Malaci Slab Analysis Report

This slab analysis and design report provides details for slabs on the first storey of a building project called Malaci. It analyzes 18 slab strips labeled X1 through X9. For each strip it specifies the slab type, loadings, dimensions, moment coefficients, required and supplied steel reinforcement areas. Reinforcement is specified as T12-200 bars with a yield strength of 460 MPa. All strips meet deflection requirements except strip 1S21 which requires further checking.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
93 views5 pages

Malaci Slab Analysis Report

This slab analysis and design report provides details for slabs on the first storey of a building project called Malaci. It analyzes 18 slab strips labeled X1 through X9. For each strip it specifies the slab type, loadings, dimensions, moment coefficients, required and supplied steel reinforcement areas. Reinforcement is specified as T12-200 bars with a yield strength of 460 MPa. All strips meet deflection requirements except strip 1S21 which requires further checking.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Project: Malaci - OkeBen Services (*1LX-CWX8-822F-L6MU)

SLAB ANALYSIS AND DESIGN REPORT Orion Building Design System 18.0 (04.2012) / Page: DSM-1

SLAB ANALYSIS AND DESIGN REPORT

NOTATION:
d/h = Effective/Total Depth of Slab (d=[Link])
g/q = Dead/Live Load (not factored)
L1 = Width of the Slab Along the Strip Direction
L2 = Width of the Slab Perpendicular to the Strip Direction
C = Moment Coefficient M=C p / L^2
M-spn = Ultimate Design Span Moment
M-sup = Ultimate Design Support Moment
Mc = Balanced Support Moment
As = Steel Area (Required/Supplied)

Material: C20/25 / Grade 460 (Type 2)

Slab Strip: X1 -- Storey: 1


---------------------------

TYPE g L1 C-sup C-span As


Slab d/h q L2 M-sup M-span Req/Prov S T E E L B A R S
(mm) (kN/m2) (mm) (kN.m) (kN.m) (mm2)
(mm) (kN/m2) (mm) (kN.m) (kN.m) (mm2)
Support Mc = 0.0Support As = 295.20/565.49 Top:T12-200(T1)

1S1 1 6.300 7500.00 0.0000 0.0000 295.2/565.49


157/200 5.000 3000.00 0.0 0.0 Bottom: T12-200(B2)

Support Mc = 0.0Support As = 295.20/565.49 Top:T12-200(T1)

1S10 1 6.300 7500.00 0.0000 0.0000 295.2/565.49


157/200 5.000 3000.00 0.0 0.0 Bottom: T12-200(B2)

Support Mc = 0.0Support As = 295.20/565.49 Top:T12-200(T1)

Slab Strip: X2 -- Storey: 1


---------------------------

TYPE g L1 C-sup C-span As


Slab d/h q L2 M-sup M-span Req/Prov S T E E L B A R S
(mm) (kN/m2) (mm) (kN.m) (kN.m) (mm2)
(mm) (kN/m2) (mm) (kN.m) (kN.m) (mm2)
Support Mc = 0.5Support As = 295.20/565.49 Top:T12-200(T1)

1S11 1 6.300 5000.00 0.0000 0.0240 295.2/565.49


157/200 5.000 3000.00 0.5 3.6 Bottom: T12-200(B2)

Support Mc = 0.5Support As = 295.20/565.49 Top:T12-200(T1)

Slab Strip: X3 -- Storey: 1


---------------------------

TYPE g L1 C-sup C-span As


Slab d/h q L2 M-sup M-span Req/Prov S T E E L B A R S
(mm) (kN/m2) (mm) (kN.m) (kN.m) (mm2)
(mm) (kN/m2) (mm) (kN.m) (kN.m) (mm2)
Support Mc = 0.0Support As = 295.20/565.49 Top:T12-200(T1)

1S20 1 6.300 7500.00 0.0000 0.0000 295.2/565.49


157/200 5.000 3000.00 0.0 0.0 Bottom: T12-200(B2)

