was attributed to such reasons as poor estimates,
how to control the project costs, the author conducted two Delphi design errors and rework, poor productivity, and unclear scope
of work. For further details on this, the reader is encouraged to
see Gharaibeh and Cow Falls (2011).
A sample of each project team was selected to represent various
1
Managing Director, PMPC Consulting Inc., 47 Citadel Hills Green, project departments involved in the project including people from
NW, Calgary, AB T3G 4J6, Canada. E-mail: hani@pmpc-inc.com engineering, procurement, construction, and project control and
Note. This manuscript was submitted on November 2, 2012; approved
on December 10, 2012; published online on December 12, 2012. Discus-
project management. Team members were contacted and asked
sion period open until January 1, 2014; separate discussions must be sub- to participate in this study. Fifteen people agreed to participate
mitted for individual papers. This technical note is part of the Journal of in the Delphi study for project A and 12, for project B.
Construction Engineering and Management, Vol. 139, No. 8, August 1, The following key issues were investigated in the three-round
2013. © ASCE, ISSN 0733-9364/(5)/$25.00. Delphi study:

JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT © ASCE / AUGUST 2013 / 1063

J. Constr. Eng. Manage., 2013, 139(8): 1063-1067


• Problems and challenges that prevented the project team from Discussion and Analysis
controlling the project cost and resulted in exceeding the project
budget; Having completed the two cases and conducted the analysis, the
• Solutions and recommended actions that should be adopted by following were noted with regard to the main three questions con-
the project team to be able to control the project cost and mini- sidered in the Delphi study:
mize variances to the project budget;
• Lessons learned from the project that should be implemented in
Problems of Controlling the Project Cost
future projects to help in managing the project cost.
To deal with the issue of bias in the data collection process, the In terms of similarities between the two projects; six problems were
author adopted the following key steps: (1) The sample was care- identified that were similar across the two cases; however, they had
fully selected from a variety of people with diversified skills from different ranking numbers for each case. Moreover, in all cases the
Downloaded from ascelibrary.org by Universidad Peruana De Ciencias Aplicadas on 12/10/19. Copyright ASCE. For personal use only; all rights reserved.

different departments within the organization (i.e., engineering pro- first problem in terms of managing project costs was “high em-
curement, construction, project controls and project management); ployee turnover.” In addition, project team members in both cases
therefore, the feedback reflected variety of opinions and perspec- agreed with close ranking number (5 and 6) that continuous design
tives on any certain point. (2) The author validated the results from changes in the late engineering phase were a major problem in con-
one case (i.e., one project team) with the opinions and data col- trolling project costs.
lected from another case (different project team) to compare simi- By looking across the organization, we can easily notice that
larities and differences in the responses. (3) The author used high employee turnover is a corporate challenge regardless of
triangulation by validating the results of the Delphi study against the project. The turnover rate in this organization was noticeably
other methods used in the research study such as case studies and higher than other organizations, with at least one or two persons
focus groups. leaving the company each week at the time the study was con-
The first round of the Delphi study used a fully unstructured ducted. The high turnover has a severe impact on the productivity
format to try to collect answers on the preceding issues. Responses of the organization as new employees joining the project will need
were collected, and all problems, solutions, and lessons learned sufficient time to understand the project and most often end up
were summarized and grouped into certain categories based on learning by themselves as the systems and processes are not adap-
certain identified themes (e.g., estimate, scope, schedule, people, tive to learning, which ultimately results in hours billed to the client
process). The second round presented the results obtained from with very low earned value to them. This represented additional
the first round to the team with the aim to rank the items identified cost to the project.
according to the degree of importance and relevance based on each In terms of differences between cases, the following two prob-
participant’s own judgment and expert opinion. Participants were lems were ranked as significantly less important in affecting the
given the chance to comment on the items identified, eliminate final costs of the project by project team B as opposed to project
any of the items, or add new items that were not originally listed. team A. Those problems were the heavy regulations of the industry
The result of round one identified 30 problems, 25 solutions, and and the unclear scope of work. These two problems were ranked: 2
20 lessons learned. and 4, respectively, in case A and 6 and 10, respectively, in case B.
All responses from round two were collected, and a score was This could be explained by fact that project A is more complex in
calculated for each item based on the unique ranking numbers as- scope when compared with project B.
signed by each participant. The ranking number was a number from Tables 1 and 2 demonstrate how project teams A and B rank
1 to 10 with 1 being the most important and 10 being the least im- these problems.
portant item. An average score was then calculated for each of the
problems, solutions, and lessons learned identified by the project
team to represent the group ranking of all project team members. Solutions to Control the Project Cost
The average score was calculated by adding up the individual In terms of similarities between the two projects, the following
scores (ranking numbers) from each participants and dividing this solutions were seen as almost equally important in both projects
by the total number of participants. The top 10 problems, top 10 A and B: a clear understanding of the scope of work, documenta-
solutions, and top 10 lessons learned were selected for the third tion of assumptions in the scope of work and estimates, alignment
round of the Delphi study. with key project stakeholders, and staff retention. The ranking
In round three the team was asked to assign a percentage/weight numbers were 1, 5, 7 and 9, respectively, for project A and 3,
to represents the degree to which each respondent agrees/disagrees 4, 9 and 10, respectively, for project B. The first two solutions
with the group ranking identified by the project team for each item. are scope related and therefore important to both projects, as man-
The higher the percentage, the more the participant is in agreement aging the scope of work is essential for controlling project costs.
with the statement indicated. All responses were then gathered The third problem is industry related and therefore would impact
and analyzed collectively. An average weight was calculated by any project in this industry. The fourth problem is corporate related
adding all the individual weights assigned by each participant and has a severe impact on all projects across the organization.
and dividing by the total number of participants. Because the rank- In terms of differences between the two projects: the following
ing number was assigned in ascending order (i.e., the lower the solution was seen as more important by project team A compared
number, the more important the item, whereas the higher the per- with project team B: site visits by estimators. This is explained by
centage, the more important the weight of this item), it was neces- the fact that project A suffered from a poorly done estimate more
sary to reverse the ranking numbers so that 10 is the most important than project B, and it was seen as beneficial for the estimator to visit
item and 1 is the least important item. This reverse rank was the site prior to putting together the estimates. Other solutions iden-
necessary to achieve before multiplying the reversed score by the tified by project A are the role of the project control group in
average weight to reach a weighted score. The final step was to the preparation of the estimate and spending more time to create
rerank the items and assign a revised ranking number based on realistic estimates. This was more a topic of focus by project team
the highest weighted score ranked No.1 and the lowest weighted A as there was a greater concern to develop accurate estimates at an
score ranked No. 10. early phase of the project. Tables 3 and 4 highlight the solutions

