Eid Gah F.F.L +0 mm (7.9 M topo)

Pavillion F.F.L -800 mm (7.1 M topo)

450
Slope 1:2
Pond edge
for plantation
100 water over flow drain level -1350 mm (6.5 M topo)

water level -1700 mm (6.2 M topo)

Slope 1:1 300 x 300 x 100 block layer with soil medium

Geo textile/ fabric for shore protection

100
450 Toe wall pond bottom -4900 mm (3.0 M topo)

POND SECTION Blow up

GOVERNMENT OF THE PEOPLES REPUBLIC OF BANGLADESH IMPROVEMENT of AKUIN CHARPARA GRAVEYARD & Ar. Manifa Rehnuma
EID-GAON
LOCAL GOVERNMENT ENGINEERING DEPARTMENT
UNDER SADAR UPAZILA, DIST:FARIDPUR. A K M Tanvir Hassan PROJECT DIRECTOR GSIDP/GRAVE/FAR/
GSIDP Manifa Rehnuma ENGR. MD. HAFIZUR RAHMAN EXECUTIVE ENGINEER, FARIDPUR. GSIDP, LGED. DATE: March, 2019 Decription SAD/AQN./ ARCH 14.4