Support Mc = 0.0Support As = 295.20/565.49 Top:T12-200(T1)

Slab Strip: X4 -- Storey: 1


---------------------------

TYPE g L1 C-sup C-span As


Slab d/h q L2 M-sup M-span Req/Prov S T E E L B A R S
(mm) (kN/m2) (mm) (kN.m) (kN.m) (mm2)
(mm) (kN/m2) (mm) (kN.m) (kN.m) (mm2)

Project: Malaci
Project: Malaci - OkeBen Services (*1LX-CWX8-822F-L6MU)
SLAB ANALYSIS AND DESIGN REPORT Orion Building Design System 18.0 (04.2012) / Page: DSM-2

Support Mc = 0.0Support As = 295.20/565.49 Top:T12-200(T1)

1S2 1 6.300 7500.00 0.0000 0.0000 295.2/565.49


157/200 5.000 3000.00 0.0 0.0 Bottom: T12-200(B2)

Support Mc = 0.0Support As = 295.20/565.49 Top:T12-200(T1)

1S9 1 6.300 7500.00 0.0000 0.0000 295.2/565.49


157/200 5.000 3000.00 0.0 0.0 Bottom: T12-200(B2)

Support Mc = 4.8Support As = 295.20/565.49 Top:T12-200(T1)

1S12 1 6.300 5000.00 0.0320 0.0240 295.2/565.49


157/200 5.000 3000.00 4.8 3.6 Bottom: T12-200(B2)

Support Mc = 0.5Support As = 295.20/565.49 Top:T12-200(T1)

Slab Strip: X5 -- Storey: 1


---------------------------

TYPE g L1 C-sup C-span As


Slab d/h q L2 M-sup M-span Req/Prov S T E E L B A R S
(mm) (kN/m2) (mm) (kN.m) (kN.m) (mm2)
(mm) (kN/m2) (mm) (kN.m) (kN.m) (mm2)
Support Mc = 0.0Support As = 295.20/565.49 Top:T12-200(T1)

1S19 1 6.300 7500.00 0.0000 0.0000 295.2/565.49


157/200 5.000 3000.00 0.0 0.0 Bottom: T12-200(B2)

Support Mc = 0.0Support As = 295.20/565.49 Top:T12-200(T1)

Slab Strip: X6 -- Storey: 1


---------------------------

TYPE g L1 C-sup C-span As


Slab d/h q L2 M-sup M-span Req/Prov S T E E L B A R S
(mm) (kN/m2) (mm) (kN.m) (kN.m) (mm2)
(mm) (kN/m2) (mm) (kN.m) (kN.m) (mm2)
Support Mc = 0.0Support As = 295.20/565.49 Top:T12-200(T1)

1S3 1 6.300 7500.00 0.0000 0.0000 295.2/565.49


157/200 5.000 3000.00 0.0 0.0 Bottom: T12-200(B2)

Support Mc = 0.0Support As = 295.20/565.49 Top:T12-200(T1)

1S8 1 6.300 7500.00 0.0000 0.0000 295.2/565.49


157/200 5.000 3000.00 0.0 0.0 Bottom: T12-200(B2)

Support Mc = 0.0Support As = 295.20/565.49 Top:T12-200(T1)

1S13 1 6.300 7500.00 0.0000 0.0000 295.2/565.49


157/200 5.000 3000.00 0.0 0.0 Bottom: T12-200(B2)

Support Mc = 0.0Support As = 295.20/565.49 Top:T12-200(T1)

1S18 1 6.300 7500.00 0.0000 0.0000 295.2/565.49


157/200 5.000 3000.00 0.0 0.0 Bottom: T12-200(B2)

Support Mc = 0.0Support As = 295.20/565.49 Top:T12-200(T1)

Slab Strip: X7 -- Storey: 1


---------------------------

TYPE g L1 C-sup C-span As


Slab d/h q L2 M-sup M-span Req/Prov S T E E L B A R S
(mm) (kN/m2) (mm) (kN.m) (kN.m) (mm2)
(mm) (kN/m2) (mm) (kN.m) (kN.m) (mm2)
Support Mc = 0.0Support As = 295.20/565.49 Top:T12-200(T1)