1064 / JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT © ASCE / AUGUST 2013

J. Constr. Eng. Manage., 2013, 139(8): 1063-1067


Table 1. Top 10 Most Important Problems in Managing Project Cost (Project A)
Group Reversed Average Weighted Revised
rank Problems score weight score rank
1 High employee turnover rate especially in engineering and procurement 10 74 736 1
2 Restrictions imposed by heavily regulated industry beyond the control of the project team 9 80 720 2
3 Shortage of staff in general and senior staff in particular 8 75 600 3
4 Original scope of work not sufficiently detailed by the client to fully define the work required 7 74 520 4
5 Changing key project players and senior team members in the middle of the project 6 67 403 5
6 Continuous design changes in the late detailed engineering phase leading to cost variances 5 76 379 6
7 Inaccurate initial estimate (i.e., missing items, underestimation of other items) 4 66 263 7
8 Submission by subcontractors of inflated bid prices that do not reflect true costs 3 61 184 8
Downloaded from ascelibrary.org by Universidad Peruana De Ciencias Aplicadas on 12/10/19. Copyright ASCE. For personal use only; all rights reserved.

9 Changes made by the regulator to the requirements of the project during the execution phase 2 80 160 9
10 Overly optimistic in terms of achieving key schedule milestones (i.e., permits and license, 1 64 64 10
equipment delivery dates, in service date)

Table 2. Top 10 Most Important Problems in Managing Project Cost (Project B)


Group Average Reversed Weighted Revised
rank Problems weight score score rank
1 High employee turnover rate, especially in engineering and procurement 86 10 858 1
2 Misunderstanding/wrong interpretation of the scope of work by the contractor 69 9 618 3
3 Changing key project players and senior team members in the middle of the project 83 8 667 2
4 Overly optimistic in terms of achieving key schedule milestones (i.e., permits and license, 83 7 578 4
equipment delivery dates, in service date)
5 Poor procurement practices (i.e., too many purchase orders to buy small value items, zero dollar 70 6 420 5
purchase orders)
6 Restrictions imposed by heavily regulated industry beyond the control of the project team 76 5 379 6
(i.e., permits and license, landowner issues, environmental issues, hearing process)
7 Continuous design changes in the late detailed engineering phase leading to cost variance 69 4 277 7
8 Poorly defined scope of work for subcontractors/suppliers 59 3 178 8
9 Lack of contingency and escalation for material and construction labor costs in the initial estimate 50 2 100 9
10 Original scope of project not sufficiently detailed by the client to fully define the work required 65 1 65 10

