Professional Documents
Culture Documents
Structures
•Planning the layout of restraining members
•Structural separation
function of the latter is for limited time which might be two or three months, whereas the
former, which its function is to make rooms for temperature produced movements, should work
and continue its function for the entire life span of the structure.
The space between two regions of the slab is filled and consolidated with non-shrink concrete,
commonly after a period of one to two months. The time required to keep the closure strip open
is dictated by the extent of shortening deemed needed before the two slabs are jointed together.
The continuity between the two slab portions is provided by reinforcement that extended on
each concrete slab side into the closure strips.
The amount of steel reinforcement embedded in the closure strip is computed based on the
bending moment and shear forces at the position of the closure strip; when the whole slab is
considered in continuum.
It is recommended that, stressing ends of tendons, which are stopped in the closure strip, must
be cut, sealed, and grouted and this is applied for corrosion protection purposes. Based on
experience, closure concrete is poured after calculating shortening on each side of the closure
strip which is around 6.35 mm.
The construction joints provide separation for short time between two regions of the slab for
crack control purposes in addition to divide large size slabs into smaller ones to manage
construction easily.
Fig.5: Construction Joint; (A) Without Stressing, (B) With Intermediate Stressing
The construction joints provided in Figure-5 is different from cold joints because not only does
the position of construction joint is specified by designer but also it is employed to control
cracks.
However, cold joints are formed when concrete batch is finished and time interval of three to
seven days usually occurs between first and second concrete placement. Intermediate stressing
is used for long tendons where large stress loss occurs.
One centrally positioned closure strip is provided when slab length is greater than 76 m and
less than 114 m, and for slab length larger than 114 m it is recommended to provide structural
separation.
•Wall joints:
Figure-6 shows various types of wall-slab release for exterior walls and terminating slabs,
nonetheless all types can be used for intermediate slabs and interior walls with some
modifications.
WALL JOINTS
These are vertical joints between adjacent walls by which displacements of slabs and beams
supported by the wall are accommodated.
They are considerably influential in mitigating cracks in beams, slabs, and supported walls as
well. Figure-8 illustrates plan of rectangular slab supported by interior columns and perimeter
walls.
Fig.8: Wall Joints; (A) Plan Showing All Joints and Closure Strips, (B) Plan Showing
Arrangements of Different Wall-Slab Joints
For example, at slab and its supporting walls in which proper release joints to mitigate cracks
cannot be provided because of shear transfer requirements which are specified in the design, as
shown in Figure-9.
Fig.9: Crack Mitigating Reinforcement next to Shear Walls; (A) Interior Shear
Wall. (B) Exterior Shear Wall
It is demonstrated that, placing reinforcement as shown in Figure 10 in slabs parallel to shear
walls over distance of nearly 3m vertical to the wall is substantially effective.
The reinforcement ratio is 0.0015 multiply by slab cross sectional area over one third of the
transverse span. The spacing between bars is 1.5 times the thickness and installed alternately at
the top and bottom.
Fig.10: Reinforcements at the Corner of the Slab