1S4 1 6.300 7500.00 0.0000 0.0000 295.2/565.49


157/200 5.000 3000.00 0.0 0.0 Bottom: T12-200(B2)

Project: Malaci
Project: Malaci - OkeBen Services (*1LX-CWX8-822F-L6MU)
SLAB ANALYSIS AND DESIGN REPORT Orion Building Design System 18.0 (04.2012) / Page: DSM-3

Support Mc = 0.0Support As = 295.20/565.49 Top:T12-200(T1)

1S7 1 6.300 7500.00 0.0000 0.0000 295.2/565.49


157/200 5.000 3000.00 0.0 0.0 Bottom: T12-200(B2)

Support Mc = 0.0Support As = 295.20/565.49 Top:T12-200(T1)

1S14 1 6.300 7500.00 0.0000 0.0000 295.2/565.49


157/200 5.000 3000.00 0.0 0.0 Bottom: T12-200(B2)

Support Mc = 0.0Support As = 295.20/565.49 Top:T12-200(T1)

1S17 1 6.300 7500.00 0.0000 0.0000 295.2/565.49


157/200 5.000 3000.00 0.0 0.0 Bottom: T12-200(B2)

Support Mc = 0.0Support As = 295.20/565.49 Top:T12-200(T1)

Slab Strip: X8 -- Storey: 1


---------------------------

TYPE g L1 C-sup C-span As


Slab d/h q L2 M-sup M-span Req/Prov S T E E L B A R S
(mm) (kN/m2) (mm) (kN.m) (kN.m) (mm2)
(mm) (kN/m2) (mm) (kN.m) (kN.m) (mm2)
Support Mc = 0.0Support As = 295.20/565.49 Top:T12-200(T1)

1S5 1 6.300 7500.00 0.0000 0.0000 295.2/565.49


157/200 5.000 3000.00 0.0 0.0 Bottom: T12-200(B2)

Support Mc = 0.0Support As = 295.20/565.49 Top:T12-200(T1)

1S6 1 6.300 7500.00 0.0000 0.0000 295.2/565.49


157/200 5.000 3000.00 0.0 0.0 Bottom: T12-200(B2)

Support Mc = 0.0Support As = 295.20/565.49 Top:T12-200(T1)

1S15 1 6.300 7500.00 0.0000 0.0000 295.2/565.49


157/200 5.000 3000.00 0.0 0.0 Bottom: T12-200(B2)

Support Mc = 0.0Support As = 295.20/565.49 Top:T12-200(T1)

1S16 1 6.300 7500.00 0.0000 0.0000 295.2/565.49


157/200 5.000 3000.00 0.0 0.0 Bottom: T12-200(B2)

Support Mc = 0.0Support As = 295.20/565.49 Top:T12-200(T1)

Slab Strip: X9 -- Storey: 1


---------------------------

TYPE g L1 C-sup C-span As


Slab d/h q L2 M-sup M-span Req/Prov S T E E L B A R S
(mm) (kN/m2) (mm) (kN.m) (kN.m) (mm2)
(mm) (kN/m2) (mm) (kN.m) (kN.m) (mm2)
Support Mc = 2.0Support As = 295.20/565.49 Top:T12-200(T1)

1S1 1 6.300 3000.00 0.0860 0.0860 295.2/565.49


169/200 5.000 7500.00 13.0 13.0 Bottom: T12-200(B1)
Deflection Check: L/d = 17.75 < 52.0 *** Sufficient ***

Support Mc = 11.9Support As = 295.20/565.49 Top:T12-200(T1)

1S2 1 6.300 3000.00 0.0630 0.0630 295.2/565.49


169/200 5.000 7500.00 9.5 9.5 Bottom: T12-200(B1)
Deflection Check: L/d = 17.75 < 52.0 *** Sufficient ***

Support Mc = 9.5Support As = 295.20/565.49 Top:T12-200(T1)