Table 3. Top 10 Most Important Solutions for Managing Project Cost (Project A)
Group Reversed Average Weighted Revised
rank Solutions score weight score rank
1 Obtain clear understanding of scope of work and client requirements upfront 10 94 940 1
2 Heavily involve engineering and project controls during the process of estimation 9 81 733 2
3 Spend sufficient time detailing and clarifying subcontractor’s scope of work to ensure it 8 76 611 3
captures all work required
4 Attach a sufficiently detailed estimate assumptions document with each estimate produced 7 69 485 5
5 Spend more time on creating realistic estimates based on sound conceptual design 6 81 488 4
6 Communicate budget information to lead engineers, project managers, and key project 5 66 332 6
members once the estimate is approved
7 Require that estimators visit project sites before developing the estimate 4 56 226 8
8 Establish better alignment with key project stakeholders 3 74 221 7
9 Work on staff retention to accumulate knowledge gained through experience 2 70 140 9
10 Establish better integration between various departments 1 61 61 10

proposed by each project team to deal with the problem of cost learned regarding continuous design change was a client-related
overrun. issue that was obvious on both projects. This was because the
client was the same on both projects. The second lesson learned
with regard to employee turnover is an organizational challenge
Lessons Learned to Control the Project Cost that applies to all projects. The third and fourth lessons learned
Due to similarities between the two projects, the following les- were process-related lessons that had to do with internal com-
sons were ranked as equally important by the two project teams: pany procedures and policies that affected both projects. These
continuous design changes lead to engineering redesign, high lessons were similar between the two projects because they were
employee turnover rate results in lower productivity, develop es- both conducted in the same organization; therefore, all the
timates consistently with quantity-tracking concept, and absence organizational issues were applicable to both projects to a certain
of on-site storage yard leads to lost or stolen materials. Project A extent.
ranked those lessons at 1, 2, 6, and 7, respectively, and project B In terms of differences between the two projects, the follow-
ranked them at 1, 3, 6, and 7, respectively. The first lesson ing lessons learned were different in terms of ranking: Provide

JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT © ASCE / AUGUST 2013 / 1065

J. Constr. Eng. Manage., 2013, 139(8): 1063-1067


Table 4. Top 10 Most Important Solutions in Managing Project Cost (Project B)
Group Average Reversed Weighted Revised
rank Solutions weight score score rank
1 Spend sufficient time detailing and clarifying subcontractor’s scope of work to ensure it captures 18 10 183 2
all work needed
2 Obtain clear understanding of scope of work and client requirements upfront 13 9 120 3
3 Attach a sufficiently detailed estimate assumptions document with each estimate produced 12 8 93 4
4 Communicate budget information to lead engineers, project managers, and key project members 27 7 187 1
once the estimate is approved
5 Develop better communication between disciplines, departments, and project teams 10 6 60 7
6 Commit members to the team (do not move them between projects before completion of project) 10 5 50 8
Downloaded from ascelibrary.org by Universidad Peruana De Ciencias Aplicadas on 12/10/19. Copyright ASCE. For personal use only; all rights reserved.

7 Require that estimators visits project sites before developing the estimate 21 4 83 5
8 Establish better integration between various departments (i.e., engineering, procurement, 22 3 65 6
construction)
9 Work on staff retention to accumulate knowledge gained through experience 12 2 23 10
10 Establish better alignment with key project stakeholders 25 1 25 9

sufficient training and mentorship was ranked at 3 in project A and optimistic schedules and estimates lead to cost variances. This was
8 in project B. This was due to the sophisticated scope of work ranked at 4 by project team B and 8 by project team A. This
and complexity of project A, which required special training was explained by the significant impact of the regulatory process
and constant mentoring of new team members to be able to learn in the delivery of project B as there were major delays in obtaining
quickly. In project B the scope of work was less complex, and the permits and license for construction and meeting construction dates
project suffered from continuous delays, so there was sufficient and project completion date. Tables 5 and 6 highlight the lessons
time for training and mentorship. The second lesson was that learned in controlling project costs on each project.

