Given:-
Width of column-b 300 mm
Depth of the column-D 570 mm
fck 20 n/mm^2
fy 415 n/mm^2
Ultimate load transfered from the column at base-Pu 300 kn
Ultimate moment bisecting the depth of col.at col.base-Mux 192.5 kn-m
SBC-fb 400 kn/m^2
Design:-
Working load transfered from col.to the base-P 200 kn
Proportioning of base size:-
Area of footing reqd.-Af 0.55 m^2
e 0.64166667 m
Pedestal size:-
offset 100 mm
Width 500 mm
Depth 770 mm
Height 300 mm
Area of pedestal-Ap 0.385 m^2
q 0.51948052 n/mm^2
tan α (reqd.) 1.7070138
tan α (provided) 3
safe
Width of footing-Bf 500 mm
Length of footing reqd.-Lf 1.1 m
Min. Length of footing to effect uniform pressure distribution 2053.33333 mm
Provided Lf 2250 mm
Depth of footing from bending moment consideration:-
Provided area of footing- Af 1.125 m^2
ok
factored
column
pedestal
α
Pedestal size
Bf
b1 b2
Lf1 Lf2
Lf1 2.7326899 m
Provided Lf1 2.75 m
Lf2 2.4880952 m
Provided Lf2 2.5 m
Area provided-Af 11.025 m²
Total ultimate load from columns 3000 Kn
Upward intensity of soil pressure -Pu/Af 272.109 Kn/m²
(b) Design of footing slab
max. Width of column 500 mm
Let the width of strap beam- b 500 mm
Cantilever projection of slab beyond beam 0.8 m
Consider 1m width of slab 1000 mm
Max. Ultimate moment 87.07483 Kn-m
Required-d1 177.61996 mm
Provided depth-d1 330 mm
d2 200 mm
d1
d2
b1 b2
Lf1 Lf2
C D E F G H J
0.4
x 2m
L=Lf1+Lf2 5.2380952 m
a -0.5
b 5.2
c -10.47619
2.4673101
2.7326899
7.6673101
Not factored
Not factored
% steel tuc-M20
0.15 0.28
0.25 0.35
0.5 0.46
0.75 0.54
1 0.6
For drawing 1.25 0.64
1.5 0.68
1.75 0.71
2 0.71
2.25 0.71
2.5 0.71
2.75 0.71
3 0.71
For drawing
For drawing
< OK
Tension at top
For drawing
20 mm dia at top
20 mm dia at bottom
N/mm²
Bf
b1 b2
Lf1 Lf2
Lf1 2.7054278 m
Provided Lf1 2.75 m
Lf2 2.4880952 m
Provided Lf2 2.5 m
Area provided-Af 11.025 m²
Total ultimate load from columns 3000 Kn
Upward intensity of soil pressure -Pu/Af 272.109 Kn/m²
(b) Design of footing slab
max. Width of column 375 mm
Let the width of strap beam- b 375 mm
Cantilever projection of slab beyond beam 0.8625 m
Consider 1m width of slab 1000 mm
Max. Ultimate moment 101.21173 Kn-m
Required-d1 191.49652 mm
Provided depth-d1 330 mm
d2 200 mm
d1
d2
col-A col-B
Bf
b1 b2
Lf1 Lf2
1.0625
C D E F G H J
0.45
x 2m
L=Lf1+Lf2 5.2380952 m
a -0.5
b 5.225
c -10.47619
2.5195722
2.7054278
7.7445722
Not factored
Not factored
For drawing
% steel tuc-M20
0.15 0.28
0.25 0.35
0.5 0.46
0.75 0.54
1 0.6
1.25 0.64
For drawing 1.5 0.68
1.75 0.71
2 0.71
2.25 0.71
2.5 0.71
2.75 0.71
3 0.71
Tension at top
For drawing
20 mm dia at top
20 mm dia at bottom
N/mm²