1S3 1 6.300 3000.00 0.0630 0.0630 295.2/565.49


169/200 5.000 7500.00 9.5 9.5 Bottom: T12-200(B1)
Deflection Check: L/d = 17.75 < 52.0 *** Sufficient ***

Support Mc = 9.5Support As = 295.20/565.49 Top:T12-200(T1)

Project: Malaci
Project: Malaci - OkeBen Services (*1LX-CWX8-822F-L6MU)
SLAB ANALYSIS AND DESIGN REPORT Orion Building Design System 18.0 (04.2012) / Page: DSM-4

1S4 1 6.300 3000.00 0.0630 0.0630 295.2/565.49


169/200 5.000 7500.00 9.5 9.5 Bottom: T12-200(B1)
Deflection Check: L/d = 17.75 < 52.0 *** Sufficient ***

Support Mc = 11.9Support As = 295.20/565.49 Top:T12-200(T1)

1S5 1 6.300 3000.00 0.0860 0.0860 295.2/565.49


169/200 5.000 7500.00 13.0 13.0 Bottom: T12-200(B1)
Deflection Check: L/d = 17.75 < 52.0 *** Sufficient ***

Support Mc = 2.0Support As = 295.20/565.49 Top:T12-200(T1)

Slab Strip: X10 -- Storey: 1


----------------------------

TYPE g L1 C-sup C-span As


Slab d/h q L2 M-sup M-span Req/Prov S T E E L B A R S
(mm) (kN/m2) (mm) (kN.m) (kN.m) (mm2)
(mm) (kN/m2) (mm) (kN.m) (kN.m) (mm2)
Support Mc = 2.0Support As = 295.20/565.49 Top:T12-200(T1)

1S10 1 6.300 3000.00 0.0860 0.0860 295.2/565.49


169/200 5.000 7500.00 13.0 13.0 Bottom: T12-200(B1)
Deflection Check: L/d = 17.75 < 52.0 *** Sufficient ***

Support Mc = 11.9Support As = 295.20/565.49 Top:T12-200(T1)

1S9 1 6.300 3000.00 0.0630 0.0630 295.2/565.49


169/200 5.000 7500.00 9.5 9.5 Bottom: T12-200(B1)
Deflection Check: L/d = 17.75 < 52.0 *** Sufficient ***

Support Mc = 9.5Support As = 295.20/565.49 Top:T12-200(T1)

1S8 1 6.300 3000.00 0.0630 0.0630 295.2/565.49


169/200 5.000 7500.00 9.5 9.5 Bottom: T12-200(B1)
Deflection Check: L/d = 17.75 < 52.0 *** Sufficient ***

Support Mc = 9.5Support As = 295.20/565.49 Top:T12-200(T1)

1S7 1 6.300 3000.00 0.0630 0.0630 295.2/565.49


169/200 5.000 7500.00 9.5 9.5 Bottom: T12-200(B1)
Deflection Check: L/d = 17.75 < 52.0 *** Sufficient ***

Support Mc = 11.9Support As = 295.20/565.49 Top:T12-200(T1)

1S6 1 6.300 3000.00 0.0860 0.0860 295.2/565.49


169/200 5.000 7500.00 13.0 13.0 Bottom: T12-200(B1)
Deflection Check: L/d = 17.75 < 52.0 *** Sufficient ***

Support Mc = 2.0Support As = 295.20/565.49 Top:T12-200(T1)

Slab Strip: X11 -- Storey: 1


----------------------------

TYPE g L1 C-sup C-span As


Slab d/h q L2 M-sup M-span Req/Prov S T E E L B A R S
(mm) (kN/m2) (mm) (kN.m) (kN.m) (mm2)
(mm) (kN/m2) (mm) (kN.m) (kN.m) (mm2)
Support Mc = 1.0Support As = 295.20/565.49 Top:T12-200(T1)