Table 5. Top 10 Most Important Lessons Learned in Managing Project Cost (Project A)
Group Reversed Average Weighted Revised
rank Lessons learned score weight score rank
1 Continuous changes in project objectives, scope, and client requirement lead to engineering redesign. 10 24 243 1
2 High employee turnover rate results in lower productivity in the project and leads to additional cost. 9 26 231 2
3 Provide sufficient training and mentorship to new members joining the project team to increase their 8 27 217 3
productivity
4 Clearly define lines of accountability for each project team member 7 26 180 4
5 Develop estimates consistently with quantity-tracking concept, project execution plan, and scope 6 20 120 6
of work
6 Streamline the process of preparing issued for construction drawings (IFC) packages so it arrives on 5 26 129 5
site in a timely manner
7 Absence of a centralized storage yard on site leads to material being lost or stolen from the project. 4 23 91 7
8 Optimistic schedules and estimates lead to significant cost variance as they do not take into account 3 24 73 8
various factors that could affect the project
9 Regulatory process imposes restrictions that will result in project schedule delays and additional costs 2 21 43 9
incurred
10 Applying quantity-tracking concept helps to monitor changes of material and construction labor 1 26 26 10
quantities

Table 6. Top 10 Most Important Lessons Learned in Managing Project Cost (Project B)
Group Average Reversed Weighted Revised
rank Lessons learned weight score score rank
1 Continuous changes in project objectives, scope, and client requirements lead to engineering redesign 89 10 892 1
2 High employee turnover rate results in lower productivity in the project and leads to additional cost 90 9 810 3
3 Always review engineering man-hour estimates to make sure they reflect actual project scope before 83 8 660 2
estimate is approved
4 Optimistic schedules and estimates lead to significant cost variance as they do not take into account 87 7 607 4
various factors that could affect the project
5 Regulatory process imposes restrictions that will result in project schedule delays and additional costs 88 6 525 5
incurred
6 Absence of a centralized storage yard on site leads to material being lost or stolen from the project 63 5 313 7
7 Develop estimates consistently with quantity-tracking concept, project execution plan, and design bias 79 4 317 6
memorandum
8 Provide sufficient training and mentorship to new members joining the project team to increase their 83 3 250 8
productivity
9 Applying quantity-tracking concept helps to monitor changes of material and construction labor 81 2 162 9
quantities
10 Remove barriers between client and contractor to work as one project team 67 1 67 10

1066 / JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT © ASCE / AUGUST 2013

J. Constr. Eng. Manage., 2013, 139(8): 1063-1067


Conclusions industry and how to apply such lessons to improve project learn-
ing. Moreover, this paper contributed to the profession of con-
The problem of cost control is a complex and sophisticated problem struction engineering and management by identifying industry
associated with so many internal and external factors, such factors practices to be implemented on major projects and to minimize
include government involvement, project execution strategy, corpo- cost overruns.
rate culture, organizational processes, corporate information sys-
tems and tools, and human behaviour. To address this problem
at a project level requires involvement and collaboration from References
the project team and all stakeholders. Therefore, it becomes crucial
for the project team to improve its learning skills on how to deal Alberta Economic Development Authority. (2004). Mega project
with the problem on an individual level, a group level, and an excellence: Preparing for Alberta’s legacy—An action plan, Alberta,
Downloaded from ascelibrary.org by Universidad Peruana De Ciencias Aplicadas on 12/10/19. Copyright ASCE. For personal use only; all rights reserved.

organizational level. Canada.


This research sheds light on the scarce literature in organiza- Gharaibeh, H., and Cow Falls, L. (2011). “Problems and challenges of cost
tional learning in major engineering and construction projects. control in major utility projects in Canada.” Cost Eng. J., 53(5), 14.
Prior to conducting this study, there was limited information Gustafson, D. H., Shukla, R. K., Delbecq, A., and Walster, G. W. (1973).
“A comparison study of differences in subjective likelihood estimates
available on what makes project teams learn from problems re-
made by individuals, interacting groups, Delphi groups and nominal
lated to cost overrun on major projects in Canada. Although we groups.” Organ. Behav. Hum. Performance, 9(2), 280–291.
know the kind of problems normally faced on a project, the fact Rowe, G., and Wright, G. (1999). “The Delphi technique as a forecasting
that we still continue to see cost overruns on these projects in- tool: Issues and analysis.” Int. J. Forecasting, 15(4), 353–375.
dicates a failure to learn lessons. This paper helped to identify Skulmoski, G. J., Hartman, F. T., and Krahn, J. (2007). “The Delphi study
lessons learned from existing projects in the power transmission for graduate research.” J. Inf. Tech. Educ., 6, 1–21.

JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT © ASCE / AUGUST 2013 / 1067

J. Constr. Eng. Manage., 2013, 139(8): 1063-1067

You might also like