1S11 1 6.300 3000.00 0.0570 0.0427 295.2/565.49


169/200 5.000 5000.00 8.6 6.5 Bottom: T12-200(B1)
Deflection Check: L/d = 17.75 < 52.0 *** Sufficient ***

Support Mc = 8.6Support As = 295.20/565.49 Top:T12-200(T1)

1S12 1 6.300 3000.00 0.0570 0.0427 295.2/565.49


169/200 5.000 5000.00 8.6 6.5 Bottom: T12-200(B1)
Deflection Check: L/d = 17.75 < 52.0 *** Sufficient ***

Support Mc = 9.5Support As = 295.20/565.49 Top:T12-200(T1)

1S13 1 6.300 3000.00 0.0630 0.0630 295.2/565.49

Project: Malaci
Project: Malaci - OkeBen Services (*1LX-CWX8-822F-L6MU)
SLAB ANALYSIS AND DESIGN REPORT Orion Building Design System 18.0 (04.2012) / Page: DSM-5

169/200 5.000 7500.00 9.5 9.5 Bottom: T12-200(B1)


Deflection Check: L/d = 17.75 < 52.0 *** Sufficient ***

Support Mc = 9.5Support As = 295.20/565.49 Top:T12-200(T1)

1S14 1 6.300 3000.00 0.0630 0.0630 295.2/565.49


169/200 5.000 7500.00 9.5 9.5 Bottom: T12-200(B1)
Deflection Check: L/d = 17.75 < 52.0 *** Sufficient ***

Support Mc = 11.9Support As = 295.20/565.49 Top:T12-200(T1)

1S15 1 6.300 3000.00 0.0860 0.0860 295.2/565.49


169/200 5.000 7500.00 13.0 13.0 Bottom: T12-200(B1)
Deflection Check: L/d = 17.75 < 52.0 *** Sufficient ***

Support Mc = 2.0Support As = 295.20/565.49 Top:T12-200(T1)

Slab Strip: X12 -- Storey: 1


----------------------------

TYPE g L1 C-sup C-span As


Slab d/h q L2 M-sup M-span Req/Prov S T E E L B A R S
(mm) (kN/m2) (mm) (kN.m) (kN.m) (mm2)
(mm) (kN/m2) (mm) (kN.m) (kN.m) (mm2)
Support Mc = 2.0Support As = 295.20/565.49 Top:T12-200(T1)

1S20 1 6.300 3000.00 0.0860 0.0860 295.2/565.49


169/200 5.000 7500.00 13.0 13.0 Bottom: T12-200(B1)
Deflection Check: L/d = 17.75 < 52.0 *** Sufficient ***

Support Mc = 11.9Support As = 295.20/565.49 Top:T12-200(T1)

1S19 1 6.300 3000.00 0.0630 0.0630 295.2/565.49


169/200 5.000 7500.00 9.5 9.5 Bottom: T12-200(B1)
Deflection Check: L/d = 17.75 < 52.0 *** Sufficient ***

Support Mc = 9.5Support As = 295.20/565.49 Top:T12-200(T1)

1S18 1 6.300 3000.00 0.0630 0.0630 295.2/565.49


169/200 5.000 7500.00 9.5 9.5 Bottom: T12-200(B1)
Deflection Check: L/d = 17.75 < 52.0 *** Sufficient ***

Support Mc = 9.5Support As = 295.20/565.49 Top:T12-200(T1)

1S17 1 6.300 3000.00 0.0630 0.0630 295.2/565.49


169/200 5.000 7500.00 9.5 9.5 Bottom: T12-200(B1)
Deflection Check: L/d = 17.75 < 52.0 *** Sufficient ***

Support Mc = 11.9Support As = 295.20/565.49 Top:T12-200(T1)

1S16 1 6.300 3000.00 0.0860 0.0860 295.2/565.49


169/200 5.000 7500.00 13.0 13.0 Bottom: T12-200(B1)
Deflection Check: L/d = 17.75 < 52.0 *** Sufficient ***

Support Mc = 2.0Support As = 295.20/565.49 Top:T12-200(T1)

Project: Malaci